Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.3 LAccepted-AOC ADUKKATTU HOUSE THIMIRI PO | KERALA | L1 | Accepted-AOC 1ST LOWEST | |
| 2 | Rejected-Technical | - | Rejected-Technical 2ND LOWEST |
Tender Value
₹7.9 L
EMD Value
₹19,665
Closing Date
25 Mar 2025, 5:00 pmClosed
Assistant Engineer
Eramam KUttoor Grama Panchayath
Consctruction of check dam
2025_LSGD_743550_20
255/24-25
Open Tender
Civil Works - Water Works
Item Rate
180 days
Eramam north
Please refer Tender documents.
8 documents required · 8 mandatory
₹1,735
Yes
₹19,665
Yes
2 Jun 2025
18 Mar 2025
27 Mar 2025
18 Mar 2025
25 Mar 2025
18 Mar 2025
Amount
Construction Of Check Dam
OD485666/2024-2025:RING BUND Type II Putting up ring bund with earth fill in gunny bags of top width 1.0m bottom width 2.0m height 2.0 m side and filling in between with earth to form ring bund and maintaining the same leak proof till the completion of the work and clearing the site by dismantling the bund after completion of the work.etc.complete.(Data for 10m) (Same as Item No.60.1.2)
OD485665/2024-2025:Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete Same as item No.60.2.2
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.3.3:Centering and shuttering including strutting, propping etc. and removal of form work for:Columns, piers, abutments, pillars, posts and struts
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
4.1.4:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 )1 cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size)
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
OD485668/2024-2025:Shutter for check dams- Supplying and providing Thambagam wood shutter planks 5cm thick including cost of materials and labour charges etc complete(Same as item no.60.8)
Riju M T (BID ID -2175245)
Bidder Name
Riju M T
A K REJEESH
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .