Executive Engineer, Electrical and Mechanical Division, Vadodara
The works of Repair along with dismantling and installation of the 600 Cusecs water discharge capacity Pumping Station at MRBC near NMC Ch 149.81 km for SCF pump no. 10. PS II.
348370
06 of 2026-27
Open
Electrical - Motors and other equipment
Works
Vadodara
19 documents required · 16 mandatory · 3 optional
₹708
Executive Engineer, NPHP, Vadodara
₹2,025
23 Sept 2026
23 Sept 2026
23 Sept 2026
8 Oct 2026
23 Sept 2026
BILL OF QUANTITIES
THIS PAGE HAS BEEN KEPT BLANK
BILL OF QUANTITIES
(1) The bill of Quantities shall be read in conjunction with the Instructions to Bidder, Conditions
of Contract, Technical Specifications and Drawings.
(2) The quantities given in the Bill of Quantities are estimated and provisional, and are given to
provide a common basis for bidding. The basis of payment will be the actual quantities of
work ordered and carried out, as measured by the Contractor and verified by the Engineer
and valued at the rates and prices tendered in the priced Bill of Quantities, where applicable,
and otherwise at such rates and prices as the Engineer may fix within the terms of the
(3) The rates and prices tendered in the priced Bill of Quantities shall, except in so far as it is
otherwise provided under the Contract, include all constructional plant, layout, supervision,
materials, erection, maintenance, insurance, profit, taxes and duties, together with all general
risks, liabilities and obligations set out or implied in the Contract.
(4) The rates and prices shall be quoted entirely in Indian Currency.
(5) A rate or prices shall be entered against each item in the Bill Quantities, whether quantities
are stated or not. The cost of Items against which Contractor has failed to enter a rate or price
shall be deemed to be covered by other rates and prices entered in the Bill of Quantities (in
case of Item rate contract).
(6) The whole cost of complying with the provisions of the Contract shall be included in the
items provided in the priced Bill of Quantities, and where no Items are provided the cost shall
be deemed to be distributed among the rates and prices entered for the related items of Work.
(7) General direction and descriptions of work and materials are not necessarily repeated or
summarized in the Bill of Quantities. References to the relevant sections of the contract
documentation shall be made before entering rates or prices against each item in the Bill of
(8) The method of completed work of payment shall be in accordance with the specification for
Road and Bridge works. For building works specifications for building are to be followed.
(9) Errors will be corrected by the Employer for any arithmetic errors pursuant to Clause 29 of
the Instructions to Bidder.
(10) Rock is defined as all materials which, in the opinion of the Engineer, required blasting, or
the use of metal wedges and sledgehammers, or the use of compressed air drilling for its
removal, and which cannot be extracted by ripping with a tractor of at least 150 kw with a
single rear mounted heavy duty ripper.
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr. )
Item Description of Item (with brief Qty Unit Rate in Amount
No specification and reference to figure
book of specifications)
Dismantling of CSF Pump with ₹ 40000 ₹
1 accessories etc. - -
Installation, testing and ₹ 40000 ₹
2 commissioning of CSF pump with - -
accessories etc.
150 Ton Long Bum Crane for ₹ 80000 ₹
3 Pump Dismantling and Installation. - -
Ms Special Nut, Bolt, Washer, ₹ 32400 ₹
4 Rubberpacking, etc. - -
Transportation (considered for both ₹ 10064 ₹
Total amount in Rs.
Total amount in Rs.
I/We am/are willing to carry out the work at…………………. % above/below percent (Should be
written in figures and words) of the estimated rate mentioned above. Amount of my /our tender
works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………% below Add………% Above
In words In words
(B) For Item Rate Tender
Item Description of Item (with Quantity Unit Rate in figure Amount
No brief specification and
reference to book of In figures In Words
specifications)
Total amount in Rs.
Total amount in Rs.
1. The Contractor shall exhibit a board with detailed specifications and details of work as
directed by the Engineer-In-Charge for which no extra payment shall be made.
2. The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.(if
3. GST and Income tax TDS will be deducted at a source while making payments of bills.
4. In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per
Govt. G.R.: PRC-10/2017 Cement Consumption/16/C Date:11/05/2017 as stated in S.O.R.
therefore in R.C.C. items where there is a change as per actual mix design the cost of
difference of cement consumption have been deducted from the rate of original item at the
rate of input rate mentioned in all the tender.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Approve Draft Tender Document MRBC REpair of Pump 10.pdf
BOQ of Repair Estimate of Pump 10.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .