| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | Stanley Crescent Fernandes L1₹88.4 LAccepted-AOC | ₹88.4 L | L1 | Accepted-AOC First Lowest quoted firm |
| 2 | L2₹1.1 Cr+₹16.7 L (18.8%)Rejected-AOC | ₹1.1 Cr+₹16.7 L (18.8%) | L2 | Rejected-AOC Second lowest quoted firm |
Tender Value
₹90.6 L
EMD Value
₹1.8 L
Closing Date
21 Sept 2022, 3:00 pmClosed
Director, CSIR - NIO
CSIR - NATIONAL INSTITUTE OF OCEANOGRAPHY, GOA
Re-Carpetting of Staff quarters colony Roads with Hotmix and Re-carpetting of Institute road with hotmix from Main gate to Administrative Building at CSIR-NIO, Goa
2022_CSIR_128245_1
19/397/2021-Wks
Open Tender
Civil Works - Roads
Item Rate
30 days
CSIR - NATIONAL INSTITUTE OF OCEANOGRAPHY
Please refer Tender documents.
10 documents required · 10 mandatory
₹1,000
Director
₹1.8 L
Yes
1 Dec 2022
13 Sept 2022
22 Sept 2022
13 Sept 2022
21 Sept 2022
13 Sept 2022
13 Sept 2022 - 20 Sept 2022
Amount
Surface dressing on old surface with hot bitumen of grade VG - 10 of approved quality using 1.95 kg of bitumen per sqm with 1.50 cum of stone chippings 11.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity, etc. complete
Providing and applying tack coat using hot straight run bitumen of grade VG - 10, including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications : On bituminous surface @ 0.50 Kg / sqm
Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge. 40/50 mm compacted thickness with bitumen of grade VG-30 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate)prepared in drum Type Hot Mix Plant of 60-90 TPH capacity
Painting road surface marking with adequate nos of coats to give uniform finish with ready mixed road marking paint conforming to IS : 164, on bituminous surface in white/yellow shade, including cleaning the surface of all dirt, scales, oil, grease and foreign material etc. complete. New work (Two or more coats
Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : One or more coats on old work
Description of Work / Item(s)
Amount
Surface dressing on old surface with hot bitumen of grade VG - 10 of approved quality using 1.95 kg of bitumen per sqm with 1.50 cum of stone chippings 11.2 mm nominal size per 100 sqm of road surface, including consolidation with road roller of 6 to 8 tonne capacity, etc. complete
Providing and applying tack coat using hot straight run bitumen of grade VG - 10, including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications : On bituminous surface @ 0.50 Kg / sqm
Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge. 40/50 mm compacted thickness with bitumen of grade VG-30 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate)prepared in drum Type Hot Mix Plant of 60-90 TPH capacity
Painting road surface marking with adequate nos of coats to give uniform finish with ready mixed road marking paint conforming to IS : 164, on bituminous surface in white/yellow shade, including cleaning the surface of all dirt, scales, oil, grease and foreign material etc. complete. New work (Two or more coats
Dismantling Brick/Tile Work In cement mortar
Excavation in Ordinary Rock using Hydraulic ExcavatorCK-90 and Tippers with disposal upto 1000 metres. (Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.
Compacting original ground supporting subgrade (Loosening of the ground upto a level of 500 mm below the subgrade level, watered, graded and compacted in layers to meet requirement of table 300-2 for subgrade construction.)
Supplying and stacking laterite stones of size 150-200 mm(contractor's stone) for soling at siteLaying stone soiling including packing with smaller stones and consolidation with road roller including spreading, watering and consolidating of binding material Murrum or earth etc.(payment to be made for quantity of only soling stone used excluding binding material).
Supplying of granitic or basaltic stone soling of size 15-20 cm and Murrum having P.I. Value not more than 6 and laying including packing with smaller stones and consolidation with power roller including spreading waters and consolidation of binding material etc. complete.(Measurements shall be considered on finished item and and layer of WBM of 50/75mm thick shall be taken seperately over this sub-base to obtain smooth surface, as per the directives of Engineerin-charge).
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.)
Description of Work / Item(s)
TOTAL OF BoQ1 FOR PART A - Staff quarters colony roads
TOTAL OF BoQ2 FOR PART B - Institute road from Main gate to Administrative Building
SAI KAMAL CONSTRUCTIONS
SAI KAMAL CONSTRUCTIONS
SAI KAMAL CONSTRUCTIONS
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .