Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹24.9 LAdmitted-Finance | ₹24.9 L | L1 | Admitted-Finance |
| 2 | L2₹25.2 LAdmitted-Finance BLDG NO 03 SF 3 SF 4 TECHNO CIDADE CHOGM ROAD ALTO PORVORIM BARDEZ GOA | NORTH GOA | GOA | 403524 | ₹25.2 L | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | BAGKIYA CONSTRUCTIONS PVT LTD L2 | katragunta srikanth L1 |
|---|---|---|---|---|---|
| 1.00 | Earthwork in excavation by mechanical / manual means in all type of strata comprising any of the materials such as soil, sand, silt, clay, gravel, moorum of all varieties shingles, pebbles, all type of conglomerates, laterite rock, soft rock, ordinary rock, disintegrated rock, or weathered rock fissured/shattered, decomposed rock and all such other materials, either in full or in parts as the case may be by adopting any approved method or methods as may be convenient or permitted inclusive of chiselling, wedging etc. but blasting prohibited in all condition such as dry moist, saturated submerged, foul conditions etc. including pumping or bailing out water / dewatering including setting out construction of shoring strutting and bracing removal of stumps and other deleterious matter, dressing of sides and bottom providing barricading, danger lighting, gaurding etc and back filling the excavated earth to the extent required and disposal of surplus excavated soil / rock at specified areas with all leads and all lifts etc complete as per specification and drawing and as directed by the engineer - in -charge etc complete. | 192.3 | Cu.M | 96,150 ₹1,13,457 | 63,037.86 ₹74,384.68 Lowest |
| 2.00 | Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete. | 4.2 | Cu.M | 10,500 ₹12,390 | 6,608.36 ₹7,797.87 Lowest |
| 3.00 | Centering & Shuttering including strutting, propping etc & removal of formwork for :
Foundations, Footings, bases for columns and mass concrete. | 156.1 | Sqm | 78,050 ₹92,099 Lowest | 81,874.45 ₹96,611.85 |
| 4.00 | Centering & Shuttering including strutting, propping etc & removal of formwork for :
vertical surfaces such as retaining walls, return walls, walls ( any thk) including attached pilasters, buttresses, plinth and string courses, fillets etc. | 60.4 | Sqm | 36,240 ₹42,763.2 | 31,679.8 ₹37,382.16 Lowest |
| 5.00 | Centering & Shuttering including strutting, propping & removal of forms for : Coulumns, piers, pillars, aburments, posts and struts (Square, rectangle polygon in plan) | 13.2 | Sqm | 9,900 ₹11,682 | 6,923.4 ₹8,169.61 Lowest |
| 6.00 | Centering & shuttering including Strutting, Propping & removal of forms for sloping or battering surface (slabs, beams, louvers, etc) including folded plates columns, pillars, posts and struts (circular or curved in plan) | 17 | Sqm | 13,600 ₹16,048 Lowest | 15,603.96 ₹18,412.67 |
| 7.00 | Providing & Laying cement concrete 1:2:4 (1 cement: 2 Coarse Sand: 4 graded granitic or basaltic stone aggrt. 20mm nominal size) excluding cost of centering, shuttering and finishing in:
All works upto plinth level | 107.8 | Cum | 8,62,400 ₹10,17,632 | 7,77,437.43 ₹9,17,376.17 Lowest |
| 8.00 | Providing & Laying cement concrete 1:2:4 (1 cement: 2 Coarse Sand: 4 graded granitic or basaltic stone aggrt. 20mm nominal size) excluding cost of centering, shuttering and finishing in:
in retaining walls, return walls (any thk) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets etc upto floor five level. | 18.7 | Cum | 1,49,600 ₹1,76,528 Lowest | 1,71,642.63 ₹2,02,538.3 |
| 9.00 | Providing and Laying in position (1:11/2:3) Reinforced Cement Concrete excluding the cost of centering, shuttering, finishing and reinforcement (1 cement : 1 1/2 Coarse Sand : 3 graded stone agg 20 mm nominal size)
All works upto plinth level | 28.8 | Cum | 2,59,200 ₹3,05,856 Lowest | 2,64,348 ₹3,11,930.64 |
| 10.00 | Providing and Laying in position (1:11/2:3) Reinforced Cement Concrete excluding the cost of centering, shuttering, finishing and reinforcement (1 cement : 1 1/2 Coarse Sand : 3 graded stone agg 20 mm nominal size)
In walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. upto floor five level. | 9.8 | Cum | 98,000 ₹1,15,640 Lowest | 1,03,239.08 ₹1,21,822.11 |
Tender Value
₹23.8 L
EMD Value
₹47,558
Closing Date
4 Aug 2026, 5:30 pmClosed
EEVI, WRD, Bicholim
EEVI, WRD, Bicholim
Construction of Open Type Bandhara for Harvalem nallah near Moksha Dham left side of Rudreshware Temple at Harvalem Sankhali in Bicholim Taluka of Sankhalim Constituency.
2026_WRD_30526_1
No.WRD/WDVI/PB/F.30/TN e 14/2026-27/347 line 3 Dated 21/07 /2026
Open Tender
Civil Works - Water Works
Item Rate
90 days
Bicholim
Please refer Tender documents.
3 documents required · 3 mandatory
₹3,000
₹47,558
24 Aug 2026
22 Jul 2026
5 Aug 2026
22 Jul 2026
4 Aug 2026
22 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | GST % |
|---|---|---|---|---|---|---|
| 1 | Earthwork in excavation by mechanical / manual means in all type of strata comprising any of the materials such as soil, sand, silt, clay, gravel, moorum of all varieties shingles, pebbles, all type of conglomerates, laterite rock, soft rock, ordinary rock, disintegrated rock, or weathered rock fissured/shattered, decomposed rock and all such other materials, either in full or in parts as the case may be by adopting any approved method or methods as may be convenient or permitted inclusive of chiselling, wedging etc. but blasting prohibited in all condition such as dry moist, saturated submerged, foul conditions etc. including pumping or bailing out water / dewatering including setting out construction of shoring strutting and bracing removal of stumps and other deleterious matter, dressing of sides and bottom providing barricading, danger lighting, gaurding etc and back filling the excavated earth to the extent required and disposal of surplus excavated soil / rock at specified areas with all leads and all lifts etc complete as per specification and drawing and as directed by the engineer - in -charge etc complete. | 192.3 | Cu.M | 291 | ₹55,959.3 | 18% |
| 2 | Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete. | 4.2 | Cu.M | 2,211 | ₹9,286.2 | 18% |
| 3 | Centering & Shuttering including strutting, propping etc & removal of formwork for :
Foundations, Footings, bases for columns and mass concrete. | 156.1 | Sqm | 6,810 | ₹10,63,041 | 18% |
| 4 | Centering & Shuttering including strutting, propping etc & removal of formwork for :
vertical surfaces such as retaining walls, return walls, walls ( any thk) including attached pilasters, buttresses, plinth and string courses, fillets etc. | 60.4 | Sqm | 407 | ₹24,582.8 | 18% |
| 5 | Centering & Shuttering including strutting, propping & removal of forms for : Coulumns, piers, pillars, aburments, posts and struts (Square, rectangle polygon in plan) | 13.2 | Sqm | - | - | 18% |
| 6 | Centering & shuttering including Strutting, Propping & removal of forms for sloping or battering surface (slabs, beams, louvers, etc) including folded plates columns, pillars, posts and struts (circular or curved in plan) | 17 | Sqm | - | - | 18% |
| 7 | Providing & Laying cement concrete 1:2:4 (1 cement: 2 Coarse Sand: 4 graded granitic or basaltic stone aggrt. 20mm nominal size) excluding cost of centering, shuttering and finishing in:
All works upto plinth level | 107.8 | Cum | - | - | 18% |
| 8 | Providing & Laying cement concrete 1:2:4 (1 cement: 2 Coarse Sand: 4 graded granitic or basaltic stone aggrt. 20mm nominal size) excluding cost of centering, shuttering and finishing in:
in retaining walls, return walls (any thk) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets etc upto floor five level. | 18.7 | Cum | - | - | 18% |
| 9 | Providing and Laying in position (1:11/2:3) Reinforced Cement Concrete excluding the cost of centering, shuttering, finishing and reinforcement (1 cement : 1 1/2 Coarse Sand : 3 graded stone agg 20 mm nominal size)
All works upto plinth level | 28.8 | Cum | - | - | 18% |
| 10 | Providing and Laying in position (1:11/2:3) Reinforced Cement Concrete excluding the cost of centering, shuttering, finishing and reinforcement (1 cement : 1 1/2 Coarse Sand : 3 graded stone agg 20 mm nominal size)
In walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. upto floor five level. | 9.8 | Cum | - | - | 18% |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.69 MB
Tendernotice_2.pdf
PDF • 0.93 MB
BOQ_30935.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].