| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹5.0 CrAccepted-Finance | ₹5.0 Cr | L-1 | Accepted-Finance Admitted |
| 2 | L-2₹5.7 Cr+₹77.0 L (15.5%)Accepted-Finance | ₹5.7 Cr+₹77.0 L (15.5%) | L-2 | Accepted-Finance Admitted |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹3.9 Cr
EMD Value
₹6 L
Closing Date
1 Aug 2022, 4:00 pmClosed
Superintending Engineer
Electricity Transmission Circle, 220 KV S/S Campus Natwa, Mirzapur
Construction of 220 KV Aurai (400)-Phoolpur DC line on debitable basis under E.T.D-IV, Varanasi.
2022_UPTCL_714250_1
short term T. No. 21/2022-23/ETC/Mzp
Open Tender
Electrical Works
Fixed-rate
365 days
Bhadohi
As per tender specification
2 documents required · 2 mandatory
₹11,800
Executive Engineer, ETD, Mirzapur
₹6 L
20 Aug 2022
13 Jul 2022
2 Aug 2022
13 Jul 2022
1 Aug 2022
13 Jul 2022
Amount
[A] Supply
220 KV Double Ckt. Mono Pole PB (2-15 degree) Bottom Cross arm height 27mtr
220 KV Double Ckt. Mono Pole PC (30-60 degree) Bottom Cross arm height 27 mtr
Single Suspension fitting complete in all respect for ACSR Zebra conductor
Single tention fitting complete in all respect for ACSR Zebra conductor
Double Suspension fitting complete in all respect for ACSR Zebra conductor
Double tension fitting complete in all respect for ACSR Zebra conductor
70 KN Disc insulator
160 KN Disc insulator
Vibration damper for ACSR Zebra conductor
Mid Span Compression Joint for ACSR Zebra conductor
Repair Sleeve for ACSR Zebra conductor
Perforated Armour Rod for ACSR Zebra conductor
Bird Guard
Earthing marerial(Pipe type)
Number plate
phase plate(set of three color red,blue and yellow)
Danger plate
Anchor Bolt with Double Nut & washer
24 Fibre(DWSM) OPGW Fibre Optic Cable
Supply and installation of Hardware set for 24 Fibre OPGW
Joint Box (24 Fibre)
[B] Work
Check survey including final peg marking
Casting of foundation, work includes excavation, pilling, Reenforcement steel, boring, fixing of foundation bolts,concreting, back filling and other associated work required to complete the foundation work as per approved design for given monopoles.
220 KV Double Ckt. Pole PB (2-15 degree) Bottom Cross arm height 27mtr
220 KV Double Ckt. Pole PC (30-60 degree) Bottom Cross arm height 27 mtr
Erection of 220 KV D/C MONOPOLE & there extensions wherever required including all work above ground level.
220 KV Double Ckt. Pole PB (2-15 degree) Bottom Cross arm height 27mtr
220 KV Double Ckt. Pole PC (30-60 degree) Bottom Cross arm height 27 mtr
Excavation of foundation pits including all earth work, back filling and leveling etc.
Setting of stubs including all foundation work but excluding the cost of concreting and excavation
Cost concreting for all types of foundation of tower & gantry including cost of cement dewatering, shoring, shuttering, forming and curing but excluding of reinforcement bar with 1:2:4 mix concrete.
Erection of super structure of A,B and C type tower with their 5M/10M extensions wherever required including all work above ground level excluding hoisting of insulators but fitting of danger, number & phase plates.(weight of toweris excluding the weight of stub,washer,nutbolts etc including all cost of T&P and labour charges and carriage of structure of towers from UPPTCL store to site)
Tack welding of the nut & bolts up to the height of one section or 5 meter from ground level whichever is higher with three tacks & application of Zinc rich paint.
Laying, stringing, tensioning, clamping, jointing etc. of all three power conductors with ACSR Zebra conductor including hoisting of insulators, fitting of all necessary hardware and accessories i.e fittings, armour rod, vibration dampers of all three phasesincluding all cost of labour, T&P and carriage of conductor from UPPTCL store to site.
Grounding work including earth work etc. for pipe type including cost of coke & salt
Installation of steel reinforcement bars in RCC foundation including cutting, placing, binding etc.
Laying,stringing,tensioning,clamping,jointing,including fitting of all necessary hardware and accessories of OPGW & OFAC termination at substation ,end to end connectivity & testing etc and carriage of OPGW from UPPTCL store to site.
Round the clock watch & ward of the line/line material during construction work to avoid theft of tower parts, Conductor, OPGW, Insulators, Hardware Fittings,Accessories etc. (1 Job per Day).
Cutting of following sizes various type of trees like Mango,Neem,Shisham,Pipal,Eucalyptus etc.Falling in the range of Corridor of the said 220 KV lines to provide the maximum clearance between the trees and conductor on the both side of tower/line with all due care of safety & precaution to avoid any damaged to nearby building,power & telephone lines passing near by,crops,other near by trees etc.The work also includes removing elaminating & cleasning the line sites after cutting of trees.
Trees having girth between 0.5 to 1 Mtr.
Trees having girth between 1 to 2 Mtr.
Looping & Chooping of trees branches of different Mango, Neem, Shisham,Pipal,Eucalyptus etc.Falling in the range of Corridor of the said 220 KV lines to provide the maximum clearance between the trees and conductor on the both side of tower/line with all due care of safety & precaution to avoid any damaged to nearby building,power & telephone lines passing near by,crops,other near by trees etc.The work also includes removing elaminating & cleasning the line sites after looping & chooping of trees.
Sorting,Shifting of tower parts from 132 KV S/S Aurai to working site,fabrication of tower parts and making hole as per required missing member then replecement of fabricated member with the help of suitable size of Nut bolt & washer of 220 KV Aurai-Mirzapur line and Bolt should be properly tightened & punching. (rate including all T & P and labour charges but excluding the cost of tower parts & Nut Bolt washer)
Dismantling of damaged/Collapse 18 No. (A+0 type-16 No.,A+5-1 No.B+0-3 No.) tower by way of breaking tack welding and safely removing lattices structure and dismentaled part stacking properly including Transpotation of old & dismentaling tower parts (81.76 MT) by way of loading on private vehicle from site to Bhadohi store approx 40 KM and unloading, stacking as per direction of S.D.O/J.E.
Rama Power construction
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .