| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.1 LAccepted-AOC | 1 | Accepted-AOC Lowest | |
| 2 | 2₹1.2 L+₹2,936.60 (2.60%)Rejected-AOC | 2 | Rejected-AOC 2nd |
Tender Value
₹1.3 L
EMD Value
₹3,178
Closing Date
23 Dec 2024, 6:00 pmClosed
Anilkumar cholakkat
Office of the Assistant Engineer,LID EW Section, Puzhakkattiri GP
Annual Plan-Project No.26/2024-25-Construction of Motor shed for Chovvana GLP School General Civil Work
2024_LSGD_714941_3
AE/LIDEW/PKTY/04/2024-25
Open Tender
Civil Works - Buildings
Item Rate
335 days
Chovvana
Please refer Tender documents.
10 documents required · 10 mandatory
₹555
Yes
₹3,178
Yes
1 Apr 2025
16 Dec 2024
27 Dec 2024
16 Dec 2024
23 Dec 2024
16 Dec 2024
Amount
Motor shed
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
OD270475/2024-2025:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
50.6.1.7:Solid block masonry using pre cast solid blocks ( Factory made) of size 40x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 15 cm in : CM 1:6 ( 1 cement : 6 coarse sand ) etc complete
50.6.1.8:Solid block masonry using pre cast solid blocks (Factory made) of size 40x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level with thickness 15cm in: CM 1:6 ( 1 cement : 6 coarse sand etc complete
50.6.3.1:Solid block masonry using pre cast solid blocks ( Factory made) of size 40x20x10cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth for 10 cm thick wall in CM 1:6 ( 1 cement : 6 coarse sand) including cost of scaffolding etc complete
5.3:Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 150 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for: Edges of slabs and breaks in floors and wallsUnder 20 cm wide
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
OD235250/2024-2025:Providing and fixing 1 mm thick steel door and window including frame using MS angle , Flat and M.S. sheet, all necessary fittings complete, including applying a priming coat of approved steel primer, all materials and labour charges etc. complete.
10.25.2:Item Shifted to Sub head 14 as item 14.73 Item Shifted to head 14 as item 14.74 Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
13.4.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 coarse sand)
13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
13.43.1:Applying one coat of water thinnable cement primer of approved brand and manufacture on wall surface:Water thinnable cement primer
13.60.1:Wall painting with acrylic emulsion paint of approved brand and manufacture to give an even shade:Two or more coats on new work
13.61.1:Painting with synthetic enamel paint of approved brand and manufacture to give an even shade:Two or more coats on new work
DEVANANDAN (BID ID -2030430)
Bidder Name
SABIBUDHEEN
DEVANANDAN
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .