| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.6 LAccepted-AOC | L1 | Accepted-AOC Accepted | |
| 2 | L2₹8.2 L+₹61,137.02 (8.09%)Rejected-Finance | L2 | Rejected-Finance Being L2 |
Tender Value
₹8.5 L
EMD Value
₹21,182
Closing Date
25 Mar 2023, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Joji Paul
EXECUTIVE ENGINEER LSGD DIVISION AYYANTHOLE THRISSUR 680003
ANNUAL PLAN-DPT 2022-23 VARANDARAPPILLY GP -ECHIPPARA ST COLONY SAMAGRA VIKASANAM - KODAKARA BP -S0656/23-GENERAL CIVIL WORK
2023_LSGD_566722_1
TN-21/2022-23/42738
Open Tender
Civil Works - Others
Item Rate
365 days
THRISSUR
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,870
Yes
₹21,182
Yes
22 May 2023
17 Mar 2023
28 Mar 2023
17 Mar 2023
25 Mar 2023
17 Mar 2023
Amount
NADAPALAM
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
2.7.1:Earth work in excavation by mechanical means (Hydraulic excavator )/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.Ordinary rock
51.2.3:Filling with Quarry Muck <br> Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.3:Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 15<sup>0</sup> landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
60.7.4:DR PACKING FOR APRONS - Rough stone dry packing for apron with good quality blasted rubble including packing to compactness to lines levels, cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
10.26.3:Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approves steel primer.G.I. pipes
50.2.26.1:Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
16.42:Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size ) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete
16.1:Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earth with lead upto 50 metres.
SHEJI KT
Bidder Name
SHEJI KT
KUNJUMOITHEEN P M
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_836177.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .