Loading…
Loading…
Tender ID
Tender Value
₹10.6 L
EMD Value
₹10,587
Closing Date
10 Apr 2026, 6:10 pmClosed
Executive Engineer, P.H.Works Division, GWSSB, Valsad
KOLVERA HILL STATION WELL CONSTRUCTION Water Supply Scheme Tal.Kaprada Dist.Valsad. Trial bore Drilling of 165mm dia. X up to 90 mtr. Deep, Constructing of well 7.00mt dia X 18.00 mt.depth,Tal.Kaprada Dist.Valsad.
289167
E-Tender No.15 of 2025-26
Open
Civil Works - Water Works
Works
Valsad
6 documents required · 5 mandatory · 1 optional
₹1,500
Executive Engineer, P.H. Works Division, GWSSB, Valsad
₹10,587
27 Mar 2026
27 Mar 2026
27 Mar 2026
10 Apr 2026
27 Mar 2026
NAME OF WORK :-
PART - I Trial bore Drilling of 165mm dia. X up to 90.00 mtr. Deep
PART - II Constructing of well 7.00mt dia X 18.00 mt.depth
Schedule showing the approximate item wise quantity More/Less to be carried out for above mentioned work
Estimate Cost Put Tender Rs. TIME LIMIT
1058706.06 3 MONTHS
Qty. Unit Items Rate Per Amount
PART - I Trial bore Drilling of 165mm dia. X
up to 30.00 mtr. Deep
Drilling of 215 mm dia. nacked bore in loose and
90 mtr. alluvial strata &165mm dia. Bore hard & rocky 272 mtr.
Providing & fixing of 175mm dia. 'U'PVC Casing
20 mtr. 906 mtr.
Pipe "CS" type Pipe. IS-12818
Geohydrological ground water investigations with
1 Job vehicle charges. 3571 Job
1 Job Water Chemical Analysis charge 600 Job
Part - I Total Rs.
PART - II Constructing of well 7.00mt dia X
Excavation for well including Removing and
spreading the excavted stuff as directed with lead
i) 0 to 1.50 mt.Depth
87.09 M3 (a) In all sorts of soil incl.soft murrum. 140.80 M3
ii) 1.50 mt to 3.00 mt Depth
87.09 M3 (a) In Hard murrum 218.90 M3
iii) 3.00 mt to 4.50 mt Depth
87.09 M3 (a) In Soft rock 330.00 M3
iv) 4.50 mt to 6.00 mt Depth
58.06 M3 (a) In Soft rock 348.70 M3
29.03 M3 (b) In hard rock with blasting & chiselling 777.70 M3
29.03 M3 (b) Extra for dewatering in all strata. 47.30 M3
v) 6.00 mt to 7.50 mt depth.
57.70 M3 (a) In hard rock with blasting & chiselling 798.60 M3
57.70 M3 (b) Extra for dewatering in all strata. 66.00 M3
vi) 7.50 mt to 9.00 mt depth
57.70 M3 (a) In hard rock with blasting & chiselling 822.80 M3
57.70 M3 (b) Extra for dewatering in all strata. 84.70 M3
vii) 9.00 mt to 10.50 mt depth
57.70 M3 (a) In hard rock with blasting & chiselling 856.90 M3
57.70 M3 (b) Extra for dewatering in all strata. 105.60 M3
viii) 10.50 mt to 12.00 mt depth
57.70 M3 (a) In hard rock with blasting & chiselling 893.20 M3
57.70 M3 (b) Extra for dewatering in all strata. 122.10 M3
ix) 12.00 mt to 13.50 mt depth
57.70 M3 (a)In hard rock with blasting & chiselling 928.40 M3
57.70 M3 (b) Extra for dewatering in all strata. 152.90 M3
x) 13.50 mt to 15.00 mt depth
57.70 M3 (a)In hard rock with blasting & chiselling 965.80 M3
57.70 M3 (b) Extra for dewatering in all strata. 204.60 M3
xi) 15.00 mt to 16.50 mt depth
57.70 M3 (a)In hard rock with blasting & chiselling 1001.00 M3
57.70 M3 (b) Extra for dewatering in all strata. 210.10 M3
xi) 16.50 mt to 18.00 mt depth
57.70 M3 (a)In hard rock with blasting & chiselling 1037.30 M3
57.70 M3 (b) Extra for dewatering in all strata. 239.80 M3
Providing & casting in situ C.C.in grade M-20
(proportions as per mix design or as per Table 9 of
IS456 2000 in masses by weight batching) using
granite, quartzite trap metal of size 6 mm to 20 mm
for RCC work including scaffolding centering
formwork needle vibrated consolidation curing comp.
up to 6 meter depth or height ( excluding cost of
reinforcement and neat finishing ) with centering and
shuttering / desshuttering etc. comp. for structure for
other than water retainig.(Below G.L.)
Providing & casting in situ C.C.in grade M-20
(proportions as per mix design or as per Table 9 of
IS456 2000 in masses by weight batching) using
granite, quartzite trap metal of size 6 mm to 20 mm
for RCC work including scaffolding centering
formwork needle vibrated consolidation curing comp.
up to 6 meter depth or height ( excluding cost of
reinforcement and neat finishing ) with centering and
shuttering / desshuttering etc. comp. for structure for
other than water retainig.(Below G.L.)
33.33 M3 b) Vertical Wall-M20 7456.90 M3
Providing & casting in situ mass cement concrete in
grade M-10 (approx, corresp.to. Prop. 1:3:6) using
granite, quartzite trap metal of size 12 mm to 25 mm
incl. consolidation curing etc. comp.
3.64 M3 c) CC of M10 For PCC 4028.20 M3
Supplying cutting, bending, binding and placing in
position steel bars as per plan & design as per ISS
2502 incl. Cost of steel and binding wire for
reservoirs/ structures only including lift up to 6 mtr.
Height or depth below G.L. Do-Thermo mechanically
treated (TMT)bars Fe-415 grade for all diameters.
27.31 sqm a) Cement plaster 20 mm thick rough coat with c. m. 1:3 incl
curing etc comp. for4476.34
Providing & fixing at site of work with railway
freight,loading,unloading,carting etc.comp. Such as
joists,channle,angle iron, plate,rails
0.36 Qtl etc.complete.M.S. Section 7421.33 Qtl
Filling with available excavated earth(Excluding rock)
in trenches plinth sides of foundation etc. in layers
not exeeding 20 cm in depth consolidating earth
83.20 M3 deposited layers by raming and watering 79.54 M3
Providing & fixing 20 cm. X 15cm. X 2.5 cm. Thick
Plate of marble stone set in CM 1:4 including
1.00 No finishing & engraving latter etc. Comp. 259.64 No
Part - II Total Rs.
Part - I Total Rs.
Part - II Total Rs.
( Rupees Ten Lacs Fifty Eight Thousand Seven Hundred Six And Six Paise Only)
I / We am/are willing carry above said work at __________ percentage ___________________
(should be written in figure and words) above/below the put to tendered rates maintioned above
.Amount of my tender working out as per under :- Rs.______________
Estimate amount Estimate amount
Put to tender Rs. Put to tender Rs.
Deduct % below Rs. Add % above Rs.
Net Rs. Net Rs.
In words Rs. In words Rs.
(Please strick out which ever is not applicable)
1. All the work shall be carried out as per P. W. D. Hand book vol. I & II and other specification.
2. All the columns in schedule “B” should be filled in the total of the entry in the last column.
3. Rates quoted shall be for the completed items of work and shall include clearance of site
Signature of Executive Engineer, Deputy Executive Engineer
the Contractor. P.H.W.Division, P. H. Sani. Sub. Division
G.W.S.S.Board, Valsad G.W.S.S.Board, Dharampur
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Circulars-1.zip
ZIP
Circulars-2.zip
ZIP
05. Affidavit.pdf
Minimum wages rates for Labor.pdf
Standard Bid Document.pdf
SD-EMD GR 03-May-2025.pdf
01. Tender Notice Kolvera Hill Station.pdf
02. B-1 Booklet Kolvera Hill Station.pdf
03. Sch -A Kolvera Hill Station final.pdf
04. Sch -B Kolvera Hill Station.pdf
05. Specification Kolvera Hill Station.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .