Loading…
Loading…
Tender Value
₹73.0 L
EMD Value
₹1.5 L
Closing Date
24 Jul 2026, 3:00 pm
(A) Electrical General work in connection with Engg. Work "At BLGT: -Construction of Type II (12 UNIT) Staff Quarters and related Ancillary Work etc. at Balurghat (Phase-I)". (B) Electrical General work in connection with Engg. Work "At BLGT: - Construction of Type II (12 UNIT) Staff Quarters and related Ancillary Work etc. at Balurghat (Phase-II)".
41_2026
41_2026
Open
6 Months
Dinajpur Dakshin, West Bengal
₹0
₹1.5 L
2 Jul 2026
2 Jul 2026
10 Jul 2026
Ancillary Work etc. at Balurghat (Phase-II))
Item- 1 PART-A (General Items)
S No. Item Description of Item Unit Qty Rate Amount
1 1 Supply, wiring, testing & commissioning of Numbers 48.00 797.00 38256.00
concealed point wiring by FR PVC insulated and
unsheathed 1.5 sq mm, single core multi strand
copper wire with earth continuity wire by PVC
insulated and unsheathed 1 sq mm , single core
multi strand copper wire concealed on wall
through PVC rigid conduit pipe of dia not less
than 20 mm dia heavy duty including all types
of joints and bends as required, complete with 6
amps flush type controlling modular switch to be
mounted on modular GI inner plate and modular
mounting frame of suitable module as per
requirement complete to be concealed in wall as
per instruction of Engineer Incharge at site.
Existing wall should be cut and re-mended to
original finish by contractor's own material. a) FL
Point/LED Tube Point with c/rose
2 2 b) LED Mirror Light Point with c/rose Numbers 12.00 797.00 9564.00
4 4 d) Fan point with c/rose and 5 step fan regulator Numbers 36.00 1450.00 52200.00
6 6 f) Plug point 6 amps on board complete Numbers 108.00 361.00 38988.00
7 7 Supply, wiring, testing & commissioning of Numbers 108.00 855.00 92340.00
concealed 6/16 amps power plug point on
separate board complete with modular 16 amps
switch (with indicator) and 6/16 amps 3 pin
combined shuttered socket to be mounted on
modular GI inner plate 4M or suitable size with
modular mounting frame to be concealed in wall
as per instruction of Engineer Incharge at Site.
KATIHAR DIVISION-ELECTRICAL/N F RLY
8 8 Supply, wiring, testing & commissioning of Numbers 12.00 395.00 4740.00
concealed call bell point wiring by FR-LSH PVC
insulated and unsheathed 1.5 sq mm, single
core flexible copper wire concealed on wall
through PVC rigid conduit pipe of dia not less
than 20 mm dia with all types of joints and
bends as required complete with 6 amps bell
push controlling switch fitted on half flush MS
board with hylem sheet top and earth continuity
wire by PVC insulated and unsheathed 1 sq mm
, single core multi strand copper wire complete
to be concealed in wall including supply, fixing,
testing & commissioning of call bell "Ding Dong /
Multitune door bell" type.
9 9 Supply, fixing, connection & testing of indoor Numbers 48.00 987.00 47376.00
LED tube batten with 20 watt LED T8 tubular
lamp with extuded aluminium body and PC
diffuser complete with inbuilt driver (System
wattage-20 Watt, System efficacy> 120 lm/W,
Power factor 0.90) with suitable fixing
arrangement as per instruction of Engineer
incharge at site.
10 10 Supply, fixing, connection, testing & Numbers 12.00 1336.00 16032.00
commissioning of surface mounting sleek LED
mirror light 5 W or 7 W, IP 20, 1 ft version
powder coated CRCA housing, high output
diffuser including suitable fixing arrangement on
surface as per instruction of Engineer incharge
11 11 Supply, fixing & testing of LED retrofit lamp 9 Numbers 84.00 146.00 12264.00
watt, B-22 cap as per instruction of Engineer
incharge at site.
12 12 Fixing, testing & commissioning of ceiling fan Numbers 36.00 46.00 1656.00
with supply & fixing of MS clamp with hook, nut,
bolt, washer etc. as per instruction of Engineer
incharge at site. (Fan will be supplied by
13 13 Supply, installation, testing & commissioning of Numbers 36.00 2824.00 101664.00
300 mm sweep (metallic) heavy duty exhaust
fan, 1400 RPM complete with fixing on wall by
suitable size bolts & nuts grouted on wall as per
instruction of Engineer incharge at site.
14 14 Supply, wiring & testing of main wire by 2.5 sq Metre 1800.00 75.00 135000.00
mm, Single Core FR-LSH PVC Insulated Industrial
Grade Copper Conductor (Unsheathed) Flexible
Cables, 1100 Volts and earth continuity wire by
1.0 sq mm FR-LSH PVC Insulated Industrial
Grade Copper Conductor Conforming to IS: 694
concealed in wall through PVC rigid conduit pipe
not less than 20 mm dia as per instruction of
Engineer incharge at site.
15 15 Supply, wiring & testing of main wire by 4 sq Metre 2280.00 87.00 198360.00
mm, Single Core FR-LSH PVC Insulated Industrial
Grade Copper Conductor (Unsheathed) Flexible
Cables, 1100 Volts and earth continuity wire by
1.0 sq mm FR-LSH PVC Insulated Industrial
Grade Copper Conductor Conforming to IS: 694
concealed in wall through PVC rigid conduit pipe
not less than 20 mm dia as per instruction of
Engineer incharge at site.
16 16 Supply, wiring & testing of main wire by 6 sq Metre 1440.00 100.00 144000.00
mm, Single Core FR-LSH PVC Insulated Industrial
Grade Copper Conductor (Unsheathed) Flexible
Cables, 1100 Volts and earth continuity wire by
1.0 sq mm FR-LSH PVC Insulated Industrial
Grade Copper Conductor Conforming to IS: 694
through PVC rigid conduit pipe/polythene pipe
not less than 20 mm dia as per instruction of
Engineer incharge at site.
KATIHAR DIVISION-ELECTRICAL/N F RLY
17 17 Supply, installation, testing & commissioning of Set 72.00 1193.00 85896.00
modular power unit complete with 32 Amp mini
MCB DP "C" series 3kA , 25 amps starter, 25
Amp Socket and 25 Amp plug to be mounted on
6 module GI box, 6 module combined plate
concealed on wall and wiring by 6 sq mm, Single
Core FR-LSH PVC Insulated Industrial Grade
Copper Conductor (Unsheathed) Flexible Cables,
1100 Volts with earth coninuity wire by 1 sq mm
copper cable Conforming to IS: 694 to be drawn
through Rigid PVC conduit pipe not less than 20
mm dia as per instruction of Engineer incharge
at site. (For AC & Geyser Point)
18 18 Supply, installation, testing & commissioning of Numbers 12.00 11309.00 135708.00
Stationary storage type electric water heater
(Geyser), Digital display, Type:-Vertical,
Capacity (Ltrs):25, Power input: 2000 watt,
Class:-I, Star Rating: 5 Star suitable for
operation on 230 Volts, single phase AC, 50 Hz.
Storage electric water heater shall be complete
in all respect with fittings as per general
technical requirements and as per instruction of
Engineer incharge at site.
19 19 Supply, installation, testing & commissioning of Numbers 12.00 1265.00 15180.00
10 watt LED Bulkhead luminaires, IP65 as per
instruction of Engineer incharge at site. (For
20 20 Supply, installation, testing & commissioning of Set 12.00 1413.00 16956.00
service pipe made of 50 mm dia, medium gauge
12 ft long GI Pipe with 3 no GI bend and socket
to be fixed with the building by necessary
grouting, complete with service bracket , stay
by 7/14 SWG stay wire clamped with service line
and guard wire, shackle / pin insulator as per
instruction of Engineer incharge at site.
21 21 Supply, laying, commissioning & testing of HDPE Metre 72.00 70.00 5040.00
pipe 50 mm dia, PN-6 grade to be laid partly
along the p o l e / w a l l with suitable fixing
arrangement by MS clamp made of MS flat of
size 50x6 mm and suitable size nut , bolt,
washer etc as per instruction of Engineer
Incharge at site.
22 22 Supply, installation, testing & commissioning of Set 12.00 1166.00 13992.00
poly carbonated/ Thermoplastic meter
box/Empty box of size (217 x 253 x 115) mm
with IP 65 grade protection as per instruction of
Engineer incharge at site. (For Energy meter)
23 23 Supply & Erection of earth by 50 mm dia 3 Mtrs. Numbers 12.00 4349.00 52188.00
long (3.6 mm thickness) GI pipe, 32x6 mm GI
strip- 5 Mtrs, GI nuts, bolts including masonry
materials for earthing pit, salt, charcoal,
soldered end terminal etc. and construction of
earth pit covered with RCC cover slab12.7 mm
thickness and watering pipe as per Drg. No.-
PCEE/ELG/DRG/2024/1 Date:- 30.09.2024 and as
per instruction of Engineer Incharge at site.
24 24 a) Supply, installation, testing & commissioning Set 12.00 2712.00 32544.00
of 18 way SPN Distribution Board, Flush/Surface
mounting, IK 09, IP 43 grade protection with
copper bus bar, fully shrouded neutral bar, earth
bar, cable ties, Prefitted masking sheet,
Reversible metal door as per IS 8623 - 1& 3 as
per instruction of Engineer incharge at site.
25 25 b) RCBO DP 32 Amp, 2 module Conforms to IEC Numbers 12.00 2883.00 34596.00
Conforms to IS/IEC 60898 - 1:2002
KATIHAR DIVISION-ELECTRICAL/N F RLY
Conforms to IS/IEC 60898 - 1:2002
28 28 Laying, commissioning & testing of HT/LT Metre 360.00 55.00 19800.00
XLPE/PVC cable of different sizes partly along
the pole and partly through ground in cable
trench by excavation of ground below 1.5 mt
from ground level with suitable fixing
arrangement by MS clamp of size 50x6 mm and
suitable size nut, bolt. Loading, Unloading &
Carrying of cable to actual work site by
contractor's own arrangement. (Aluminium
Crimping Socket should be provided for each
Cable Termination). (Cable will be supplied by
Item- 2 PART-B (Additional Items)
S No. Item Description of Item Unit Qty Rate Amount
1 1 "Supply & testing of GI octagonal pole 6 mt long Numbers 12.00 14193.00 170316.00
with foundation bolt, loop box of bakelite sheet
with one 6A SP MCB and 16 sq mm stud type
connector etc. The octagonal pole shall be hot
dip galvanized in single dip. Technical
specification of pole as following:- Height - 6 mt
Top dia (A/F) - 70 mm Bottom dia (A/F) - 130 mm
Sheet thickness - 3 mm Base plate (L x B x T) -
(200 x 200 x 12) mm Foundation Bolt size (no.x
dia) - 4 x 20 dia mm Pitch Circle Dia (PCD) - 200
mm Bolt length - 600 mm Projected Bolt Length -
2 2 Supply & fixing of 1 mtr GI Single arm bracket Numbers 12.00 1615.00 19380.00
(header) and holder with Nut & bolt as per
instruction of Engineer incharge at site.
3 3 Erection of Rail/Tubular/Octagonal pole to 1/5 th Numbers 12.00 1712.00 20544.00
of its height with CC foundation from base block
(30 cm x 30 cm x 15 cm) including digging &
refilling of earth to a height of 30 cm above
ground level as per drawing
no.CEE/OH@47'40@FGA) in ratio 1:3:6 by
cement sand & Chips 19 mm & down including
excavation of earth.
4 4 Supply, installation, testing & commissioning of Numbers 12.00 14159.00 169908.00
150 Watt LED Street Light made up of pressure
die cast aluminium housing with high efficiency
LEDs as lighting source and lens embedded PC
cover having TOP Opening seperate driver
compartment with IP66 protection and impact
resistance of IK08. as per instruction of Engineer
incharge at site.
5 5 Supply, installation, testing & commissioning of Numbers 10.00 8823.00 88230.00
90 Watt LED street light with pressure die-cast
housing and toughened glass and individual
LEDs with secondary lens optics for City Road
application withIP66 ingress protection. 4kV
inbuilt and 10kV external surge protecton with
Top opening driver cover for easy maintenance
as per instruction of Engineer incharge at site.
KATIHAR DIVISION-ELECTRICAL/N F RLY
6 6 "Supply, installation, testing and commissioning Numbers 6.00 52751.00 316506.00
of drop down Led decorative light warm white
Cast iron based pole of height 3 meter with 45
watt capacity double arm bracket mild steel
grooved pipe pole made out of cast iron base
390 mm base dia, Top 83mm OD above the
ground level primer coated and painted with
polyurethane paint with die cast aluminum
embellishments, joints/ column's section etc.
The bottom column shall be integral connection
box having mounting arrangement of One No.
MCB, 4 Way heavy duty connector cover the
same etc. as required with medium Led Hanging
light made out of spun aluminium housing,
minimum 4500 lumens with maximum system
wattage 45 watt Led Mounting on aluminum die
casted heat sink with power Led, minimum
efficacy 100 Lumen per watt with external driver
CCT 5700, CRI > 70, PF>0.90, Operating Voltage
220-240V AC Painted with PU Paint as matching
of above Pole complete. The LED driver access
should be from top for easy maintenance LEDs
should be provided with non-yellowing modular
secondary lens optics. LED used shall be SMD
type, Life of fixture 50000 hrs, THD< 10%, and
Operating Temperature Range 0 deg C to + 50
deg C, IP66. Built in Surge Protection of SKV &
external surge protection of 10 kV. LED Driver
should be of Constant current driver to have
built-in surge, open & short circuit protection,
Over Voltage Protection @ 300V+5V, Double
Phase Protection (up to 48 hrs.) and as per
requirement and direction of Railway site
engineer in-charge. "
7 7 Supply, fixing, testing, commissioning of 15 W Numbers 20.00 8096.00 161920.00
LED Bollard light IP 66 complete as per IS & IE
rules and as per instruction of Engineer Incharge
8 8 Supply, installation, commissioning & testing of Square 96.00 1772.00 170112.00
LED indication name board (Length of board will Foot
be as per proportion of letter so that all the 4
side of the board will have extra space) with
channel letters with 3.75 ft. in lenght with
suitable widen and 4 mm projection size which
inside ACP board (Brand- ALUDECOR, category-
AL 33 series exterior & thikness-3 mm) with
acrylic face on front and having Sumsung 5630
LED's (Shape- Lens type, operating voltage- 12
V DC, carring current-80 mA, power Dissipation-
0.96 watt, working hours-50000, case material-
ABS ,protection-IP68) inside for illumination
letters in English, Hindi, Bengali or regional
language complete with all materials including
provision of erection structure made of MS
angle/channel/flat duly painted with aluminium
paint over a coat of red oxide primer with CC
foundation (1:3:6) of cement, sand and stone
chips as required at site and as per instruction
of Egnineer incharge at site.
9 9 Supply, testing & fixing of LED Rope Light 50 Numbers 16.00 7237.00 115792.00
Meters (Red, Yellow, Blue, Green, White as
required) Waterproof, IP 65 or above as per
instruction of Engineer Incharge at Site.
10 10 Horizontal machine boring of 300 mm dia hole Metre 50.00 2538.00 126900.00
across track/Road/High drain etc. at a depth of
1.0 mtr below of ground level with suitable
boring instruments & neessary arrangement and
as per technical procedure.
KATIHAR DIVISION-ELECTRICAL/N F RLY
11 11 Supply, laying, commissioning & testing of HDPE Metre 200.00 383.00 76600.00
pipe 110 mm dia PN-6 grade conforming IS
4984/1995 or latest to to be laid partly along the
p o l e with suitable fixing arrangement by MS
clamp m ade of MS flat of size 50x6 mm and
suitable size nut , bolt, washer as per instruction
of Engineer incharge at site.
12 12 Supply, laying, commissioning & testing of HDPE Metre 300.00 278.00 83400.00
Pipe 75 mm dia PN-6 grade to be laid partly
along the pole /underground with suitable fixing
arrangement by MS clamp made of MS flat of
size 50x6 mm and suitable size nut, bolt, washer
and required bend, joints as per instruction of
Engineer incharge at site.
13 13 Supply, fixing, testing & commissioning of IP Numbers 10.00 5291.00 52910.00
66/67 thermoplastic cable junction box / loop
box of size (210 x 310 x 116) mm with
knockouts & 04 nos terminals as per instruction
of Engineer incharge at site.
14 14 Supply & Erection of earth by 50 mm dia 3 Mtrs. Numbers 10.00 4349.00 43490.00
long (3.6 mm thickness) GI pipe, 32x6 mm GI
strip- 5 Mtrs, GI nuts, bolts including masonry
materials for earthing pit, salt, charcoal,
soldered end terminal etc. and construction of
earth pit covered with RCC cover slab12.7 mm
thickness and watering pipe as per Drg. No.-
PCEE/ELG/DRG/2024/1 Date:- 30.09.2024 and as
per instruction of Engineer Incharge at site.
15 15 Supply, erection & commissioning of earth spike Numbers 10.00 366.00 3660.00
made of 16 mm dia 1.8 mt long GI rod &
connection metal body with the earth spike rod
by 6 SWG GI earth wire with nut, bolt & washer
16 16 a) Supply, installation, testing & commissioning Set 6.00 5070.00 30420.00
of oudoor type weather proof sheded feeder
pillar box of suitable size made of powder
coated 14 SWG MS/CRCA sheet, angle, flat etc.
The feeder pillar box four legs should be
grounted on CC foundation (1:3:6). Cable entry
should have PVC glands. Feeder pillar box
should have double door system with locking
arrangement with fixing of rubber gasket for
protection of entry of dust and water alongwith
supply and fixing of following MCCB as per
instruction of Engineer Incharge at site.
electrolytic grade copper consisting of 4 no bars
( 3 Ph & neutral )
KATIHAR DIVISION-ELECTRICAL/N F RLY
19 19 a) Supply, fabrication, erection, testing, Set 1.00 32916.00 32916.00
commissioning & painting of floor mounted
powder coated cubicle panel board (Modular
look) of suitable size (neither big nor small) ),
outdoor type with double door made of suitable
size MS/GI angle 50 x 50 x 6 mm, MS/GI flat 50 x
6 mm, 14 SWG MS sheet/Powder coated CRCA
sheet with provision of weather proof,rust
proof,dust proof,water proof having internal
rubber gasket with supply and fixing of following
ACB/MCCB/Bus bar/Meter etc. (Connections to
be made by copper strips, glands should be
provided at cable entry and exit, components
should be compartmentalized, Each
compartment will be provided with the door and
pad locking arrangement. The compartment
illumination lamp with door operated switch
shall be provided for each compartment. Panel
board drawing approval must be obtained with
clear indication of make of items of
20 20 b) Supply & fixing of onload changeover switch Numbers 1.00 24733.00 24733.00
630 amps Four Pole, 415 V 50 Hz, with Sheet
Steel Enclosure (with front handle) as per IS/IEC
26 26 h) Supply, Fixing & Testing of Copper bus bar Set 1.00 6830.00 6830.00
800 amps made of electrolytic grade copper
consisting of 4 bars ( 3 Ph and Neutral ) ( Bus
bar should have insulation cover)
28 28 j)Supply, Fixing & Testing of LED multifunction Set 1.00 10470.00 10470.00
meter, Accuracy Class 1.0, Input voltage
measurement range 50-550 VAC (P-P), Aux
supply 90-300VAC/DC for measuring of V, A, F,
PF, kW, kVA, kVAR, kWh, kVAh, kVARh,
Runhours, On hours, Interrupts, THD, neutral
current etc parameters alongwith supply & fixing
of 3 nos. suitable CTc.
29 29 Laying, commissioning & testing of HT/LT Metre 2000.00 55.00 110000.00
XLPE/PVC cable of different sizes partly along
the pole and partly through ground in cable
trench by excavation of ground below 1.5 mt
from ground level with suitable fixing
arrangement by MS clamp of size 50x6 mm and
suitable size nut, bolt. Loading, Unloading &
Carrying of cable to actual work site by
contractor's own arrangement. (Aluminium
Crimping Socket should be provided for each
Cable Termination). (Cable will be supplied by
30 30 Excavation of cable trench (0.3 x 1.5) mtr below Metre 617.00 148.00 91316.00
ground level for laying of cable & refilling the
soil after digging the earth as per instruction of
Engineer incharge at site. Cable should be laid
on bedding of height 75 mm sand at the bottom
of trench, and covering it with additional sand of
height 75 mm and thereafter protecing it by
mean of bricks before refilling the soil as per IS
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GCC 2022 Works with ACS
ATTACHMENT
NITforBLGTstaffqtrphase1andphase2.pdf Tender Paper
ATTACHMENT
GCCApril-2022PDFwithallACS_compressed.pdf
ATTACHMENT
NITforBLGTstaffqtrphase1andphase2.pdf
ATTACHMENT
Download all tender documents and submit your bid