| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹29.7 LAccepted-AOC | L1 | Accepted-AOC Lowest bidder | |
| 2 | L2₹32.7 L+₹3.0 L (10.0%)Rejected-AOC | L2 | Rejected-AOC Other than lowest bidder | |
| 3 | L3₹54.5 L+₹24.8 L (83.3%)Rejected-AOC | L3 | Rejected-AOC Other than lowest bidder | |
| 4 | Rejected-Technical | - | Rejected-Technical Requisite docus and Earnest money |
Tender Value
₹44 L
EMD Value
₹88,000
Closing Date
13 Jan 2020, 6:00 pmClosed
CWE Jammu
HQ CWE Jammu PIN-900172 C/o-56APO
MANNING AND OPERATION THROUGH OUTSOURCING OF ELECTRICAL INSTALLATIONS FOR MAIN RECEIVING STATION 11 KV AND 33 KV AT PEERU VIHAR, OFFRS MESS AND TRANSIT OFFICER MESS UNDER GE SATWARI
2019_MES_306568_1
CANO-CWE/JP-43/2019-20
Open Tender
Miscellaneous Services
Item Rate
335 days
AOR OF GE Satwari
Class D Category d(v)
9 documents required · 9 mandatory
₹500
GE Satwari
₹88,000
Yes
24 Apr 2020
14 Dec 2019
15 Jan 2020
14 Dec 2019
13 Jan 2020
27 Dec 2019
Amount
Maintenace and operation of HT 33 KV installation around the clock in three shifts per day of eight hours each by employing 3 Skilled (electrician) and 3 Unskilled (helpers) [i.e, one Skilled (electrician) and one Unskilled (helper) per shift] contineous all as per the directions of Engr in charge (it will be ensured that the helper and operator must remain on duty per shift and at the time of change of shift). The contractor shall employ qualified electrician having ITI from the recognised institution with minimun 5 years experience or in case without ITI, having 7 years experience in related field in operation of following HT 33/11 KV system:- (MAINTENANCE AND OPERATION OF MRS 33 KV NEAR 26 IDSR OFFICER MESS).
33/11 KV POWER TRANSFORMER MAKE:-CONTINETAL TRANSFORMER -01 NO
(TRANSFORMER CR PANEL MAKE :- POWER CONTROL SYSTEMS -01 NO
33 KV VCB MAKE:- ALIND SWITCH GEAR - 01 NO
33 KV CURRENT TRANSFORMER MAKE :- CROMPTON GREAVES LTD - 01SET/03NOS
33 KV POTENTIAL TRANSFORMER MAKE :- CROMPTON GREAVES LTD - 01SET/03NOS
TRANSFORMER ISOLATOR - 01 SET
OUTGOING STRUCTURES & 11 KV CABLES - 04 NOS
33 KV LIGHTENING ARRESTOR - 01 SET
11 KV SWITCHGEAR MAKE - ALIND INDUSTRIES 1+4 SET
AC BOARD MAKE :- POWER CONTROL SYSTEMS - 01 NOS
DC BOARD MAKE :- POWER CONTROL SYSTEMS- 01NOS
BATTERY CHARGER MAKE :- POWER CONTROL SYSTEMS - 01 NOS
BATTERY BANK MAKE:- TITANIC - 18CELL 2V EACH
AUXILIARY TRANSFORMER MAKE :- NATIONAL CABLES (INDIA) - 01 NOS
Note :- (i) The contractor shall employ 03 electrician and 03 helpers i.e., one electrician and one helper per shift of eight hours.
(ii) The cost of maintenance of document, installation chart, daily records i.e., log sheet as clarified under relevant PS shall deemed to be included in rates quoted for the above items.
(iii) Any breakdown/fault of electric supply will be attended by the tradesman employed by the contractor. All tools and T&P required by tradesman will be provided by the contractor (Such as bamboo ladder, tourch, search light, Axe, Dha, HT Gloves and other T&P required for working in HT/LT line/under ground cable).
(iv) Contractor shall replace blown out fuse wire, HT Jumper and lead as and when required. The aspect shall be deemed to be included in the quoted rates and nothing extra shall be admissible on this account.
(v) All the complaints lodge in the substation of external electric supply and internal electrical supply will be attended by contractor and will keep record of complaint slip attended.
(vi) Electrician shall attend the telephone while on duty and will keep the record of complaints.
(vii) The recovery @ Rs 2200/- per shift shall be made from contractor in case of non availibility of operator/helper on plant/ any breakdown/ failure of electric supply.
(viii) Proper shutdown will be taken by the electrician while attending fault/rewiring fuse element on DO fuse assy at MRS, Sub Station and GOD on two/Four poles structure as directed by Engineer-in-Charge.
(ix) All the shifts shall also be monitored properly by the contractor to avoid any delay in attending faults occurred at MRS.
(x) The contractor will be fully responsible for safety, security of the worker and upkeep of installations.
(xi) The contractor is also generally responsible for cleanliness of equipments inside the sub station complex and cleaning/cutting of grass at the surrounding areas of sub station and MRS.
(xii) the contractor will also be responsible to attend complaints of internal electrification nature.
(xiii) Emergency light will be provided by the contractor during night hours without any extra cost.
Maintenace and operation of HT 11 KV installation around the clock in three shifts per day of eight hours each by employing 3 Skilled (electrician) and 3 Unskilled (helpers) [i.e, one Skilled (electrician) and one Unskilled (helper) per shift] contineous all as per the directions of Engr in charge (it will be ensured that the helper and operator must remain on duty per shift and at the time of change of shift). The contractor shall employ qualified electrician having ITI from the recognised institution with minimun 5 years experience or in case without ITI, having 7 years experience in related field in operation of following HT 11 KV system:-(MAINTENANCE AND OPERATION OF MRS 11 KV AT 213 TRANSIT CAMP OFFRS MESS).
HT 11 KV Panel VCBSF-6 (Incommer)-01 No Make - ABB
HT 11 KV Panel VCBSF-6 (Outgoing)-03 No Make - ABB
GOD HT 60 Nos
LT/HT UG cable of different sizes 20 KMs
Transformers 25 Nos
Note :- (i) The contractor shall employ 03 electrician and 03 helpers i.e., one electrician and one helper per shift of eight hours.
(ii) The cost of maintenance of document, installation chart, daily records i.e., log sheet as clarified under relevant PS shall deemed to be included in rates quoted for the above items.
(iii) Any breakdown/fault of electric supply will be attended by the tradesman employed by the contractor. All tools and T&P required by tradesman will be provided by the contractor (Such as bamboo ladder, tourch, search light, Axe, Dha, HT Gloves and other T&P required for working in HT/LT line/under ground cable).
(iv) Contractor shall replace blown out fuse wire, HT Jumper and lead as and when required. The aspect shall be deemed to be included in the quoted rates and nothing extra shall be admissible on this account.
(v) All the complaints lodge in the substation of external electric supply and internal electrical supply will be attended by contractor and will keep record of complaint slip attended.
(vi) Electrician shall attend the telephone while on duty and will keep the record of complaints.
(vii) The recovery @ Rs 2200/- per shift shall be made from contractor in case of non availibility of operator/helper on plant/ any breakdown/ failure of electric supply.
(viii) Proper shutdown will be taken by the electrician while attending fault/rewiring fuse element on DO fuse assy at MRS, Sub Station and GOD on two/Four poles structure as directed by Engineer-in-Charge.
(ix) All the shifts shall also be monitored properlly by the contractor to avoid any delay in attending faults occurred at MRS.
(x) The contractor will be fully responsible for safety, security of the worker and upkeep of installations.
(xi) The contractor is also generally responsible for cleanliness of equipments inside the sub station complex and cleaning/cutting of grass at the surrounding areas of sub station and MRS.
(xii) the contractor will also be responsible to attend complaints of internal electrification nature.
(xiii) Emergency light will be provided by the contractor during night hours without any extra cost.
Maintenace and operation of HT 11 KV installation around the clock in three shifts per day of eight hours each by employing 3 Skilled (electrician) and 3 Unskilled (helpers) [i.e, one Skilled (electrician) and one Unskilled (helper) per shift] contineous all as per the directions of Engr in charge (it will be ensured that the helper and operator must remain on duty per shift and at the time of change of shift). The contractor shall employ qualified electrician having ITI from the recognised institution with minimun 5 years experience or in case without ITI, having 7 years experience in related field in operation of following HT 11 KV system:- (MAINTENANCE AND OPERATION OF MRS 11 KV AT PEERU VIHAR).
HT 11 KV Panel VCBSF-6 (Incommer)-01 No Make - ABB
HT 11 KV Panel VCBSF-6 (Outgoing)-03 No Make - ABB
GOD HT 60 Nos
LT/HT UG cable of different sizes 20 KMs
Transformers 25 Nos
Note :- (i) The contractor shall employ 03 electrician and 03 helpers i.e., one electrician and one helper per shift of eight hours.
(ii) The cost of maintenance of document, installation chart, daily records i.e., log sheet as clarified under relevant PS shall deemed to be included in rates quoted for the above items.
(iii) Any breakdown/fault of electric supply will be attended by the tradesman employed by the contractor. All tools and T&P required by tradesman will be provided by the contractor (Such as bamboo ladder, tourch, search light, Axe, Dha, HT Gloves and other T&P required for working in HT/LT line/under ground cable).
(iv) Contractor shall replace blown out fuse wire, HT Jumper and lead as and when required. The aspect shall be deemed to be included in the quoted rates and nothing extra shall be admissible on this account.
(v) All the complaints lodge in the substation of external electric supply and internal electrical supply will be attended by contractor and will keep record of complaint slip attended.
(vi) Electrician shall attend the telephone while on duty and will keep the record of complaints.
(vii) The recovery @ Rs 2200/- per shift shall be made from contractor in case of non availibility of operator/helper on plant/ any breakdown/ failure of electric supply.
(viii) Proper shutdown will be taken by the electrician while attending fault/rewiring fuse element on DO fuse assy at MRS, Sub Station and GOD on two/Four poles structure as directed by Engineer-in-Charge.
(ix) All the shifts shall also be monitored properlly by the contractor to avoid any delay in attending faults occurred at MRS.
(x) The contractor will be fully responsible for safety, security of the worker and upkeep of installations.
(xi) The contractor is also generally responsible for cleanliness of equipments inside the sub station complex and cleaning/cutting of grass at the surrounding areas of sub station and MRS.
(xii) the contractor will also be responsible to attend complaints of internal electrification nature.
(xiii) Emergency light will be provided by the contractor during night hours without any extra cost.
Vishesh Engineers
BMMJ TRADERS AND ENGINEERS
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .