Loading…
Loading…
Tender Value
₹44.3 L
EMD Value
₹88,500
Closing Date
3 Sept 2026, 3:00 pm
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Revenue
TENDER 1
137 conditions · 4 needing a document upload
The following documents should be submitted along with the Tender:
List of Personnel Organization available on hand and proposed to be engaged for the subject work as per format given in Annexure-A
List of works completed in Government/Semi-Government (fully owned by Govt.) departments in the last three financial years giving description of work. Organization for whom executed, approximate value of contract at the time of award, date of award and date of schedule completion and final value of contract should also be given as per format given in Annexure-B
List of work on hand indicating description of work, contract value, approximate value of balance work yet to be done and date of award as per format given in Annexure-C
Tenderers personnel information in the format enclosed as annexure -D
(Mandatory) : Valid Class A ECL (Electrical Contractor License) issued in favor of Firms/tenderers only. Tenders submitted with Class A ECL issued in the name of other firms/tenderers will be summarily rejected. In case the Class A'ECL is not valid on the date of opening of tender, details of renewal should be submitted.
(Mandatory) : Certificate of information regarding employment/partnership etc. Of retired railway employees with the tenderer as per format given in Annexure-E.
(Mandatory): Please submit a certificate (as furnished in tender document) for affidavit for verification / confirmation of the documents submitted for compliance of eligibility / qualifying criteria. Non submission of the certificate, or submission of certificate either not properly filled in, or in a format other than the prescribed format shall lead to summary rejection of your offer. In addition to Annexure-V, in case of other than Company/Proprietary firm. Annexure -V(A) shall also be submitted by the each member of a Partnership Firm / Joint Venture (JV) / Hindu Undivided Family (HUH / Limited Liability Partnership (LLP) etc, as the case may be. Non submission of above certificate(s) by the bidder shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent upon the tenderer to identify, state and submit the supporting documents duly self attested/digitally signed by which they/he is qualifying the Qualifying Criteria mentioned in the Tender Document
(Mandatory): CONSTITUTION OF THE TENDERER'S FIRM: The tenderer shall clearly specify whether the tender is submitted on his own (Proprietary Firm) or on behalf of a Partnership Firm / Company / Joint Venture (JV) / Registered Society / Registered Trust / Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc. The tenderer(s) shall enclose the attested copies of the constitution of their concern, and copy of PAN Card along with their tender. Tender Documents in such cases are to be signed by such persons as may be legally competent to sign them on behalf of the firm, company, association, trust or society, as the case may be.a) Sole Proprietorship Firm: (i)All documents in terms of Para 10 of the GCC 2022 Tender Form (Second Sheet) above.b) HUF: (i)A copy of notarized affidavit on Stamp Paper declaring that he who is submitting the tender on behalf of HUF is in the position of 'Karta' of Hindu Undivided Family (HUF) and he has the authority, power and consent given by other members to act on behalf of HUF. (ii)All other documents in terms of Para 10 of the GCC 2022 Tender Form (Second Sheet) above.c) Partnership Firm: (i)All documents as mentioned in para18 of the GCC 2022 Tender Form (Second Sheet). d) Joint Venture (JV): All documents as mentioned in para 17 of the GCC 2022 Tender Form (Second Sheet).e) Company registered under Companies Act2013: (i)The copies of MOA (Memorandum of Association) / AOA (Articles of Association) of the company (ii)A copy of Certificate of Incorporation (iii)A copy of Authorization/Power of Attorney issued by the Company (backed by the resolution of Board of Directors) in favour of the individual to sign the tender on behalf of the company and create liability against the company. (iv)All other documents in terms Para 10 of the GCC 2022 Tender Form (Second Sheet) above.f) LLP (Limited Liability Partnership): (i)A copy of LLP Agreement (ii)A copy of Certificate of Incorporation (iii)A copy of Power of Attorney/Authorization issued by the LLP in favour of the individual to sign the tender on behalf of the LLP and create liability against the LLP. (iv)An undertaking by all partners of the LLP that they are not blacklisted or debarred by Railways or any other Ministry / Department of the Govt. of India from participation in tenders / contracts as on the date of submission of bids, either in their individual capacity or in any firm/LLP or JV in which they were / are partners/members. Concealment / wrong information in regard to above shall make the contract liable for determination under Clause 62 of the Standard General Conditions of Contract. (v)All other documents in terms of Para 10 of the GCC 2022 Tender Form (Second Sheet).g) Registered Society & Registered Trust: (i)A copy of Certificate of Registration (ii)A copy of Memorandum of Association of Society/Trust Deed (iii)A copy of Power of Attorney in favour of the individual to sign the tender documents and create liability against the Society/Trust. (iv)A copy of Rules & Regulations of the Society (v)All other documents in terms of Para 10 of the GCC 2022 Tender Form (Second Sheet) above.
If it is NOT mentioned in the submitted tender that tender is being submitted on behalf of a Sole Proprietorship firm / Partnership firm / Joint Venture /Registered Company etc., then the tender shall be treated as having been submitted by the individual who has signed the tender.
After opening of the tender, any document pertaining to the constitution of Sole Proprietorship Firm / Partnership Firm / Registered Company/Registered Trust / Registered Society / HUF etc. shall be neither asked nor considered, if submitted. Further, no suo moto cognizance of any document available in public domain (i.e., on internet etc.) or in Railway's record/office files etc. will be taken for consideration of the tender, if no such mention is available in tender offer submitted.
A tender from JV / Partnership firm etc. shall be considered only where permissible as per the tender conditions.
The Railway will not be bound by any change in the composition of the firm made subsequent to the submission of tender. Railway may, however, recognize such power of attorney and changes after obtaining proper legal advice, the cost of which will be chargeable to the Contractor.
The tenderer whether sole proprietor / a company or a partnership firm / joint venture (JV) / registered society / registered trust / HUF etc if they want to act through agent or individual partner(s), should submit along with the tender, a copy of power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person specifically authorizing him/them to submit the tender, sign the agreement, receive money, co-ordinate measurements through contractor's authorized engineer, witness measurements, sign measurement books, compromise, settle, relinquish any claim(s) preferred by the firm and sign "No Claim Certificate" and refer all or any disputes to arbitration. The above power of attorney shall be submitted even if such specific person is authorized for above purposes through partnership deed / Memorandum of Understanding / Article of Association or such other document, failing which tender is liable to be rejected.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
SECURITY MONEY:- The successful tenderer shall have to deposit security money @ 5.0% of total value of the contract awarded for proper execution of the contract. The security deposit shall be recovered @ 6.0% from the bill amount till the full SD is released. The amount of earnest money / security deposit if any refundable to the tenderer for any other work accepted and completed by him /them, they can not be set off towards the earnest money /security deposit due against this Tender. The earnest money/security deposit receipts of Banks should be placed and hypothecated in favour of the PFA/ S. E. C. Rly /BSP.
Security Deposit: The Security Deposit shall be 5% of the contract value. The Bid Security submitted by the Contractor with his tender will be retained/encashed by the Railways as part of security for the due and faithful fulfillment of the contract by the Contractor. Provided further that, if Contractor submits the Cash or Term Deposit Receipt issued from a Scheduled commercial bank of India or irrevocable Bank Guarantee Bond from a Scheduled commercial bank of India, either towards the Full Security Depositor the Part Security Deposit equal to or more than Bid Security, the Railway shall return the Bid Security, to the Contractor. Balance of Security Deposit may be deposited by the Contractor in cash or Term Deposit Receipt issued from Scheduled commercial bank of India or irrevocable Bank Guarantee bond issued from Scheduled commercial bank of India, or may be recovered at the rate of 6% of the bill amount till the full Security Deposit is recovered. Provided also that in case of defaulting Contractor, the Railway may retain any amount due for payment to the Contractor on the pending "on account bills" so that the amounts so retained (including amount guaranteed through Performance Guarantee) may not exceed 10% of the total value of the contract. The Irrevocable Bank Guarantee submitted towards Security deposit shall be initially valid up to the stipulated date of Maintenance period plus 60 days and shall be extended from time to time, depending upon extension of contract granted in terms of Clause 17A and 17B of the Standard General Conditions of Contract.
The Tender Committee shall not be bound to accept the lowest BID and reserves the right to accept or reject any tender without assigning any reason to the tenderer. However negotiation may be made with the lowest valid and eligible tenderer as regards the rates or any other issue.
The successful Tenderer shall have to UNDERTAKE THE WORK at the rate quoted and subject to acceptance of his tender by the Sr.DEE (RS&G)/ S.E.C. Railway, Bilaspur which would constitute the contract binding between the parties, subject to execution of written agreement as stipulated, with the President Of India acting through the Sr.DEE (RS&G)/ S. E. C. Railway, Bilaspur for carrying out the work according to the conditions of the contract. In the event of any tenderer whose tender is accepted shall refuse to execute the contract documents as herein before provided, the Railway may determine that such tenderer has abandoned the contract and there upon his tender and acceptance thereof shall be treated as cancelled and the Railways shall be entitled to forfeit the full amount of security deposit and to recover the liquidated damages for such default.
Bid Security: (1) (a) The tenderer shall be required to submit the Bid Security with the tender for the due performance with the stipulation to keep the offer open till such date as specified in the tender, under the conditions of tender. The Bid Security shall be as under: (1) For all works : 2% of the estimated cost of the work.
Note: (i) The Bid Security shall be rounded off to the nearest 100. This Bid Security shall be applicable for all modes of tendering. (ii) Any firm recognized by Department of Industrial Policy and Promotion (DIPP) as 'Startups' shall be exempted from payment of Bid Security detailed above. (iii) Labour Cooperative Societies shall submit only 50% of above Bid Security detailed above.
(b) It shall be understood that the tender documents have been issued to the tenderer and the tenderer is permitted to tender in consideration of stipulation on his part, that after submitting his tender he will not resile from his offer or modify the terms and conditions thereof in a manner not acceptable to the Engineer. Should the tenderer fail to observe or comply with the said stipulation, the aforesaid amount shall be liable to be forfeited to the Railway. (c) If his tender is accepted, this Bid Security mentioned in sub para (a) above will be retained as part security for the due and faithful fulfillment of the contract in terms of Clause 16 of the Standard General Conditions of Contract. The Bid Security of other Tenderers shall, save as herein before provided, be returned to them, but the Railway shall not be responsible for any loss or depreciation that may happen thereto while in their possession, nor be liable to pay interest thereon.
(2) The Bid Security shall be deposited either in cash through e- payment gateway or submitted as Bank Guarantee bond from a scheduled commercial bank of India or as mentioned in tender documents. The Bank Guarantee bond shall be as per Annexure- VIA and shall be valid for a period of 90days beyond the bid validity period.
(3) In case, submission of Bid Security in the form of Bank Guarantee, following shall be ensured: i. A scanned copy of the Bank Guarantee shall be uploaded on e-Procurement Portal (IREPS) while applying to the tender. ii. The original Bank Guarantee should be delivered in person to the official nominated as indicated in the tender document within 5 working days before closing date for submission of bids. iii. Non submission of scanned copy of Bank Guarantee with the bid on e-tendering portal (IREPS) and/or non submission of original Bank Guarantee within the specified period shall lead to summary rejection of bid. iv. The Tender Security shall remain valid for a period of 90 days beyond the validity period for the Tender. v. The details of the BG, physically submitted should match with the details available in the scanned copy and the data entered during bid submission time, failing which the bid will be rejected vi. The Bank Guarantee shall be placed in an envelope, which shall be sealed. The envelope shall clearly bear the identification "Bid for the ***** Project" and shall clearly indicate the name and address of the Bidder. In addition, the Bid Due Date should be indicated on the right hand top corner of the envelope. vii. The envelope shall be addressed to the officer and address as mentioned in the tender document. viii. If the envelope is not sealed and marked as instructed above, the Railway assumes no responsibility for the misplacement or premature opening of the contents of the Bid submitted and consequent losses, if any, suffered by the Bidder.
Force Majeure Clause: If at any time, during the continuance of this contract, the performance in whole or in part by either party of any obligation under this contract shall be prevented or delayed by reason of any war, hostility, acts of public enemy, civil commotion, sabotage, serious loss or damage by fire, explosions, epidemics/pandemics, strikes, lockouts or acts of God (hereinafter, referred to events) provided, notice of the happening of any such event is given by either party to the other within 30 days from the date of occurrence thereof, neither party shall by reason of such event, be entitled to terminate this contract nor shall either party have any claim for damages against the other in respect of such non-performance or delay in performance, and works under the contract shall be resumed as soon as practicable after such event has come to an end or ceased to exist, and the decision of the Engineer as to whether the works have been so resumed or not shall be final and conclusive, PROVIDED FURTHER that if the performance in whole or in part of any obligation under this contract is prevented or delayed by reason of any such event for a period exceeding 120 days, either party may at its option terminate the contract by giving notice to the other party.
2% Income Tax will be deducted from the monthly bills. All other taxes including Service tax as applicable from time to time shall be borne by the contractor. In the EVENT OF FAILURE of the contractor to execute the agreement and/ or to take up the work on the date and time specified in the letter of acceptance, the security deposit is liable to be forfeited.
The Railway Administration reserves the right either not to award any of all the works to the contractor to increase or decrease the value of works without assigning any reasons. Contractor will not be entitled to any compensation whatsoever in such case.No INTEREST shall be payable either on the earnest money or on security deposit or PG.
EMPLOYMENT OF STAFFS: - The contractor shall employ such persons who have been working with good record in the same field on the existing terms and conditions or on such other terms and conditions which are more beneficial.
Should a tenderer or a contractor being an individual on the list of approved contractors, have a relative employed in Gazetted capacity in the Electrical Engineering department of South East Central Railway or in the case of partnership firm or company incorporated under the Indian Company Law should a partner or a relative of the partner or a share holder of a relative of the share holder be employed in Gazetted capacity in the Electrical Engineering Department of South East Central Railway ; the authority inviting tenders shall be informed of the fact at the time of submission of tenders , failing which the tender may be rejected or if such fact subsequently comes to light then the contract may be in accordance with the provision in the General conditions of contract.
It shall be understood that every endeavor has been made to avoid any error which can Materially affect the basis of the tender and the successful tender shall take open himself and provide for the risk of any error which may subsequently may be discovered and shall not make subsequently claim on account thereof.
In case of any problem with the portal is faced while filling the e-tender, Tenderers are advised to contact with the Helpdesk of IREPS portal who will render all help and assistance related with the website and portal except that related with the details of the tender. Railway will not take any responsibility for non- participation in the e-tender online for the reasons related to the website and portal or server etc beyond the control of railways.
The Schedules of Works is also available seperately in the website online and Rates are to be quoted online and submitted online duly signed digitally.
Opening of e-tender online:- The e-tenders will be opened online using the IREPS portal. No representative is required to be present for opening of tender and taking notes of rates quoted and ranking as the complete details of rates etc. of all the bidders shall be available to the bidders in the website after the opening of the tender.
In case the date of closing mentioned in the Notice Inviting Tender is declared a holiday/bandh/strike etc. on any account, the date of closing tender online will not be changed as the application in the website of IREPS does not permit submission of any offer after closing date and time of the tender. However, opening of tenders online will be on any convenient day after the closing date/time of tenders.
SUBMISSION OF DOCUMENTS IN SUPPORT OF ELIGILIITY CRITERIA- All documents in support of fulfilment of the eligibility criteria with respect to completion of Similar nature of work for Technical Eligibility Criteria and Total gross contractual receipt value for Financial Eligibility Criteria should be uploaded online in the website with scanned copy in pdf format at the time of tender bidding with details showing in the Annexure(s).
I/We have read the various conditions to tender attached hereto and agree to abide by the said conditions. I/We also agree to keep this tender opened for acceptance for a period of 45 (forty five) days from the date fixed for opening the same and in default thereof, I/we will be liable for forfeiture of my/our Earnest Money. I/We offer to do the work for South East Central Railway, at the rates quoted in the attached schedule and hereby bind myself/ourselves to complete the work in all respects within as mentioned in NIT from the date of issue of letter of acceptance of the tender.
Instructions to tenderers and conditions of tender: - The following documents form part of Tender/Contract:
Tender forms- First sheet and second sheet.
Special conditions/specifications
Standard General Conditions of Contract-April-2022 and standard specification for materials and works (IRUSS-2019) as amended/corrected upto latest correction slips, copies of which can be seen in the office of Sr. Divisional Electrical Engineer(RS&G), South East Central Railway on payment of prescribed charges .
(b) The Tenderer(s) shall keep the offer open for a minimum period of Forty Five days from the date of opening of the tender. It is understood that the tender documents has been sold / issued to the Tenderer(s) and the Tenderer(s), is/are permitted to tender in consideration of the stipulation on his/their part that after submitting his/their tender subject to the period being extended further, if required by mutual agreement from time to time, he will not resile from his offer or modify the terms and conditions thereof in a manner not acceptable to the South East Central Railway, Should the Tenderer fail to observe or comply with the foregoing stipulation, the amount deposited, as Earnest money for the due performance of the above stipulation shall be forfeited to the Railway.
Performance Guarantee: The procedure for obtaining Performance Guarantee is outlined below: (a) The successful bidder shall have to submit a Performance Guarantee (PG) within 21 (Twenty one) days from the date of issue of Letter of Acceptance (LOA). Extension of time for submission of PG beyond 21 (Twenty one) days and upto 60 days from the date of issue of LOA may be given by the Authority who is competent to sign the contract agreement. However, a penal interest of 12% per annum shall be charged for the delay beyond 21(Twenty one) days, i.e. from 22ndday after the date of issue of LOA. Further, if the 60thday happens to be a declared holiday in the concerned office of the Railway, submission of PG can be accepted on the next working day. In all other cases, if the Contractor fails to submit the requisite PG even after 60 days from the date of issue of LOA, In case contract is terminated railway shall be entitled to forfeit EMD and other dues payable to the contractor against that particular contract, subject to maximum of PG amount. The failed Contractor shall be debarred from participating in re-tender for that work.
(b) The successful bidder shall submit the Performance Guarantee (PG) in any of the following forms, amounting to 5% of the original contract value and additional performance guarantee as per clause 16(4) in any of the following forms:- (i) A deposit of Cash; (ii) Irrevocable Bank Guarantee; (iii) Insurance Surety Bond as per Annexure-XVII (annexure as per GCC April 2022) Note: In case of extension of date of completion, selected bidder needs to submit extended insurance surety Bond/fresh insurance surety bond/fresh performance security, in any form as given above, before expiry of existing insurance surety bond. (iv) Government Securities including State Loan Bonds at 5% below the market value; (v) Pay Orders and Demand Drafts tendered by any Scheduled Commercial Bank of India; (vi) Guarantee Bonds executed or Deposits Receipts tendered by any Scheduled Commercial Bank of India; (vii) Deposit in the Post Office Saving Bank; (viii) Deposit in the National Savings Certificates; (ix) Twelve years National Defence Certificates; (x) Ten years Defence Deposits; (xi) National Defence Bonds and (xii) Unit Trust Certificates at 5% below market value or at the face value whichever is less. Also, FDR in favour of FA&CAO (free from any encumbrance) may be accepted. (c) The Performance Guarantee shall be submitted by the successful bidder after the Letter of Acceptance (LOA) has been issued, but before signing of the contract agreement. This P.G. shall be initially valid upto the stipulated date of completion plus 60 days beyond that. In case, the time for completion of work gets extended, the Contractor shall get the validity of P.G. extended to cover such extended time for completion of work plus 60 days. (d) The value of PG to be submitted by the Contractor is based on original contract value and shall not change due to subsequent variation(s) in the original contract value. (e) The Performance Guarantee (PG) shall be released after physical completion of the work based on 'Completion Certificate' issued by the competent authority stating that the Contractor has completed the work in all respects satisfactorily. (f) Whenever the contract is rescinded, the Performance Guarantee already submitted for the contract shall be encashed. (g) The Engineer shall not make a claim under the Performance Guarantee except for amounts to which the President of India is entitled under the contract (not withstanding and/or without prejudice to any other provisions in the contract agreement) in the event of: (i) Failure by the Contractor to extend the validity of the Performance Guarantee as described herein above, in which event the Engineer may claim the full amount of the Performance Guarantee. (ii) Failure by the Contractor to pay President of India any amount due, either as agreed by the Contractor or determined under any of the Clauses/Conditions of the Agreement, within 30 days of the service of notice to this effect by Engineer. (iii) The Contract being determined or rescinded under clause 62 of these conditions.
Note: Online BG submission as per Railway board letter no : No.2020/ACII/9/6/e dt.07.04.2022 enclosed at annexure. The matter regarding online verification of BGs by the vendors /contractors through Structured Financial Messaging System (SFMS) platform in association with SBI was under consideration from quite some time. Now, this facility is available on IPAS. In order to avail this facility, it is necessary that following details 18.1.1 may be entered into SFMS while issuing Bank Guarantees by vendors/contractors in favour of Railways: IFSC CODE: SBIN000RAIL IFSC TYPE:BRANCH BANK NAME:STATE BANK OF INDIA BRANCH NAME:RAIL CITY NAME:NAVI MUMBAI ADDRESS: SECTOR-11,CBD BELAPUR, NAVI MUMBAI DISTRICT:NAVI MUMBAI STATE: MAHARASHTRABG ENABLED: YES* This IFSC Code is only valid for BG issuance and verification in favour of Railways.
Certificates duly attested and testimonials regarding contracting experience for the type of job for which tender is invited with list of works carried out in the past.
Obligation of the contractors :- The contractor shall fully comply with the following enactments:
(a)Contract labour (R & A) Act, 1970 and rules formed there in under the Central labour Department.(b)Wage Rates not less than that notified by Central/State labour Department from time to time.(c)Payment of wages Act.(d)ESI Act, 1948 and contribution of Employer/Contractor @ 4.75% of wages.(e)EPF Act, 1952 and contribution of Employer/Contractor @ 13.61% of wages.(f)workman's compensation Act, 1923.(with latest amendments.)(g)SECR instructions as issued from time to time in regard to working hours, holidays, or any other statutory provision.
The contractor shall obtain license from the assistant labour commissioner (Central), or appropriate government if he engages twenty or more workmen only. The contractor shall observe weekly rest day according to normal norms
Contractor shall obtain complete bio-data of the labour employment certificate and antecedent verification in the prescribed form for each labour and supervisor engaged by him and shall submit the same to the personnel department/IR section through the contract executing officers before commencement of the work.
The contractor shall make himself or his representative available at the work spot everyday during execution of work, for effective supervision
Non-compliance of any provision under the act/rule/instructions/guidelines shall make the contractor liable for penal action including termination of contract
Contractor shall in his absence keep competent agent constantly on the works and any directions or explanations given by the Contract Signing Officer or his representative to such agent shall be held to have been given to the contractor himself.
The contractor shall give all notices required by the acts, regulation, By laws, legal acts and pay all fees in connection therewith unless and other wise arranged and decided in writing with SECR. In all such cases, contractor shall protect and indemnify SECR against any claim or liability arising from or based on the violation of any such laws, ordinance, regulations, orders, decrees or attachment either by himself or by his employees.
It shall be contractors sole responsibility to protect the public and his employees against accident from any cause and provide required safety equipments and shall indemnify SECR against any claims for damages for injury to the person or property resulting from any such accidents and losses shall, where the provisions of the workmen's compensation Act apply, take steps to properly insure against any claims there under.
The contractor shall keep his work place clean and safe to avoid injuries to men and damage to finished products/equipments.
On the occurrence of an accident, which result in the death of any of the workmen employed by the contractor or which is so serious as to be likely to result in the death of any such workmen, the contractor shall within 24 hours of the happening of such an accident intimate in writing to the Principal Employer or official in charge of the work.
The contractor shall ensure abidance by all the labour laws especially including contract labour (R&A) Act, payment of wages Act workmen's compensation Act, minimum wages Act, ESI Act and provident fund act as amended from time to time, and contributes @ 4.75% of wages in favour of Labours.
The contractor shall comply with provident fund Act as amended from time to time either through PF code allotted to him or by the code provided by PF Department where 20 or more labours are engaged and contributes @ 13.61% of wages in favour of Labours.
The contractor should engage only those labourers who shall be more than 18(eighteen) years of age.
The contractor shall provide the required safety equipment to the labours engaged by him
Contractor shall issue Employment Card as per status to all labour and supervisors covered under the job work contract.
Contractor must ensure that payment of wages to workmen should be made in presence of representative of Principal Employer or in presence of Staff welfare inspector.
The tenderer(s) shall quote his/their rates as a percentage above or below the schedule of rates of the South East Central Railway as applicable to Bilaspur Division except where he/they are required to quote item rates and must tender for all the items shown in the schedule of approximate quantities attached. The quantities shown in the attached schedule are given as guide and are approximate only and are subject to variation according to the needs of the Railway. The Railway does not guarantee work under each item of the schedule.
Tenders containing erasures and/or alterations of the tender documents are liable to be rejected. Any corrections made by the Tenderer (S) in his/their entries must be attested by him/them.
Rights of the Railway to deal with tender: The authority for the acceptance of the tender will rest with the Railway. It shall not be obligatory on the said authority to accept the lowest tender or any other tender and no tender(s) shall demand any explanation for the cause of rejection of his/their tender nor the Railway undertake to assign reasons for declining to consider or reject any particular tender or tenders.
If the tenderer(s) deliberately gives / give wrong information in his/their tender or creates/create circumstances for the acceptance of his/their tender, the Railway reserves the right to reject such tender at any stage.
If the tenderer(s) expires after the submission of his/their tender or after the acceptance of his/their tender, the Railway shall deem such tender cancelled. If a partner of a firm expires after the submission of their tender or after acceptance of their tender, the Railway shall deem such tender as cancelled, unless the firm retains its character.
Execution of contract documents:- The successful tenderer(s) shall be required to execute an agreement with the president of India acting through the South East Central Railway for carrying out the work according to Standard General condition of contract, Special conditions/specifications. annexed to the tender and specifications for work and materials of Railway as amended/corrected upto latest correction slips, mentioned in tender form (first sheet).
Price Variation Clause (PVC): 46A.1 Applicability: Price Variation Clause (PVC) shall be applicable only in tender having advertised value above Rs. 2 Crores. Provided further that, in a contract where PVC is applicable, following shall be outside the purview of price adjustments (i.e. shall be excluded from the gross value of the work for the purpose of price variation) : a) Materials supplied by Railway to the Contractors, either free or at fixed rate; b) Any extra item(s) included in subsequent variation falling outside the purview of the Bill(s) of Quantities of tender, under clause 39. (1)(b) of these Standard General Conditions, unless applicability of PVC and 'Base Month' has been specially agreed, while fixing the rates of such extra item(s).
46A.2 Base Month: The Base Month for 'Price Variation Clause' shall be taken as the one month prior to closing of tender, unless otherwise stated elsewhere. The quarter for applicability of PVC shall commence from the month following the Base month. The Price Variation shall be based on the average Price Index of the quarter under consideration. 46A.3 Validity: Rates accepted by Railway Administration shall hold good till completion of work and no additional individual claim shall be admissible except: (a) Payment/recovery for increase/decrease in GST on works contract or imposition/removal of any tax/cess on Works Contract as per Clause 37, (b) Payment/recovery for overall market situation as per Price Variation Clause given hereunder. 46A.4 Components of various items in a contract on which variation in prices be admissible, shall be steel, cement, ferrous material, non-ferrous material, insulators, zinc and other materials, labour, plant & machinery, fuel, explosives, detonators etc. Adjustment for variation in prices of these items shall be determined in the manner prescribed. 46A.5No price variation shall be admissible for fixed components. 46A.6 The percentages of various components in various type of works shall be as specified for all item (s)/ Bill(s) of Quantities in tender document and the same shall be fixed as per table & classifications given in GCC-2022.
Law Governing the Contract: The contract shall be governed by the law for the time being in force in the Republic of India.
Communications to be in writing: All notices, communications, reference and complaints made by the Railway or the Contractor inter-se concerning the works shall be in writing and no notice, communication, reference or complaint not in writing shall be recognized
Assignment Or Subletting of Contract: The contractor shall not assign or sublet the contract or any part thereof or allow any person to become interested therein any manner whatsoever without the special permission in writing of the Railway. Any breach of this condition shall entitle the Railway to rescind the contract under clause 62 of GCC and also render the contractor liable for payment to the Railway in respect of any loss or damage arising or ensuing form such cancellation.
Railway Passes: No free Railway passes shall be issued by the Railway to the Contractor or any of his employee/worker
Representation on Works: The contractor shall, when he is not personally present on the site of the works place, keep a responsible agent at the works during working hours who shall on receiving reasonable notice, present himself to the Sr.DEE(RS&G)/BSP and orders given by the officer or the nominated representative for said work to the agent shall be deemed to have the same force as if they had been given to the contractor. Before absenting himself, the contractor shall furnish the name and address of his representative for the purpose of this clause and failure on the part of the Contractor to comply with this provision at any time will entitle the Railway to rescind the contract under Clause 62 of GCC.
Security Deposit: The Security Deposit shall be 5% of the contract value. Security deposit shall be initially valid up to the stipulated date of Maintenance period plus 60 days and shall be extended from time to time, depending upon extension of contract granted in terms of Clause 17A and 17B of the Standard General Conditions of Contract. Note: Security Deposit deposited in cash by the Contractor or recovered from the running bills of a Contractor or submitted by contractor as Term Deposit Receipt(s) can be refunded/returned to the contractor, in lieu of irrevocable Bank Guarantee bond issued from scheduled commercial bank of India, to be submitted by him, for an amount equal to or more than the already available Security Deposit, provided however that, in a contract of value less than Rs. 50 Crore, such refund/ return of the already available Security Deposit is permitted up to two times and in a contract of value equal to or more than Rs. 50 Crore, such refund / return of the already available Security Deposit is permitted up to three times.
16.(2) (i) Refund of Security Deposit: Security Deposit mentioned in sub clause (1) above shall be returned to the Contractor along with or after, the following: (a) Final Payment of the Contract as per clause 51.(1) and (b) Execution of Final Supplementary Agreement or Certification by Engineer that Railway has No Claim on Contractor and (c) Maintenance Certificate issued, on expiry of the maintenance period as per clause 50.(1), in case applicable. 16. (2) (ii) Forfeiture of Security Deposit: Whenever the contract is rescinded as a whole under clause 62 (1) of these conditions, the Security Deposit already with railways under the contract shall be forfeited. However, in case the contract is rescinded in part or parts under clause 62 (1) of these conditions, the Security Deposit shall not be forfeited. 16.(3) No interest shall be payable upon the Bid Security and Security Deposit or amounts payable to the Contractor under the Contract, but Government Securities deposited in terms of Sub-Clause 16.(4)(b) of this clause will be payable with interest accrued thereon.
EXECUTION OF WORKS (9) Contractor's Understanding: It is understood and agreed that the Contractor has, by careful examination, satisfied himself as to the nature and location of work, the conformation of the ground, the character, quality of the materials to be encountered, the character of equipment and facilities needed preliminary to and during the progress of the works, the general and local conditions, the labour conditions prevailing therein and all other matters which can in any way affect the works under the contract, clarified all the points and doubts and interpretations by the proper authorities of the Railway.
Powers of Modification to Contract: The competent authority on behalf of the Railway shall be entitled by order in writing to enlarge or extend, diminish or reduce the works or make any alterations in their design, character, position, site, quantities, dimensions or in the method of their execution or in the combination and use of materials for the execution thereof or to order any additional work to be done and the contractor will not be entitled to any compensation for any increase /reduction in the quantities of work but will be paid only for the actual amount or work done and for approved materials supplied a specific order.
On Account Payments: Payment to the contractor will be done on submission of CC on A/c Bills verification of records, preferably on monthly basis by Electronic Fund Transfer (EFT) at the sole discretion of the Railway Administration in current account of contractor through any of the nationalized /schedule bank. For this proforma collect from this office before made first bill and is to be essentially filled up by the tenderer and submit the same to accounts department for releasing the payment.
It shall be understood that every endeavor has been made to avoid any error which can Materially affect the basis of the tender and the successful tender shall take open himself and provide for the risk of any error which may subsequently may be discovered and shall not make subsequently claim on account thereof.
GENERAL INSTRUCTIONS TO TENDERERS For e-Tenders
E-tender have been invited for and on behalf of the President of India through website www.ireps.gov.in for the work mentioned against the tender notice number available in the website. Tenderers are to bid online only in the above mentioned website. All Mandatory fields marked with (*) have to be filled in by the tenderer. No Manual offer is acceptable against this tender. No Tender document in hard copy will be sold against this tender Please read the Instructions to Tenderers for e- tendering, General Conditions of Contract, Special Condition of Contract before filling the e-tender through online.
E-Tender forms are not transferable and the same is to be submitted with digital signature by the Tenderer already registered with the site.
The submitted e-tender forms will be considered as digitally signed by the tenderer as a confirmation from the tenderer that the tenderer has read, agreed and accepted all the conditions and laid down documents referred in para 2 above as well as Schedule of Tender, General and Special Conditions.
The tender offer complete in all respect and with all documents is to be submitted online by e-tendering process through the website www.ireps.gov.in before the closing time/date of this tender as mentioned in the NIT (Notice Inviting Tender). Tenderer can revise the bids any number of times till the closing time/date of the tender. No manual offers shall be accepted.
The administration will not own any responsibility, if website is 54.4.1 not opened for downloading / uploading the tender documents due to any technical snag or glitch.
The Railway may, of its own or in response to any clarification requested/suggested by any person including that from the tenderer, may modify this tender document at its sole discretion at least 10 days before the due date of closing of the tender as corrigendum.
Corrigendum as required may be issued atleast 15 days prior to the closing of the tender. These corrigenda of this tender, if any, as issued time to time will be available on website at least 15 days in advance of closing of tender. The tenderers are requested to check the website before submitting their offer whether any such corrigendum to the tender has been issued or not and revise the offer if required accordingly. Failure on the part of tenderer on this aspect will be solely tenderers responsibility.
This document is the Standard Tender Document which consists of the Instruction to the Tenderers, NIT (Notice Inviting Tender), General Conditions of the Tender, Special conditions of the tender, Tender schedules, Specifications of the works & various Annexures etc. All the above mentioned documents taken together if not scored off, shall constitute the complete tender document hereafter referred to as Tender Document & have to be read together & acted upon accordingly. No part of the tender document can be relied upon or acted upon in isolation.
The Railway and the website will have no responsibility for incorrect evaluation of cost and thereby incorrect cost of work and ranking of tenderers, if the schedule is not filled in correctly and unambiguously for each item. No claim or clarification of a tenderer regarding applicability, inclusion or exclusion of any element of tax or duty or any other change in the offer subsequently (after opening of the tender) will be entertained. For this the tenderers are advised to read the Instructions, General Conditions, Special Conditions and other Instructions carefully before submission of tender.
In case of any problem with the portal is faced while filling the e-tender, Tenderers are advised to contact with the Helpdesk of IREPS portal who will render all help and assistance related with the website and portal except that related with the details of the tender. Railway will not take any responsibility for non- participation in the e-tender online for the reasons related to the website and portal or server etc beyond the control of railways.
Railway and the IREPS website will not take the responsibility for any online payment made by the tenderer and debited from his/their account towards the tender cost or Earnest Money due 54.10 to wrong or mismanipulation or any reasons related with the IT or found unsuitable for the tender etc. In this regard Railway and IREPS website will not entertain any claim or refund the paid amount.
All documents uploaded or information furnished in the website are digitally signed by the competent authority.
If any certificates or details enclosed by tenderer are found to be fake / bogus / tampered, such of those agencies shall not be awarded any work in South East Central Railway for a period of 54.12 five years from the date of opening of the tender. Joint ventures or partnership firms or any other nature of firm in which such agencies are a party shall also not be awarded any work for this period of five years.
If the tenderer(s) deliberately gives / give wrong information in his/their tender or creates/create circumstances for the 54.13 acceptance of his/their tender, the Railway reserves the right to reject such tender at any stage.
NIT PERIOD IS SPLITTED AS UNDER- Advertisement period- Time during which all information pertaining to tender shall be available BUT OFFERS CAN NOT BE SUBMITTED . Offer Submission Period - 15 (Fifteen) days prior to opening of tender during which TENDERERS CAN SUBMIT THEIR OFFER.
INCONSISTENCY BETWEEN THE DOCUMENTS The Indian railway standard General Condition of Contract shall be read with all correction slips and amendments issued thereto from time to time upto the date of tender notice and shall form integral part of this tender document. However, in case of any inconsistency and contradictions between the same and the special conditions & specifications laid in this tender document, the later shall prevail.
TENDERER'S POSTAL ADDRESS 3 . 1 Address of tenderer: The address, email - Id and Mobile phone, other phone nos. and other details given in the portal while registering will be considered as official address and all correspondences to the tenderer will be made in these registered modes. All communication sent in time to the tenderer by post at the said address shall be deemed to have reached the tenderer duly and in time. Important documents shall be sent by Registered Post. However, an undertaking has to be given in the enclosed annexure by uploading a scanned copy of duly filled in form in the portal.
THE SCHEDULE OF WORKS The Schedules of Works is also available separately in the website online and Rates are to be quoted online and submitted online duly signed digitally.
INSPECTION OF DATA Drawings for the work can be seen in the office inviting this tender on any working day during working hours. The drawings are only for the guidance of tenderers. Detailed working drawings, if required based on the drawings mentioned above, will be given by the Engineer or his representative from time to time.
Purchase voucher/ test certificate / guarantee certificate etc., from the manufacturer or their authorized dealer shall be produced in original on demand to the Sr.DEE/RS&G/BSP for all or part of the supplied materials.
For all the tenders having advertised cost of Rs 10 lakh or above, the contractor shall have the option to take payment from Railways through a letter of credit (LC) arrangement.
This option of taking payment through LC arrangement has to be exercised in IREPS (Indian Railway Electronic Procurement System - the e-application o n which tenders ar e called b y Railways) b y the tenderer a t the t ime of bidding itself, and the tenderer shall affirm having read over and agreed to the terms and conditions of the LC option.
The option so exercised, shall be an integral part of the bidder's offer T h e above option o f taking payment through L C arrangement, once exercised by tenderer at the time of bidding, shall be final and no change shall be permitted, thereafter, during execution of contract.
In case tenderer opts for payment through LC, following shall be the procedure to deal release of payment through LC: The LC shall be a sight LC The contractor shall select his Advising/Negotiating bank for LC . The incidental cost towards issue of LC and its operation thereof shall be borne by the contractor.
SBI, New Delhi, Main Branch will be the nodal branch for issue of LCs based on online requests received from Railway Accounts Units for tenders opened in current financial year. SBI branches where the respective Railway Accounts Office has its Account (local SBI branch)will be the issuance/reimbursing branch for LC issued under this arrangement. The Bank shall remain same for this tender till completion of contract. The incidental cost @ 0.15% per annum of LC value, towards issue of LC and operation thereof shall be borne by the contractor and shall be recovered from his bills.
SUBMISSION OF EARNEST MONEY: Tender must be accompanied with Earnest Money of requisite amount as mentioned in NIT in A/c of F.A.& C.A.O., S.E.C.Railway, Bilaspur deposited through Internet Banking, or payment gateway only before the closing date .
If a tender is accepted on the quoted rates of bidder which is below the advertised tender value, an additional performance security shall be submitted by the bidder as below: Bid quoted in % of advertised cost: 1)Below 0-5%(inclusive)- additional performance guarantee is NIL 2)Below 5%-Additional performance guarantee is 5%
For tender having advertised value more than Rs 10 crore wherein eligibility criteria include Bid capacity also, the tenderer will be qualified only if its available bid capacity is equal to or more than the total bid value of the present tender.
Repairing of damaged wiring of Officer's quarters, staff quarters, service buildings and repairing of Sub-stations, panel & overhead power line over BSP settlement.
OTP-26-27-12~SECR
OTP-26-27-12
Open
Works - General
12 Months
Bilaspur, Chhattisgarh
₹0
₹88,500
5 Aug 2026
5 Aug 2026
20 Aug 2026
137 items across 1 schedule
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 44,26,560 | ||
| — | 500.00 | — | — | ||
| Electrical point wiring for the 6 Amps light, fan & 5 Amps socket by 1.5 sq mm copper wire and with modular board and casing capping with supply of all materials. | — | — | — | 2,00,000 | |
| — | 200.00 | — | — | ||
| Casing-caping Wiring for 6-16 Amps plug points with PVC casing caping and PVC insulated copper conductor 2.5 sq. mm. size with with modular board and casing capping with supply of all materials. | — | — | — | 1,00,000 | |
| — | 300.00 | — | — | ||
| Re-dressing of surface wiring where ever in opened condition. | — | — | — | 3,600 | |
| — | 500.00 | — | — | ||
| Concealed wiring for light fan & 6 Amps plug points with PVC Pipe and PVC insulated copper conductor 1.5 sq. mm. size with modula rboard with supply of all materials. | — | — | — | 2,48,000 | |
| — | 200.00 | — | — | ||
| Concealed Wiring for 6/16 Amps plug points with PVC Pipe and PVC insulated copper conductor 2.5 sq.mm. size with modular board supply of all materials. | — | — | — | 1,18,000 | |
| — | 3400.00 | — | — | ||
| Concealed/casing caping Wiring for Sub-circuits. | — | — | — | 5,57,600 | |
| — | 50.00 | — | — | ||
| Supply of SPN Distribution board conforms to IS-13032. DBs are phosphatised and painted with epoxy polyster based powder paint, sheet steel enclosure for flush/surface mounting withneutral link,earth terminal & bus-bar single door 6 way. | — | — | — | 38,650 | |
| — | 300.00 | — | — | ||
| Supply of MCB SP 6-32 A capacity. | — | — | — | 48,300 | |
| — | 50.00 | — | — | ||
| Fixing , connection & commissioning of DB supplied above. | — | — | — | 1,650 | |
| — | 4.00 | — | — | ||
| Erection, painting & commissioning of Two pole structure complete for 11 KV including AB switch, LA, dropout fuse of 2 set each with allied accessories including supply of all material. | — | — | — | 3,44,884 | |
| — | 1.50 | — | — | ||
| Supply & Fabrication of steel structure for different work with painting and welding works. | — | — | — | 86,997 | |
| — | 3.00 | — | — | ||
| Supply of Aluminium Conductor Galvanized Steel Wire reinforced size 80 SQ.MM (6/4.09 MMALUM + 1/4.09 MM STEEL)" | — | — | — | 1,12,389 | |
| — | 1.00 | — | — | ||
| Drawl of conductor on rail poles with 3 wire 6/1/4.09 size ACSR conductor after releasing existing conductor. | — | — | — | 2,470 | |
| — | 5.00 | — | — | ||
| Supply of Aluminium conductor galvanized steel wire 50 sqmm reinforced size 6/3.35 MM ALUMN +1/3.35 MM STEEL. | — | — | — | 1,69,420 | |
| — | 1000.00 | — | — | ||
| Drawl of 5 conductor LT line | — | — | — | 6,000 | |
| — | 20.00 | — | — | ||
| "Erection & painting of departmentally supplied rail poles (13-8 Mtrs long)." | — | — | — | 55,220 | |
| — | 40.00 | — | — | ||
| Construction of Cement Concrete foundation containing cement concrete on the proportion 1:3:6 of cement, sand & ballast size of 40mm. | — | — | — | 1,84,520 | |
| — | 50.00 | — | — | ||
| Erection of Stays & Guys. | — | — | — | 10,850 | |
| — | 100.00 | — | — | ||
| Cutting of Rail poles | — | — | — | 55,200 | |
| — | 50.00 | — | — | ||
| Hiring of crane for transportation of Rail pole ot other heavy material from one location to other location/site. | — | — | — | 59,800 | |
| — | 500.00 | — | — | ||
| Supply of guarding for conductor made of GI 8 SWG wire with all accessories as details. | — | — | — | 68,500 | |
| — | 200.00 | — | — | ||
| fixing of guarding for conductor made of GI 8 SWG wire with all accessories as details. | — | — | — | 3,200 | |
| — | 20.00 | — | — | ||
| Supply of 11 KV- V cross arm including back clamp, nut -bolt and washers. | — | — | — | 28,140 | |
| — | 20.00 | — | — | ||
| Supply of 11 KV top clamp. | — | — | — | 5,960 | |
| — | 20.00 | — | — | ||
| Fixing of 11 KV- V cross arm including back clamp, nut - bolt and washers. | — | — | — | 2,540 | |
| — | 20.00 | — | — | ||
| Fixing of 11 KV top clamp | — | — | — | 1,040 | |
| — | 50.00 | — | — | ||
| Supply of 11 KV disc insulator with supply of requirednut & bolts. | — | — | — | 45,750 | |
| — | 50.00 | — | — | ||
| Fixing of HT disc insulator with hardware. | — | — | — | 10,450 | |
| — | 40.00 | — | — | ||
| Supply of 11/33 KV pin insulator with supply of required nut & bolts. | — | — | — | 5,040 | |
| — | 40.00 | — | — | ||
| Fixing of HT pin insulator suitable for 11/33 kv. | — | — | — | 1,080 | |
| — | 20.00 | — | — | ||
| Supply of Anti climbing Device | — | — | — | 3,980 | |
| — | 20.00 | — | — | ||
| Fixing of Anti climbing Device | — | — | — | 740 | |
| — | 100.00 | — | — | ||
| Laying of earth cone | — | — | — | 32,300 | |
| — | 200.00 | — | — | ||
| Supply and fixing of vertical guarding with reel insulator | — | — | — | 33,000 | |
| — | 200.00 | — | — | ||
| Supply of G.I . wire 8 SWG size. | — | — | — | 13,600 | |
| — | 200.00 | — | — | ||
| Drawing of guard wire after fabrication using GI wire & after release of existing guard wire | — | — | — | 1,800 | |
| — | 1000.00 | — | — | ||
| Laying of cable in open air/fixed in wall with supply of all material (Except cable & GI Pipe). | — | — | — | 35,000 | |
| — | 400.00 | — | — | ||
| Laying of cable of in GI pipe including supply of all materials (Except G.I. Pipe & Cable) | — | — | — | 42,000 | |
| — | 40.00 | — | — | ||
| Supply of DP MCB 32 A flush mounting MCB complete with sheet steel enclosure powder painted. | — | — | — | 25,920 | |
| — | 40.00 | — | — | ||
| Fixing of DP supplied above | — | — | — | 1,240 | |
| — | 20.00 | — | — | ||
| Supply of Digital Timer | — | — | — | 49,380 | |
| — | 20.00 | — | — | ||
| Supply of Contactor Block 40 Amps. Capacity with Auxiliary contact. | — | — | — | 38,500 | |
| — | 300.00 | — | — | ||
| Painting of rail pole with supply of aluminum paint. | — | — | — | 55,200 | |
| — | 300.00 | — | — | ||
| Painting of rail pole with supply of Red oxide (primer). | — | — | — | 60,600 | |
| — | 50.00 | — | — | ||
| Supply & fixing of C.I. clamp for top earth wire with all accessories like MS flat iron 50X8" size, nut - bolt, washer, reel insulator etc. | — | — | — | 15,200 | |
| — | 50.00 | — | — | ||
| Drawing of earth wire. | — | — | — | 450 | |
| — | 80.00 | — | — | ||
| Supply of LT 5 pin vertical bracket for single circuit including back clamp, nut-bolt and washer. | — | — | — | 1,74,880 | |
| — | 80.00 | — | — | ||
| Fixing of LT 5 pin vertical bracket including back clamp, nut-bolt and washers. | — | — | — | 3,840 | |
| — | 200.00 | — | — | ||
| Supply of LT insulators SHACKLE type 90 x 75 mm. | — | — | — | 30,400 | |
| — | 200.00 | — | — | ||
| Fixing of SHACKLE type insulator after release of old insulator. | — | — | — | 23,800 | |
| — | 100.00 | — | — | ||
| Supply of class A MS pipe clamp for clamping the street light fitting complete. | — | — | — | 4,100 | |
| — | 20.00 | — | — | ||
| Supply of Danger Boards HT/LT. | — | — | — | 2,080 | |
| — | 150.00 | — | — | ||
| Laying of Cable Specially Across the road/track by using trench-less construction method (through HDPE Pipe casing of PE 80 grade, 160 mm OD,0.6 MPa working pressure, 9 mm thick or as per site requirement). | — | — | — | 6,93,900 | |
| — | 1500.00 | — | — | ||
| Laying of cable of above 4x35 sq.mm in PVC/Polythene pipe without digging of earth, dressing of land including all materials. | — | — | — | 78,000 | |
| — | 1500.00 | — | — | ||
| Trenching/Digging of earth 1 mtr deep for cable laying | — | — | — | 1,45,500 | |
| — | 100.00 | — | — | ||
| Trimming of big branches above15 cm with disposal. | — | — | — | 34,300 | |
| — | 100.00 | — | — | ||
| Trimming of small branches dia.Above 5 CM &less than 15 cm with disposal. | — | — | — | 17,100 | |
| — | 50.00 | — | — | ||
| Supply of ballast 40 mm size. | — | — | — | 46,500 | |
| — | 20.00 | — | — | ||
| Supply of murrum. | — | — | — | 560 | |
| — | 50.00 | — | — | ||
| Proper leveling & Dressing of land and there after spreading of ballast in the Sub- station yard. | — | — | — | 850 | |
| — | 20.00 | — | — | ||
| Laying & spreading of Mooram including ramming rolling, water & consolidation with all contractor'slabour, tools & plants complete. | — | — | — | 1,400 | |
| — | 4.00 | — | — | ||
| Supply of Hand gloves suitable for operating voltage 11 KV. | — | — | — | 24,000 | |
| — | 2.00 | — | — | ||
| Supply of Hand gloves suitable for operating voltage 33 KV. | — | — | — | 16,000 | |
| — | 2000.00 | — | — | ||
| Straightining of loose LT/HT overhead Aluminium conductor wire. | — | — | — | 10,000 | |
| — | 50.00 | — | — | ||
| Straightining of inclined/bend pole with the help of turpher. | — | — | — | 25,000 | |
| — | 30.00 | — | — | ||
| Supply & fixing of 18W LED down light with surface mounted (RecessType) size: 1x1, diffuser material:polycarbonate, IP20 temp.:6000K, rated voltage: 230 V AC50 Hz confirming with relevant IS specifications. | — | — | — | 35,400 | |
| — | 30.00 | — | — | ||
| Supply & fixing of LED Recessed Luminaire Round shaped (downlight) wattage: 18W to 24W, colour:6000K/6500K | — | — | — | 31,980 | |
| — | 30.00 | — | — | ||
| Supply & fixing of LED Recessed Luminaire (Panel Light) wattage: 30W to 48W, size:2ftx2ft (approx), colour:6000K/6500K | — | — | — | 42,810 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GCC_April-2022.pdf
ATTACHMENT
LC.pdf
ATTACHMENT
GCC2022correctionslipupto11.pdf
ATTACHMENT
ANNEXUREABCD.pdf
ATTACHMENT
ANNEXUREE.pdf
ATTACHMENT
NewVA.pdf
ATTACHMENT
V.pdf
ATTACHMENT
CONSERVANCYCess_Charges7.9.21.pdf CONSERVENCY CESS CHARGE
ATTACHMENT
AnnexureVIABSbankform.pdf
ATTACHMENT
specialcondition.pdf
ATTACHMENT
Scopeofwork_1.pdf
ATTACHMENT
CONSERVANCYCess_Charges7.9.21.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].