| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹1.5 CrAccepted-Finance | ₹1.5 Cr | L-1 | Accepted-Finance L-1 |
| 2 | L-2₹1.5 CrRejected-Finance | ₹1.5 Cr | L-2 | Rejected-Finance L-2 |
| 3 | L-3₹1.6 CrRejected-Finance | ₹1.6 Cr | L-3 | Rejected-Finance L-3 |
Tender Value
₹1.6 Cr
EMD Value
₹3.7 L
Closing Date
11 May 2026, 5:00 pmClosed
GM-CIVIL
Main Administrative Building Sector-6 Noida
M/o Park and Green Belt (C/o R.C.C Boundary Wall in Sector-60 of Green Belt parallel to Kondali Road and Damaged Boundary Wall between Plot No. B-96C and Bijli Ghar in Sector-60) Noida
2026_NOIDA_1144964_1
38/DGM/SM(WC-05)/2025-26
Open Tender
Civil Works
180 days
NOIDA
Please refer Tender documents.
3 documents required · 3 mandatory
₹5,310
NOIDA
₹3.7 L
22 May 2026
4 May 2026
12 May 2026
4 May 2026
11 May 2026
4 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed,within a lead of 50 m.The Contractor has to dectect different utilities like sewer line, water supply line, electric cable, telephone cable , gas pipe line etc, using utility decteting machine before start of excavation and shall start excavation only after getting permission of E/I. All kind of soil (Letter No. Noida/CPE/2015/464, Dt. 20.07.2015) | 749 | Cum | 144.95 | ₹1,08,567.55 |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth, 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth, lead up to 50m and lift up to 1.5m,as directed by Engineer-in-Charge. All kinds of soil | 626.5 | Cum | 136 | ₹85,204 |
| 3 | Cleaning jungle including up rooting of rank,vegetations grass,push,wood trees and sampling of grith upto 30cms measured at a height of 1m above ground level and removal of rubbish up to a distance of 50m outside the periphery of area cleared. | 2,175 | Sqm | 3.1 | ₹6,742.5 |
| 4 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. | 2,463 | Cum | 120.55 | ₹2,96,914.65 |
| 5 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. | 374.5 | Cum | 93 | ₹34,828.5 |
| 6 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 cement : 4 coarse sand(zone-III) : 8 graded stone aggregate 40 mm nominal size) | 343 | Cum | 5,746.88 | ₹19,71,179.84 |
| 7 | Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in charge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately). | 228.2 | Cum | 8,141.85 | ₹18,57,970.17 |
| 8 | Providing and laying in position ready mixed M-25 grade concrete for reinforced concrete work , using cement content as per approved design mix , manufactured in fully automatic batching plant and transported to site of work in transit mixer for a leads having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying , excluding the cost of centering, shuttering finishing and reinforcement including cost of admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in - charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/recoverable separately ),All works upto plinth level. | 386.5 | Cum | 7,912.3 | ₹30,58,103.95 |
| 9 | Providing and laying in position ready mixed M-25 grade concrete for reinforced concrete work , using cement content as per approved design mix , manufactured in fully automatic batching plant and transported to site of work in transit mixer for a leads having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying , excluding the cost of centering, shuttering finishing and reinforcement including cost of admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in - charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/recoverable separately ),All works above plinth level upto floor V level | 207 | Cum | 8,654.75 | ₹17,91,533.25 |
| 10 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size). | 10.5 | Cum | 8,441.41 | ₹88,634.81 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.08 MB
BOQ_2139806.xls
BOQ • 0.30 MB
Capability.xls
Additional Documents • 0.04 MB
TD.pdf
Tender Documents • 5.31 MB