Tender Value
₹9.2 L
EMD Value
₹9,200
Closing Date
30 Sept 2026, 2:00 pm3d left
SUPERINTENDING ENGINEER
OFFICE OF THE SUPERINTENDING ENGINEER KEDC KARUR
Improvements works of toilet roof interior wall surface and to providing solar reflective ceramic tiles over the roof etc in existing office of the Assistant Engineer O and M South Ayyermalai at Ayyermalai substation premises
2026_EB_704799_1
SPEC04/26-27
Open Tender
Civil Works
Works
180 days
KARUR
AS PER SPEC
2 documents required · 2 mandatory
₹0
₹9,200
Yes
16 Sept 2026
16 Sept 2026
1 Oct 2026
16 Sept 2026
30 Sept 2026
16 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Name of the works | |||||
| 1.01 | Earth work excavation for foundation including all labour charges including cost of all materials, labour, lead, lift,T&Ps etc complete and as directed by the Engineer incharge of the work.. | 3.5 | M3 | 100 | ₹350 |
| 1.02 | Earth work excavation in soft disintegrated rock laterite soft rock or kankar not requiring blasting including cost of all materials, labour, initial lead, lift ,T&Ps etc complete and as directed by the Engineer incharge of the work.. | 2.5 | M3 | 100 | ₹250 |
| 1.03 | Earthwork excavation in medium rock and dense medium rock not requiring blasting including cost of all materials, labour, lead, lift,T&Ps etc complete and as directed by the Engineer incharge of the work. | 5.5 | M3 | 100 | ₹550 |
| 1.04 | Chipping of concrete and roughening the surface including cost of labour charges etc.,complete and as directed by the Engineer incharge of the work. | 88 | M2 | 100 | ₹8,800 |
| 1.05 | Chipping of old damaged plastered walls with clean removal of cement plaster from walls and racking out joints 20 mm deep for replastering including cost of all materials, labour, lead, lift etc complete and as directed by the Engineer incharge of the work. | 177 | M2 | 100 | ₹17,700 |
| 1.06 | Dismantling of wooden doors, windows and clearing away and stocking the materials suitable for reuse as directed by the Engineer incharge of work including cost of all labour, lead, lift etc., complete. | 26.5 | M2 | 100 | ₹2,650 |
| 1.07 | Dismantling the existing terracing of pressed roof tiles work and removing them away as directed by the depatment engineer in charges including cost of labour , lead, lift, scaffloding charges etc complete. | 157 | M2 | 100 | ₹15,700 |
| 1.08 | Dismantling Plain Cement Concrete removing them away as directed by the depatment engineer in charges including cost of labour , lead, lift, scaffloding charges etc complete. | 1 | M3 | 100 | ₹100 |
| 1.09 | PCC 1:4:8, using 40mm HBG metal foundation without formwork including cost of cement, all materials, labour, lead, lift, etc. complete. | 0.8 | M3 | 100 | ₹80 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.74 MB
SPEC.pdf
Tender Documents • 0.72 MB
BOQ_847220.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .