Tender Value
₹5.2 L
EMD Value
₹10,320
Closing Date
7 Sept 2026, 3:30 pm
EXECUTIVE ENGINEER
EXECUTIVE ENGINEER TESTING DIVISION SHUJALPUR
NIT for Complete Erection for construction work for 01 No.132 KV Bus Coupler Bay with construction of 04 Nos. 132KV Auxiliary Bus at 132 KV Substation Moman Badodiya under Testing Division Shujalpur
2026_MPPTC_528782_1
TS-01/2026-27/204 Date 11.08.2026
Open Tender
Miscellaneous Services
Percentage
120 days
132KV Substation Moman Badodiya
As per NIT Documents
7 documents required · 7 mandatory
₹590
₹10,320
Yes
11 Aug 2026
11 Aug 2026
8 Sept 2026
12 Aug 2026
7 Sept 2026
12 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Circuit Breaker 3 -phase (Shifting of breaker up to the place & placement of all 3 circuit breaker poles on structures including shifting within S/s premises. Complete assembly of circuit breaker including erection of control cabinet & mechanism box interconnecting piping works, erection of all accessories of the equipments and making interconnections) | 1 | No. | 19,800 | ₹19,800 |
| 2 | 132KV CT ( Shifting & placement on structure including fixing of junction box & all accessories, making all interconnections) | 3 | Nos. | 7,920 | ₹23,760 |
| 3 | Isolator without/with E/S motarised (Placement of complete isolator in all 3 phase of isolator structure, including shifting within S/s premises. Erection / mounting of mechanism box, interconnection, piping, alignment of contacts & all associated activities) | 10 | No. | 19,800 | ₹1,98,000 |
| 4 | Post/Solid core Insulator ( Shifting & placement of Post/Solid core Insulator equipment on structure including all accessories, making all interconnections,checking installation of insulator base.) | 9 | Nos. | 1,584 | ₹14,256 |
| 5 | C&R Panel ( Unloading of control & relay panel and placement of panel complete with all relays and their accessories. Making of all connections for the control and relay panel on terminal block as per drawing including all AC & DC connection) | 1 | Nos. | 10,560 | ₹10,560 |
| 6 | 132KV STRUCTURES :- Total Weight (in MT) ( Erection for structures including fixing & alignment of templates for grouted/bolted type structure foundations, tightening and punching of nuts, bolts, washers etc & including alignment & leveling of structure) | 5.13 | No. | 8,380 | ₹42,955.88 |
| 7 | BUSBAR, EARTHING WORK :- Stringing by Twin zebra conductor ( Stringing of overhead gantries, vertical droppers with ACSR conductor including fixing of insulator string, spacers, clamps etc. | 100 | MT | 139 | ₹13,900 |
| 8 | BUSBAR, EARTHING WORK :- Stringing by Single zebra conductor ( Stringing of overhead gantries, vertical droppers with ACSR conductor including fixing of insulator string, spacers, clamps etc. | 600 | Mtrs | 72 | ₹43,200 |
| 9 | Provided of steel risers and making earth mat (duly buried at a depth of 0.5 Mtrs) including back filling, welding etc. And bolting of risers to the structures/ equipments at desired places. M. S. Flat for earthing ( 65 X 8 ) | 132 | Mtrs | 86 | ₹11,352 |
| 10 | Provided of steel risers and making earth mat (duly buried at a depth of 0.5 Mtrs) including back filling, welding etc. And bolting of risers to the structures/ equipments at desired places. M. S. Flat for earthing ( 50 X 6 ) | 120 | Mtrs | 66 | ₹7,920 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.61 MB
TENDERDOCUMENT.pdf
Tender Documents • 0.96 MB
BOQ_636446.xls
BOQ • 0.55 MB
NIT.pdf
Additional Documents • 0.60 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].