| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.1 LAccepted-AOC | L1 | Accepted-AOC The Lowest Bidder | |
| 2 | L2₹11.1 L+₹8,574.63 (0.78%)Rejected-AOC KAVANUR GRAMA PANCHAYAT | TIRUVANNAMALAI | TAMIL NADU | 604401 | L2 | Rejected-AOC The Second Lowest Bidder | |
| 3 | L3₹11.3 L+₹26,425.37 (2.39%)Rejected-AOC | L3 | Rejected-AOC The Third Lowest Bidder |
Tender Value
₹12.0 L
EMD Value
₹30,000
Closing Date
1 Oct 2020, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Sadasivan E
Assistant Executive Engineer, MI Sub Division, Parappanangadi
SDRF Repair works to Canal of Lift Irrigation Scheme,Vazhakkad , chainage 3100m to 4000m
2020_Irrig_386632_1
AEE(PGDI)/ET/19/2020-21
Open Tender
Civil Works - Others
Item Rate
120 days
Vazhakkad
Please refer Tender documents.
3 documents required · 3 mandatory
₹3,149
Yes
online
₹30,000
Yes
22 Mar 2021
21 Sept 2020
6 Oct 2020
21 Sept 2020
1 Oct 2020
21 Sept 2020
21 Sept 2020 - 1 Oct 2020
60 days
Amount
Scheme 1, Repair of canal chainage 3100 m to 3200
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
60.2.1 : EARTH WORK FILLING- Supplying contractors own earth including cost of conveyance and royalty and filling (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Scheme 2,Repair of canal chainage 3200 m to 3300m
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
60.2.1 : EARTH WORK FILLING- Supplying contractors own earth including cost of conveyance and royalty and filling (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Scheme 3,Repair of canal chainage 3300m to 3400m
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
60.2.1 : EARTH WORK FILLING- Supplying contractors own earth including cost of conveyance and royalty and filling (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Scheme 4, Repair works to canal chainage 3400m to 3500m
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
60.2.1 : EARTH WORK FILLING- Supplying contractors own earth including cost of conveyance and royalty and filling (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Scheme 5, Repair works to canal chainage 3500m to 3600m
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
60.2.1 : EARTH WORK FILLING- Supplying contractors own earth including cost of conveyance and royalty and filling (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Scheme 6, Repair works to 3600m to 3700m
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
60.2.1 : EARTH WORK FILLING- Supplying contractors own earth including cost of conveyance and royalty and filling (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Scheme 7, Repair works to canal chainage 3700m to 3800m
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
60.2.1 : EARTH WORK FILLING- Supplying contractors own earth including cost of conveyance and royalty and filling (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Scheme 8, Repair works to canal chainage 3800m to 3900m.
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
60.2.1 : EARTH WORK FILLING- Supplying contractors own earth including cost of conveyance and royalty and filling (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
Scheme 9, Repair works to canal chainage 3900m to 4000m
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.9.2 : Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
60.2.1 : EARTH WORK FILLING- Supplying contractors own earth including cost of conveyance and royalty and filling (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
ALAVIKUTTY M
Beerankutty
Bidder Name
P. ANVAR SADATH
ALAVIKUTTY M
Beerankutty
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.PDF
finance_549244.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .