Tender Value
₹23.8 L
EMD Value
₹47,556
Closing Date
15 Jul 2026, 12:00 pm
Similar tender results from the same govt authority in the past 3 years.
SENIOR SUPERINTENDING ENGINEER
NEW KHADHYA BHAWAN, 11A MIRZA GHALIB STREET, KOLKATA 700087
Roof repairing to make godown no. 1,2 and 3 at Balurghat Warehouse in the district of Dakshin Dinajpur storage worthy and moisture free.
2026_WBSWC_1028271_1
07 OF 2026-27 OF SE/WBSWC
Open Tender
CIVIL WORKS
180 days
BALURGHAT, DAKSHIN DINAJPUR
PLEASE REFER TENDER DOCUMENTS
6 documents required · 6 mandatory
₹0
₹47,556
16 Jun 2026
16 Jun 2026
17 Jul 2026
17 Jun 2026
15 Jul 2026
20 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Stopping roof leakages in C.I. or G.C.I. or asbestos roofing. (iii) Closing holes in C.I. or G.C.I. or asbestos roofing with sheet bolt, limpet and bitumen washers, putty etc. | - | Each | 19.07 | - |
| 2 | Taking out carefully G.C.I. or C.I. or asbestos sheets (including ridges etc.) from roof or wall after unscrewing bolts, nuts, screws etc.and stacking the material at site as directed. | 1 | Sqm | 48.86 | ₹48.81 |
| 3 | Aluminium sheet ridging fitted with self tapping screws, EPDM washers etc complete.(Minimum 225mm end lapping).
(A) 300 mm lapping each way (b) With 0.91 mm sheet | - | Mtr | 566.11 | - |
| 4 | M.S. structural works in roof trusses with tubular sections conforming to IS: 806-1968 & IS: 1161- 1998 cnnected to one another with bracket, gusset cleats as per design, direction of Engineer-in-charge complete including cutting to requisite size, fabrication with necessary metal arc welding conforming to IS: 816- 1969 & IS: 9595 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour reqired for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural tubular memebrs as specified in relevent IS code in finished work.
Payment for gusset, bracket, cleat may be made by adding the actual weight of such items with weight of finished structural members. The rates are considered for a height of erection 8 m. / 2nd floor level from the ground. Add 1.5 % extra over the rate for each additional floor or 4m. beyond the initial 8 m. or part thereof.
i) For trusses spanning up to 12.00 m | - | MT | 89,289.66 | - |
| 5 | Labour for painting roof surface with Bitumen (using 135 kg (avg.) per % Sq.m.)including cleaning roof, heating bitumen as directed and spreading sand and complete including cost of sand @ 0.6 cu.m. per % Sq.m. and cost of carriage of Bitumen from deptt godown but excluding the cost of bitumen. (If heating is not reqd. then deduct Rs.3.45/- per Sq.m) | 1 | Sqm | 77.65 | ₹77.57 |
| 6 | Supplying & laying 3mm thick pre-fabricated plastomeric water proofing membrane conforming to EN 12311-1 & ASTMD 5147, manufactured with atactic poly propylene (APP) modified premium grade asphalt , specially reinforced with non-woven polyester core with polyester reinforcement @160 gms per sqm & both faces covered with thermo-fusible polyethylene film /MineraL on top face over a coat of primer @ 0.40 lit/sqm of manufacturer's specification on smooth,clean dry surface prepared wherever required.Lap joint shall be provided of 75 mm in longitudinal & 100 mm in transverse direction and fused using LPG/ Propane torch employing extra care ensuring full bondage, complete removal of entrapped air and sealing edges into grooves in appropriate manner as per direction of Engineer -in-charge all complete including materials,labour and applicable taxes. (Payment shall be made on the basis of finished surface area.) | 1 | Sqm | 485.06 | ₹484.57 |
| 7 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved
thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor)
(e) Extra for staging beyond 4 m in any floor (Mode of measurement: area in plan x mean height of staging upto soffit of shuttering above initial 4 m) | - | Cum | 71.51 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.45 MB
2911ii.pdf
Tender Documents • 0.50 MB
Annexure-II.pdf
Tender Documents • 1.43 MB
BOQ_2525720.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid