| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.4 LAdmitted-Finance 00 MUKUNDPUR PAHO DOMANPUR MUKUNDPUR PAHO MIRZAPUR UTTAR PRADESH 231306 | MIRZAPUR | UTTAR PRADESH | 231306 | L1 | Admitted-Finance | |
| 2 | L2₹5.6 L+₹16,925 (3.12%)Admitted-Finance SANTOSH NAGAR COLONY LACHHIPUR BARGADWA GOKAKHPUR UP 273015 | GOKAKHPUR | GORAKHPUR | UP | 273015 | L2 | Admitted-Finance | |
| 3 | L3₹6.8 L+₹1.3 L (24.3%)Admitted-Finance CENTRAL COALFIELDS LIMITED OFFICE OF THE PROJECT OFFICER E M DEPARTMENT SAUNDA D BARKA SAYAL AREA | BOKARO | JHARKHAND | 825102 | L3 | Admitted-Finance | |
| 4 | L4₹7.2 L+₹1.8 L (33.3%)Admitted-Finance NEAR RELIANCE PETROL PUMP RAMGARH CANTT 829122 DIST RAMGARH JHARKHAND | RAMGARH CANTT | RAMGARH | JHARKHAND | 829122 | L4 | Admitted-Finance |
| Sl No | Description | Qty | Unit | CENTRAL ENGINEERS L3 | Rajneesh Electricals L4 | M/S ADITYA ENTERPRISES L1 | SHIVAM INDUSTRIES L2 |
|---|---|---|---|---|---|---|---|
| 1.00 | Complete rewinding of 2MVA, 11KV/3.3KV HT copper wound, oil cooled power transformer by using 570 Kg of copper Strip wire 5mm x 1.5mm for disc winding (Primary coil) and 190Kg of copper strip wire 10 mm x 2 mm for disc winding (secondary coil) including Insulation Cost, labour Cost and less scrap Value of old copper strip. | 1 | Job | 5,55,000 ₹5,55,000 | 5,95,840 ₹5,95,840 | 4,41,560 ₹4,41,560 Lowest | 5,10,000 ₹5,10,000 |
| 2.00 | Providing &fixing of Buchulze Relay suitalble for 2MVA, IIKV/3.3KV transformer including all accessories (i.e. Flange, Pipe, packing etc.) | 1 | No | 18,000 ₹18,000 | 19,700 ₹19,700 | 14,300 ₹14,300 | 5,000 ₹5,000 Lowest |
| 3.00 | Online oil filtration inc. labour charge. | 1,600 | Ltr. | 15 ₹24,000 | 15 ₹24,000 | 10 ₹16,000 Lowest | 15 ₹24,000 |
| 4.00 | Providing and fixing of Winding Temperature Meter. | 1 | No | 23,000 ₹23,000 | 25,000 ₹25,000 | 22,300 ₹22,300 | 2,000 ₹2,000 Lowest |
| 5.00 | Providing and fixing of Oil Temperature Meter. | 1 | No | 22,000 ₹22,000 | 23,000 ₹23,000 | 19,120 ₹19,120 | 2,000 ₹2,000 Lowest |
| 6.00 | Providing and fixing of 2.5 Sq mm 4 core Al. Cable. | 25 | Mtr. | 250 ₹6,250 | 270 ₹6,750 | 210 ₹5,250 | 200 ₹5,000 Lowest |
| 7.00 | Providing and fixing of Breather with silica gel suitable for 2 MVA Transformer . | 1 | No | 8,500 ₹8,500 | 9,500 ₹9,500 | 8,000 ₹8,000 | 2,000 ₹2,000 Lowest |
| 8.00 | Providing and fixing of HT/LT Bushing Insulator with stud. | 2 | No | 8,000 ₹16,000 | 8,550 ₹17,100 | 6,310 ₹12,620 | 2,500 ₹5,000 Lowest |
| 9.00 | Providing and fixing of Gasket (1 mtr x 0.75 mtr x 3mm) | 5 | No | 450 ₹2,250 Lowest | 650 ₹3,250 | 785 ₹3,925 | 1,000 ₹5,000 |
| 11.00 | Total impact of GST for the purpose of CTC | 1 | Nos | - | - | - | - |
Tender Value
₹8.5 L
EMD Value
₹10,700
Closing Date
25 May 2026, 11:00 amClosed
Staff Officer(EnM), Argada Area
GM Unit, Sirka, Argada Area, Ramgarh-829101
Complete rewinding/repairing, installation and testing etc. of 2MVA, 11KV/3.3KV copper wound, oil cooled transformer make- East India Electrical, sl. no. - 458A/2 of Power house substation, Argada of Sirka group under Argada Area.
2026_CCL_359617_1
SO(EnM)/AA/eNIT/26-27/15
Open Tender
Electrical and Maintenance Works
Item Rate
30 days
Sirka OCP under Argada Area
2 documents required · 2 mandatory
₹10,700
14 Oct 2026
14 May 2026
26 May 2026
15 May 2026
25 May 2026
15 May 2026
15 May 2026 - 22 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Complete rewinding of 2MVA, 11KV/3.3KV HT copper wound, oil cooled power transformer by using 570 Kg of copper Strip wire 5mm x 1.5mm for disc winding (Primary coil) and 190Kg of copper strip wire 10 mm x 2 mm for disc winding (secondary coil) including Insulation Cost, labour Cost and less scrap Value of old copper strip. | 1 | Job | - | - |
| 2 | Providing &fixing of Buchulze Relay suitalble for 2MVA, IIKV/3.3KV transformer including all accessories (i.e. Flange, Pipe, packing etc.) | 1 | No | - | - |
| 3 | Online oil filtration inc. labour charge. | 1,600 | Ltr. | - | - |
| 4 | Providing and fixing of Winding Temperature Meter. | 1 | No | - | - |
| 5 | Providing and fixing of Oil Temperature Meter. | 1 | No | - | - |
| 6 | Providing and fixing of 2.5 Sq mm 4 core Al. Cable. | 25 | Mtr. | - | - |
| 7 | Providing and fixing of Breather with silica gel suitable for 2 MVA Transformer . | 1 | No | - | - |
| 8 | Providing and fixing of HT/LT Bushing Insulator with stud. | 2 | No | - | - |
| 9 | Providing and fixing of Gasket (1 mtr x 0.75 mtr x 3mm) | 5 | No | - | - |
| 11 | Total impact of GST for the purpose of CTC | - | Nos | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 3.23 MB
BOQ_372482.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .