Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹26.4 LAccepted-AOC | ₹26.4 L | L1 | Accepted-AOC AOC |
| 2 | L2₹26.9 LRejected-Finance NA | NA | NA | 121004 | ₹26.9 L | L2 | Rejected-Finance NON RESPONSIVE |
Tender Value
₹27 L
EMD Value
₹2.7 L
Closing Date
20 Mar 2026, 12:00 pmClosed
EXECUTIVE ENGINEER PD PWD AMROHA
EXECUTIVE ENGINEER PD PWD AMROHA
Construction of road from Berkhera to Primary School
2026_CEMBD_1124603_1
512/E-Tender/25-26 Dated 28-02-2026
Open Tender
Civil Works - Roads
120 days
EXECUTIVE ENGINEER PD PWD AMROHA
Please refer Tender documents.
2 documents required · 2 mandatory
₹854
₹2.7 L
Yes
28 Apr 2026
13 Mar 2026
20 Mar 2026
13 Mar 2026
20 Mar 2026
13 Mar 2026
Construction of sub grade and earthern shoulders with approved material obtained from borrow pits with all lifts and leads transporting to sites, spreading, grading to required slope and compacted to meet requirement of table 300.2 with lead upto 1000 m as per technical specification clause 303.1 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader/ tractor mounted appropriate equipment on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth MORD Specifications 401 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Providing, Laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Construction of un-reinforced plain cement concrete pavement, 15 cm thickness as per design over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M 30 Grade coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side frame work (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including leveling the framework as per drawing), spreading the concrete with shovels, rakes compacted using needle, screed and plate vibrators and finished in continious operation including provision of contraction and expansion, construction joints by providing 12mm thick dura board at the specified spacing, applying debonding strips primer, sealant near approaches to bridge/culvert and construction joints admixtures as approved, curing of concrete slabs for 14-days and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Providing concrete for plain/reinforced concrete P.C.C. Grade M-10 (1:3:6) in open foundations complete as per drawing and technical specifications including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
R.C.C. Work with cement approved coarse sand and 2cm. gauge approved stone grit in proportion of 1:2:4 (M-20) in lintels of doors, windows and sunshades excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I Binding wire and including necessary centering and shuttering etc. Binding wire of supplied by the contractor free of cost including making of drip coarse. including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Mild steel or TMT Bars(Fe-500D grade or higher) or HYSD Bars or iron in plain work such as reinforced concrete or reinforced brick work (when not included in an over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of all steel. including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Laying and compacting dry O.B.B. 40mm. Gauge in foundation in layers of not more than 15cm, thickness including local sand, in ratio 2:1 as per direction of the Engineer-in-Charge including cost of all materials, labour T&P etc. required and including watering & ramming for proper completion of work including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Supply and Layying of 350 mm dia NP3 Hume Pipe including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Laying brick soling layer on prepared sub-grade with brick on end edging according to lines, graded and cross-section shown on the drawing filling joints with sand and earth, spreading 25 mm thick layer of earth over brick soling, watering and rolliing the same with three wheeled road roller 80-100 kN as per Technical Specification Clause 412 including all material, labour, cess, T&P, machinery, and all taxes etc. complete direction by E-I/c but excluding G.S.T.
Maintenance of road for next five year after completion contractor shall be paid total maintenance cost 2.5% of Civil Cost for five year in the form of instalment as below. The payment shall be inclusive of cess but excluding GST payment shall be done as per satisfaction of engineer in charge regarding maintenance work carried out by contractor (Including All Taxes but Excluding cost of GST.) For 1st Year 0.00%
Item No. 12 but for 2nd year 0.25%
Item No. 12 but for 3rd year 0.50%
Item No. 12 but for 4th year 0.75%
Item No. 12 but for 5th year 1.00%
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.26 MB
Tendernotice_2.pdf
PDF • 1.58 MB
BOQ_2095797.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid