GTL Div: OHE modifications for additional loop line with common loop facility at Kosigi (KO) Station in Guntakal (GTL) - Wadi (WADI) Section
GTL-TRD-29-eTN-36-2026-27
GTL-TRD-29-eTN-36-2026-27
Open
Works - General
12 Months
Anantapur, Andhra Pradesh
₹0
₹3.3 L
24 Jul 2026
24 Jul 2026
3 Aug 2026
A2-FOUNDATION ITEMS (incl. Supply & Erection) 2875590.00 Below/P
Item Breakup - A1-OHE & PSI Items
Per Track Supply & Erection KM 1(c)-Preparation of Traction Working Rule Diagram along with Working Instructions
Each 1(d)-Supply and Installation of Traction Working Rule Diagram Boards
Square Foot 1(f)-Preparation and Designing of Sectioning Diagram.
Each Supply & Erection station/Gate 3(a)-Erection of Traction Masts, Feeder Masts, AT Mast and Main Masts of Switching Stations.
7.00 Block 3(b)-Erection of TTCs, Portals and Small Parts Steel (SPS)
28.00 Block 3(e) -Supply and Erection of Guy Rod Assembly
14.00 Block 4(a)(i)-Supply (without Insulators) and Erection of Single Cantilever Assembly for Conventional OHE
Each GUNTAKAL-SCOR-DIVISION-ELECTRICAL/SOUTH COAST RAILWAY
Rate Power Block 4(a)(ii)-Erection of Two Cantilever Assemblies on same structure or support for Conventional OHE
Rate Power Block 4(a)(iii)-Erection of Three Cantilever Assemblies on same structure or support for Conventional OHE
10.00 Power Block 6(a)-Supply and Erection of Regulated Conventional OHE
Per Track Supply/Material KM
Per Track Erection/ Labour KM
1.75 48362.00 Block KM 7(c)-Erection of Large Span Wire (130 Sq. mm)
200.00 Block 8(a)(iv)-Supply of Regulating Equipment Without Counter-Weight Assembly
Each 8(a)(v)-Supply and Erection of Regulating Equipment With Counter-Weight assembly for Conventional OHE
Rate Power Block 8(a)(xii)-Marking/Painting of temperature and 'Y' - Measurement on OHE Structures at BWA locations.
Each 8(b)(i)-Supply (without Insulator) and Erection of materials for Termination single conductor of OHE or terminating wire
Rate Power Block 8(b)(ii)-Supply (without Insulator) and Erection of Materials for Termination of Conventional OHE
Rate Power Block 8(b)(iii)-Supply (without Insulator) and Erection of Materials for Termination of Along Feeder (Aluminium/Copper)
2.00 Power Block GUNTAKAL-SCOR-DIVISION-ELECTRICAL/SOUTH COAST RAILWAY 9(a)-Supply (without Insulators) and Erection of Anti-creep with galvanized steel wire for Conventional OHE
2.00 Block 11(a)(i)-Supply (without Insulator) and Erection of 25 kV Solid Core Cut-in Insulator.
4.00 Power Block 11(a)(ii)-Supply (without Insulator) and Erection of 25 kV Solid Core Suspension Insulator.
6.00 Power Block 11(b)-Supply (without Insulator) and Erection of 25 kV Post Insulator
12.00 Block 12(a)-Supply (without Insulators) and Erection of 25 kV Section Insulator Assembly for Conventional OHE
8.00 Block 13(a)-Supply (without Insulators) and Erection of 25 kV Single Pole Isolator without earth contact assembly
6.00 Block 15(a)-Supply and Erection of 50 sq.mm Copper Jumper (C-Jumper, F-Jumper, Anti- Theft Jumper) (excluding copper jumper supply)
20.00 Block 15(b)-Supply and Erection of 160 or 105 sq.mm Copper Jumper (Isolator Jumper, G- Jumper) (excluding copper jumper supply)
12.00 Block 15(e)-Supply and Erection of Aluminium Jumper
Each 16(a)-Supply and Erection of Structure Bond
Each GUNTAKAL-SCOR-DIVISION-ELECTRICAL/SOUTH COAST RAILWAY
Each 16(b)-Supply and Erection of Longitudinal Bond
Each 16(c)-Supply and Erection of Transverse & Special Bond
Each 16(aa)-Drilling of Holes on Rails
Each 26(a)(ii)-Supply and Erection of 18 mm Copper Bus Bar
120.00 Power Block 26(c)(i)-Supply and Erection of Solid Copper Busbar Connector - 18 mm Bus Terminal (6310-1)
10.00 Power Block 26(c)(ii)-Supply and Erection of Solid Copper Busbar Connector - 18 mm Bus Splice (6320)
8.00 Power Block 31(a) -Transfer of Overhead Equipment from one Mast or Support to another, including removal of Cantilever Assembly from old Mast or Support
40.00 Block 31(b) -Provision of additional bracket assembly/assemblies on a mast or support
2.00 Block 31(e) -Splicing and Extension of Anchored OHE
4.00 Block 31(f) -Dismantling of Section Insulator
3.00 Block 31(h) -Dismantling of an Isolator
2.00 Block 31(k)(i) -Dismantlement of OHE Mast or structure by cutting
20.00 Power Block GUNTAKAL-SCOR-DIVISION-ELECTRICAL/SOUTH COAST RAILWAY 31(k)(ii) -Dismantlement of Upright of TTC/Portal by cutting
14.00 Power Block 31(l)(i) -Retrieval of Traction Masts, Main Masts of Switching Station, TTC Uprights etc
Rate Power Block 31(n) -Dismantling of Guy Rod
10.00 Block 31(p)-Dismantling of Drop Arms/Booms/ Temporary Masts
2.00 Block 31(s) -Dismantling of Fabricated Steel or Small Parts Steel (SPS)
3.00 Block 31(t)(i) -Dismantling of a Regulating Equipment (Three-pulley type) with counter weight assembly for Conventional OHE
Rate Power Block 31(t)(iv) -Dismantling of all types of Copper Jumpers
30.00 Power Block 31(t)(v) -Dismantling of Termination for Conventional type Overhead Equipment
10.00 Power Block 31(t)(viii) -Transfer of Feeder Wire from one Mast or Support to another Mast or Support
10.00 Power Block 31(t)(ix) -Re-adjustment of OHE Spans, including droppers
40.00 Power Block 31(t)(x) -Dismantling of Structure Bond / Longitudinal Bond / Transverse and Special Bond
Each 36(a)-Unloading of all types of Steel Structures
MT 36(b)-Loading of all types of Steel Structures
MT 37(a)-Unloading of all types of Copper & Aluminium conductors GUNTAKAL-SCOR-DIVISION-ELECTRICAL/SOUTH COAST RAILWAY
MT 37(b)-Loading of all types of Copper & Aluminium conductors
MT 38-Transportation of OHE structures / Materials / Equipments
MT-Km 40(a)-Supply and Erection of Number Plate (Enamel Type)
Each Total 6330727.50
Item Breakup - A2-FOUNDATION ITEMS (incl. Supply & Erection)
cum 2(a)(ii)-Concrete for foundations and plinth in Rocky Soil
cum 2(b)-Concrete for foundations and plinth in other than Hard and Rock Soil
cum 2(i)-Breaking of foundation up to 200 mm below track formation and drain / PF surface etc
cum Total 2875590.00
Item Breakup - B1-STEEL SUPPLY
MT 3(bs)-Supply of Fabricated and Galvanized structures such as TTCs, Portals, other than masts
MT 3(cs)-Supply of Fabricated and Galvanized Small Parts Steel (SPS) other than Masts, TTCs and Portals.
Item Breakup - B2-COPPER SUPPLY
Kg 7(cs)Supply of 130 sq.mm Cadmium Copper Large Span Wire
Kg 15(as)Supply of 50 sq.mm Annealed Stranded Copper Jumper Wire
Kg GUNTAKAL-SCOR-DIVISION-ELECTRICAL/SOUTH COAST RAILWAY 15(bs)Supply of 160 sq.mm Annealed Stranded Copper Jumper Wire
Item Breakup - B3-INSULATOR SUPPLY
Set 8(bx)-Supply of Porcelain 9-ton Insulator for item no. 8(b)(ii)/8(b)(iii)/8(b)(vi)/8(b) (ix)/9(a)/9(b)/9(c)/9(d)/11(a)(i)/11(a)(ii)
Each 11(bx)-Supply of Post Insulator for Item no. 11(b)
Each 12(ax)-Supply of Sectioning and 9-ton Insulators for Item no. 12(a)
Set 13(ax)-Supply of Post and Operating Rod Insulators for Item no. 13(a)
Set Total 950026.00
Item Breakup - C -GENERAL ITEMS
Each Total 28400.00
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
36-2026-27TenderMasterdocument_2.pdf
ATTACHMENT
Standard General Conditions of cont
ATTACHMENT
36-2026-27ExplanatoryNotes_2.pdf
ATTACHMENT
GCCCorrectionSlips__compressed_1.pdf
ATTACHMENT
36-2026-27StandardGeneralConditionsofcontract_2.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].