Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹39.0 LAccepted-Finance | ₹39.0 L | L1 | Accepted-Finance ACCEPTED FOR L1 |
| 2 | L2₹39.1 L+₹9,264.66 (0.24%)Accepted-Finance KOLLAM KOLLAM KERALA | ₹39.1 L+₹9,264.66 (0.24%) | L2 | Accepted-Finance Second bidder. Kept in abeyance till the execution of agmnt by the First Bidder |
| Sl No | Description | Qty | Unit | VINOD. G L2 | HARIPRASAD P L1 |
|---|---|---|---|---|---|
| 1.00GENERAL-NKP 133/2025-26-Construction of New Building for JAK Kulanada Main Center- General Civil Work | |||||
| 1.00 | Earth work in excavation by mechanical means (Hydraulic excavator) /manual means
in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),
including dressing of sides and ramming of bottoms, lift up to 1.5 m, including
getting out the excavated soil and disposal of surplus excavated soil as directed,
within a lead of 50 m.All kinds of soil | 77.25 | cum | 325 ₹25,105.28 | 310 ₹23,946.57 Lowest |
| 1.00 | Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3
coarse sand (zone-III) derived from natural sources : 6 graded
stone aggregate 40 mm nominal size derived from natural sources) | 22.48 | cum | 7,530 ₹1,69,244.28 Lowest | 8,100 ₹1,82,055.6 |
| 1.00 | Random rubble masonry with hard stone in foundation and plinth including levelling
up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate
20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse
sand) | 62.05 | cum | 7,510 ₹4,66,018.03 | 7,400 ₹4,59,192.2 Lowest |
| 1.00 | Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size derived from natural sources) | 7.07 | cum | 9,450 ₹66,783.15 | 9,300 ₹65,723.1 Lowest |
| 1.00 | Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers | 101.58 | sqm | 690 ₹70,087.44 | 610 ₹61,961.36 Lowest |
| 1.01 | Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform | 137.06 | sqm | 621 ₹85,116.74 Lowest | 890 ₹1,21,986.96 |
| 1.01 | Reinforced cement concrete work in beams, suspended floors, roofs, having slope up
to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills,
staircases and spiral stair cases up to floor five level excluding the cost of centering,
shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone
III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size
derived from natural sources). | 21.34 | cum | 12,100 ₹2,58,274.5 Lowest | 13,100 ₹2,79,619.5 |
| 1.01 | Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more | 2,602.26 | kilogram | 110 ₹2,86,248.6 | 98 ₹2,55,021.48 Lowest |
| 1.01 | Solid block masonry using pre cast solid blocks ( Factory made) of size 30x20x20cm
or nearest available size confirming to IS 2185 Part I of 1979 for super structure up to
floor two level thickness 20cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc
complete | 48.48 | cum | 6,555 ₹3,17,773.29 Lowest | 7,050 ₹3,41,769.9 |
Tender Value
₹44.0 L
EMD Value
₹50,000
Closing Date
8 Jun 2026, 6:00 pmClosed
PROJECT MANAGER
Project Manager District Nirmithi Kendra,R.D.O Office Building First Floor Adoor Pathanamthitta
GENERAL-NKP 133/2025-26-Construction of New Building for JAK Kulanada Main Center- General Civil Work
2026_DNK_853437_1
09/TS/DNK/2025-26
Open Tender
Civil Works - Buildings
Item Rate
365 days
KULANADA
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
Yes
₹50,000
Yes
19 Jun 2026
30 May 2026
10 Jun 2026
30 May 2026
8 Jun 2026
30 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1GENERAL-NKP 133/2025-26-Construction of New Building for JAK Kulanada Main Center- General Civil Work | |||||
| 1.001 | Earth work in excavation by mechanical means (Hydraulic excavator) /manual means
in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan),
including dressing of sides and ramming of bottoms, lift up to 1.5 m, including
getting out the excavated soil and disposal of surplus excavated soil as directed,
within a lead of 50 m.All kinds of soil | 0.8 | cum | 359.72 | ₹287.42 |
| 1.002 | Providing and laying in position cement concrete of specified grade excluding the
cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3
coarse sand (zone-III) derived from natural sources : 6 graded
stone aggregate 40 mm nominal size derived from natural sources) | 1 | cum | 8,364.57 | ₹8,356.21 |
| 1.003 | Random rubble masonry with hard stone in foundation and plinth including levelling
up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate
20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse
sand) | 0.2 | cum | 8,343.49 | ₹1,660.35 |
| 1.004 | Providing and laying in position specified grade of reinforced cement concrete,
excluding the cost of centering, shuttering, finishing and reinforcement - All work up
to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm
nominal size derived from natural sources) | - | cum | 10,488.77 | - |
| 1.005 | Centering and shuttering including strutting, etc. and removal of form for:Lintels,
beams, plinth beams, girders bressumers and cantilevers | 0.4 | sqm | 762.88 | ₹304.39 |
| 1.006 | Centering and shuttering including strutting, etc. and removal of form for:Suspended
floors, roofs, landings, balconies and access platform | 0.6 | sqm | 961.24 | ₹575.78 |
| 1.007 | Reinforced cement concrete work in beams, suspended floors, roofs, having slope up
to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills,
staircases and spiral stair cases up to floor five level excluding the cost of centering,
shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone
III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size
derived from natural sources). | 1 | cum | 13,442.14 | ₹13,428.7 |
| 1.008 | Steel reinforcement for R.C.C work including straightening, cutting, bending, placing
in position and binding all complete upto plinth levelThermo - Mechanically Treated
bars of grade Fe-500D or more | - | kilogram | 112.43 | - |
| 1.009 | Solid block masonry using pre cast solid blocks ( Factory made) of size 30x20x20cm
or nearest available size confirming to IS 2185 Part I of 1979 for super structure up to
floor two level thickness 20cm and above in: CM 1:6 ( 1 cement : 6 coarse sand) etc
complete | - | cum | 7,279.03 | - |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
finance_1442330.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.05 MB
Tendernotice_2.pdf
PDF • 0.03 MB
Tendernotice_3.pdf
PDF • 0.02 MB
BOQ_1442330.xls
BOQ • 0.40 MB
FOT.pdf
Tender Documents • 0.02 MB
AFFI.pdf
Tender Documents • 0.06 MB
SBD.pdf
Tender Documents • 0.99 MB
PAG.pdf
Tender Documents • 0.07 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .