Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L3₹2.8 Cr+₹10.7 L (3.85%)Accepted-AOC BHAJAN GARH KAILASH GATE MUNI KI RETI DISTT TEHRI GARHWAL | ₹2.8 Cr+₹10.7 L (3.85%) Quoted ₹2.9 Cr | L3 | Accepted-AOC As per Terms and condations |
| 2 | L1₹2.8 CrRejected-AOC | ₹2.8 Cr | L1 | Rejected-AOC As per Terms and condations |
| 3 | L2₹2.8 Cr+₹2.1 L (0.74%)Rejected-AOC | ₹2.8 Cr+₹2.1 L (0.74%) | L2 | Rejected-AOC As per Terms and condations |
| 4 | Rejected-Technical | - | - | Rejected-Technical Techno-Commercially not acceptable Bidder |
| Sl No | Description | Qty | Unit | TANUJ TOMER AND CONSTRUCTION L3 | SANGAM CONSTRUCTION L1 | indian construction company L2 |
|---|---|---|---|---|---|---|
| 1.00 | Carriage of materials: Carriage of materials by mechanical transport including loading, unloading and stacking: Lime, moorum, building rubbish:1 km | 282 | CUM | 100 ₹28,200 | 98 ₹27,636 | 54 ₹15,228 Lowest |
| 2.00 | Carriage of materials: Carriage of materials by mechanical transport including loading,
unloading and stacking: Earth:1 km | 11,172 | CUM | 110 ₹12,28,920 | 113 ₹12,62,436 | 45 ₹5,02,740 Lowest |
| 3.00 | Earth work: Earth work in surface excavation not exceeding 30 cm in depth but exceeding
1.5 m in width as well as 10 sqm on plan including disposal of excavated earth upto 50 m and lift upto 1.5 m, disposed soil to be levelled and neatly dressed ::All kinds of soil | 2,922 | SQM | 80 ₹2,33,760 Lowest | 80 ₹2,33,760 Lowest | 135 ₹3,94,470 |
| 4.00 | Earth work: Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth. 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead upto 50m and lift upto 1.5m, disposed earth to be levelled and neatly dressed.: All kinds of soil | 8,837 | CUM | 170 ₹15,02,290 | 144 ₹12,72,528 | 140 ₹12,37,180 Lowest |
| 5.00 | Earth work: Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth upto 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m :: All kinds of soil:Pipes, cables etc. exceeding 80 mm dia. but not exceeding 300 mm dia | 1,100 | METER | 350 ₹3,85,000 | 280 ₹3,08,000 | 135 ₹1,48,500 Lowest |
| 6.00 | Earth work:Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 6,445 | CUM | 250 ₹16,11,250 | 160 ₹10,31,200 Lowest | 260 ₹16,75,700 |
| 7.00 | Earth work: Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials.:All kinds of soil | 4,239 | CUM | 80 ₹3,39,120 | 78 ₹3,30,642 | 22 ₹93,258 Lowest |
| 8.00 | Earth work:Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. Unit:cum | 3 | CUM | 2,100 ₹6,300 | 1,699 ₹5,097 | 25 ₹75 Lowest |
| 9.00 | concrete work: Providing and laying in position cement concrete of specified grade
excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 Cement
: 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) Unit:cum CEMENT SHALL BE ISSUED FREE OF COST AT BHEL STORE | 7 | CUM | 4,200 ₹29,400 | 3,971 ₹27,797 Lowest | 4,200 ₹29,400 |
| 10.00 | concrete work: Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement
: 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) Unit:cum CEMENT SHALL BE ISSUED FREE OF COST AT BHEL STORE | 518 | CUM | 4,400 ₹22,79,200 | 4,060 ₹21,03,080 | 3,200 ₹16,57,600 Lowest |
Tender Value
Refer Docs
EMD Value
₹2 L
Closing Date
28 Apr 2026, 9:00 amClosed
AGM (WE and S)
BHEL Haridwar
Civil work for CDS, Water and Sewer lines, Roads and associated works in BHEL, Haridwar
2026_BHEL_60242_1
FF/26/FCX/CP/CC/01/001
Open Tender
Civil Works
Item Rate
365 days
BHEL Haridwar
AS PER TENDER DOCUMENT
3 documents required · 3 mandatory
₹0
₹2 L
7 Aug 2026
17 Apr 2026
28 Apr 2026
17 Apr 2026
28 Apr 2026
17 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Carriage of materials: Carriage of materials by mechanical transport including loading, unloading and stacking: Lime, moorum, building rubbish:1 km | 282 | CUM | - | - |
| 2 | Carriage of materials: Carriage of materials by mechanical transport including loading,
unloading and stacking: Earth:1 km | 11,172 | CUM | - | - |
| 3 | Earth work: Earth work in surface excavation not exceeding 30 cm in depth but exceeding
1.5 m in width as well as 10 sqm on plan including disposal of excavated earth upto 50 m and lift upto 1.5 m, disposed soil to be levelled and neatly dressed ::All kinds of soil | 2,922 | SQM | - | - |
| 4 | Earth work: Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth. 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead upto 50m and lift upto 1.5m, disposed earth to be levelled and neatly dressed.: All kinds of soil | 8,837 | CUM | - | - |
| 5 | Earth work: Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth upto 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m :: All kinds of soil:Pipes, cables etc. exceeding 80 mm dia. but not exceeding 300 mm dia | 1,100 | METER | - | - |
| 6 | Earth work:Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 6,445 | CUM | - | - |
| 7 | Earth work: Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials.:All kinds of soil | 4,239 | CUM | - | - |
| 8 | Earth work:Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. Unit:cum | 3 | CUM | - | - |
| 9 | concrete work: Providing and laying in position cement concrete of specified grade
excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 Cement
: 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) Unit:cum CEMENT SHALL BE ISSUED FREE OF COST AT BHEL STORE | 7 | CUM | - | - |
| 10 | concrete work: Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement
: 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) Unit:cum CEMENT SHALL BE ISSUED FREE OF COST AT BHEL STORE | 518 | CUM | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.28 MB
Tendernotice_2.pdf
PDF • 1.87 MB
BOQ_65214.xls
BOQ • 0.49 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .