Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.8 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹16.2 L+₹1.4 L (9.59%)Rejected-AOC | L2 | Rejected-AOC L2 |
Tender Value
₹15.8 L
EMD Value
₹39,429
Closing Date
11 Mar 2025, 4:00 pmClosed
Assistant Engineer
Municipal Office, Kothamangalam.
GENERAL-ANNUAL PROJECTS 2024-25- PROJECT 78/25 WARD 28- SC COMMUNITY HALL COMPLETIONGeneral Civil Work
2025_LSGD_745837_1
LSGD/CELSGD/109504/2024-2025
Open Tender
Civil Works - Buildings
Item Rate
180 days
Kothamangalam
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
₹39,429
30 Apr 2025
4 Mar 2025
12 Mar 2025
4 Mar 2025
11 Mar 2025
4 Mar 2025
Amount
General civil work
OD476217/2024-2025:DOWEL BARS - Supplying and providing MS dowel bars of size 20 mm dia , 1.5m long (1m in rock and 0.5 m in concrete) including drilling holes of 25mm dia and filling the gap with cement grout ( 0.25kg/each) etc complete.
5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.3:Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 150 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
ALVIN VALSALAN (BID ID -2147812)
Bidder Name
Denny P J
ALVIN VALSALAN
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .