| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.8 LAccepted-AOC | ₹5.8 L | L1 | Accepted-AOC L1 |
| 2 | L2₹6.1 LRejected-AOC | ₹6.1 L | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | PREM KUMAR A L2 | Sirajudeen K K L1 |
|---|---|---|---|---|---|
| 1.00Thanneermukkom Panchayath (including Nellathodu) | |||||
| 1.00 | OD18109/2025-2026:Forming bund to a top width 1.50m and 1.50m (avg)height and 1/4:1 slope and protecting the
side with 1/4 split well matured and sound coconut post 2.70m long driving down 1.20m below
ground level on both side at 60 cm c/c, fitting 1/4th split coconut wailing pies in two rows on
either sides and tying with 1/4th split coconut cross ties at 1.20m c/c connecting the alternate set
of post, providing areca nut reapers screen 16cm square mesh tied with coir yarn, filling inside
the formation and providing plastic shoot (medium quality) inside the screen and filled with
earth etc as per the instruction by the departmental officers at site and maintaining the bund
properly through out cultivation period including cutting and removing materials and clearing
area etc, complete as per the direction above.(Hire and labour charges only). | 329.63 | cum | 1,257.49 ₹4.1 L | 1,190.21 ₹3.9 L |
| 1.00 | OD18110/2025-2026:Putting up tidal bund on sluices available in good condition with mango wood planks and beams (H/C only) fitted in the grooves and filling the gaps between planks with earth all leads & lifts etc. complete (Hire & labour only if the planks are provided by dept. or other agencies the H/C of planks are to be deducted from the rate. | 16.8 | metre | 2,708.01 ₹45,494.57 | 2,563.13 ₹43,060.58 |
| 1.00 | OD18111/2025-2026:Maintaining the bund properly through out cultivation period including cutting and removing materials and clearing the area etc. complete as per the direction of the departmental officers at site.(1/8 th charge of putting up sluice) | 16.8 | metre | 334.89 ₹5,626.15 | 316.97 ₹5,325.10 |
| 1.00 | OD18108/2025-2026:Forming bund to a top width 4m and 2m (av)height and 1/4:1 slope and protecting the side
with1/4 split well matured and sound coconut post 3.2mlong driving down 1.2m below ground
level on both side at 60 cm c/c, fitting 1/4 split coconut wailing pieces in three rows on either sides and tying with 1/4 split coconut cross ties at 0.6m c/c connecting the alternate set of post,providing areca nut reapers screen 15cm square mesh tied with coir yarn, filling inside the formation and providing plastic sheet(medium quality) inside the screen and filled with earth etc.as per the instruction by the departmental officers at site and maintaining the bund properly through out cultivation period including cutting and removing materials and clearing area etc. complete as per the direction above.(Hire and labour charges only) | 45 | cum | 841.86 ₹37,883.70 | 841.86 ₹37,883.70 |
| 2.00Mannanchery Panchayath | |||||
| 2.00 | OD18115/2025-2026:Forming bund to a top width 1.50m and 1.50m (avg)height and 1/4:1 slope and protecting the
side with 1/4 split well matured and sound coconut post 2.70m long driving down 1.20m below
ground level on both side at 60 cm c/c, fitting 1/4th split coconut wailing pies in two rows on
either sides and tying with 1/4th split coconut cross ties at 1.20m c/c connecting the alternate set
of post, providing areca nut reapers screen 16cm square mesh tied with coir yarn, filling inside
the formation and providing plastic shoot (medium quality) inside the screen and filled with
earth etc as per the instruction by the departmental officers at site and maintaining the bund
properly through out cultivation period including cutting and removing materials and clearing
area etc, complete as per the direction above.(Hire and labour charges only). | 63.28 | cum | 1,257 ₹79,547.99 | 1,190.21 ₹75,321.25 |
| 3.00Muhamma Panchayath | |||||
| 3.00 | OD18112/2025-2026:Forming bund to a top width 1.50m and 1.50m (avg)height and 1/4:1 slope and protecting the
side with 1/4 split well matured and sound coconut post 2.70m long driving down 1.20m below
ground level on both side at 60 cm c/c, fitting 1/4th split coconut wailing pies in two rows on
either sides and tying with 1/4th split coconut cross ties at 1.20m c/c connecting the alternate set
of post, providing areca nut reapers screen 16cm square mesh tied with coir yarn, filling inside
the formation and providing plastic shoot (medium quality) inside the screen and filled with
earth etc as per the instruction by the departmental officers at site and maintaining the bund
properly through out cultivation period including cutting and removing materials and clearing
area etc, complete as per the direction above.(Hire and labour charges only). | 16.31 | cum | 1,257 ₹20,505.44 | 1,190.21 ₹19,415.90 |
| 3.00 | OD18113/2025-2026:Putting up tidal bund on sluices available in good condition with mango wood planks and beams (H/C only) fitted in the grooves and filling the gaps between planks with earth all leads & lifts etc. complete (Hire & labour only if the planks are provided by dept. or other agencies the H/C of planks are to be deducted from the rate. | 2.35 | metre | 2,708 ₹6,363.80 | 2,563.13 ₹6,023.36 |
Tender Value
₹6.1 L
EMD Value
₹15,322
Closing Date
22 Nov 2025, 6:00 pmClosed
Assistant Executive Engineer
Assistant Executive Engineer,KD SUB division,Thanneermukkom
GENERAL-Tidal Bund 2025-26-Putting up tidal bunds in various places of Thanneermukkom Panchayath (including Nellethodu),Muhamma panchayath,and Mannanchery Panchayath for 2025-26-General Civil Work
2025_Irrig_820926_1
03/AEE/KDSD/TKM/2025-26
Open Tender
Civil Works - Others
210 days
Thanneermukkom
Please refer Tender documents.
11 documents required · 11 mandatory
₹1,355
Yes
₹15,322
Yes
24 Dec 2025
18 Nov 2025
24 Nov 2025
18 Nov 2025
22 Nov 2025
18 Nov 2025
Amount
Thanneermukkom Panchayath (including Nellathodu)
OD18109/2025-2026:Forming bund to a top width 1.50m and 1.50m (avg)height and 1/4:1 slope and protecting the side with 1/4 split well matured and sound coconut post 2.70m long driving down 1.20m below ground level on both side at 60 cm c/c, fitting 1/4th split coconut wailing pies in two rows on either sides and tying with 1/4th split coconut cross ties at 1.20m c/c connecting the alternate set of post, providing areca nut reapers screen 16cm square mesh tied with coir yarn, filling inside the formation and providing plastic shoot (medium quality) inside the screen and filled with earth etc as per the instruction by the departmental officers at site and maintaining the bund properly through out cultivation period including cutting and removing materials and clearing area etc, complete as per the direction above.(Hire and labour charges only).
OD18110/2025-2026:Putting up tidal bund on sluices available in good condition with mango wood planks and beams (H/C only) fitted in the grooves and filling the gaps between planks with earth all leads & lifts etc. complete (Hire & labour only if the planks are provided by dept. or other agencies the H/C of planks are to be deducted from the rate.
OD18111/2025-2026:Maintaining the bund properly through out cultivation period including cutting and removing materials and clearing the area etc. complete as per the direction of the departmental officers at site.(1/8 th charge of putting up sluice)
OD18108/2025-2026:Forming bund to a top width 4m and 2m (av)height and 1/4:1 slope and protecting the side with1/4 split well matured and sound coconut post 3.2mlong driving down 1.2m below ground level on both side at 60 cm c/c, fitting 1/4 split coconut wailing pieces in three rows on either sides and tying with 1/4 split coconut cross ties at 0.6m c/c connecting the alternate set of post,providing areca nut reapers screen 15cm square mesh tied with coir yarn, filling inside the formation and providing plastic sheet(medium quality) inside the screen and filled with earth etc.as per the instruction by the departmental officers at site and maintaining the bund properly through out cultivation period including cutting and removing materials and clearing area etc. complete as per the direction above.(Hire and labour charges only)
Mannanchery Panchayath
OD18115/2025-2026:Forming bund to a top width 1.50m and 1.50m (avg)height and 1/4:1 slope and protecting the side with 1/4 split well matured and sound coconut post 2.70m long driving down 1.20m below ground level on both side at 60 cm c/c, fitting 1/4th split coconut wailing pies in two rows on either sides and tying with 1/4th split coconut cross ties at 1.20m c/c connecting the alternate set of post, providing areca nut reapers screen 16cm square mesh tied with coir yarn, filling inside the formation and providing plastic shoot (medium quality) inside the screen and filled with earth etc as per the instruction by the departmental officers at site and maintaining the bund properly through out cultivation period including cutting and removing materials and clearing area etc, complete as per the direction above.(Hire and labour charges only).
Muhamma Panchayath
OD18112/2025-2026:Forming bund to a top width 1.50m and 1.50m (avg)height and 1/4:1 slope and protecting the side with 1/4 split well matured and sound coconut post 2.70m long driving down 1.20m below ground level on both side at 60 cm c/c, fitting 1/4th split coconut wailing pies in two rows on either sides and tying with 1/4th split coconut cross ties at 1.20m c/c connecting the alternate set of post, providing areca nut reapers screen 16cm square mesh tied with coir yarn, filling inside the formation and providing plastic shoot (medium quality) inside the screen and filled with earth etc as per the instruction by the departmental officers at site and maintaining the bund properly through out cultivation period including cutting and removing materials and clearing area etc, complete as per the direction above.(Hire and labour charges only).
OD18113/2025-2026:Putting up tidal bund on sluices available in good condition with mango wood planks and beams (H/C only) fitted in the grooves and filling the gaps between planks with earth all leads & lifts etc. complete (Hire & labour only if the planks are provided by dept. or other agencies the H/C of planks are to be deducted from the rate.
OD18114/2025-2026:Maintaining the bund properly through out cultivation period including cutting and removing materials and clearing the area etc. complete as per the direction of the departmental officers at site.(1/8 th charge of putting up sluice)
PREM KUMAR A (BID ID -2442131)
Bidder Name
PREM KUMAR A
Sirajudeen K K
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1376370.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.04 MB
viewsbd.pdf
Tender Documents • 1.63 MB
BOQ_1376370.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid