Tender Value
₹2.0 Cr
EMD Value
₹2.0 L
Closing Date
14 Sept 2026, 6:00 pm
Executive Engineer, Surendranagar Irrigation Division, Surendranagar
Construction of Dhrangadhra (jasapar) checkdam across tributary of falku river near village Dhrangadhra (jasapar) And construction of vavdi checkdam across falku river near village vavdi Ta: dhrangadhra, District: Surendranagar
338458
08 of 2026-27
Open
Civil Works - Others
Lump-sum
Surendranagar
6 documents required · 5 mandatory · 1 optional
₹3,600
Executive Engineer, Surendranagar Irrigation Division, Surendranagar
₹2.0 L
25 Aug 2026
25 Aug 2026
25 Aug 2026
14 Sept 2026
25 Aug 2026
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr.)
SURENDRANAGAR IRRIGATION DIVISION - SURENDRANAGAR
Name of Work : CONSTRUCTION OF DHRANGADHRA (JASAPAR) CHECKDAM ACROSS TRIBUTARY OF FALKU RIVER NEAR VILLAGE DHRANGADHRA (JASAPAR), TALUKA:-
DHRANGADHRA, DISTRICT:- SURENDRANAGAR
Memorandum showing Items of Woks to be carried out
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
estimated but In Figures In words according to
may be more estimated quantities
1 2119.00 Excavation in all sort of strata and formations incl. depositing the unusefull excavated stuffas and where directed incl 79.00 Seventy Nine Rupees Cum.
sorting and stacking useful materials as directed up to 200 m. lead and all lifts etc. complete incl. dewatering. (a) In
Overburden incl. HM
2 802.00 Prov. & Laying in position cement concrete using cement , sand and crushed metal coarse aggregate by mass and 3423.00 Three Thousand Four Cum.
machine mix for PCC/RCC including necessary formworks compaction by vibrator,curing as directed with all lead & lift Hundred and twenty
etc complete. (Excluding cost of steel ) FOR .BODY WALL, APRON, TRAINING WALL, SIDE WALL, SPLAY WALL, KEY Three Rupees only
WALL, CUT OF WALL ETC.
4/C) Controlled Concrete grade M-15 and MSA-40mm
3 10.73 Providing,cutting,bending,binding and fixing in position as per drawing .TMT BAR , reinforcement for R.C.C. works and 76574.00 Seventy Six Thousand M.T.
anchor bars incl cost of black annealed 16 to 18 BWG M.S.. Wire etc.complete with all lead and lift. (b) FE 500 Five Hundred Seventy
Four Rupees Only
4 51.00 Backfilling with appropriate excavated material behind structure or refilling the trench with excavated useful material 84.00 Eighty Four Rupees Only Cum.
etc. complete all lead and all lift
5 784.00 Providing and laying STONE LOANCHING APRON by using 50% stone which having weighing not less than 40 Kg or as 765.00 seven hundred sixty five Cum.
specified incl hand packing and filling the interstices by spouls etc complete with all lead and lift. only
6 504.00 Providing and laying dry rubble pitching with 20 cms gravel/metal and 20 cms sand layers as base of inverted graded 723.00 seven hundred twenty Sqmt.
filter and without header stone but incl.hand packing trimming & dressing of slopes etc complete. three only
B) 45 cms thick stone pitching
7 65.00 Providing and laying graded filters of sand,gravel/metal and over size metal ( 100 to 150 mm) behind the retaining wall 530.00 Five Hundred And Thirty Cum.
& wing walls as directed as per approved drawing with all lead and lifts etc complete. Rupees Only
8 27.00 Providing and fixing in position 100/110 mm dia PVC Pipe weep holes in the retaining walls/sidewall/abt etc 358.00 Three Hundred and fifty Rmt.
Eight Rupees only
9 1.00 Providing and fixing in position White marble plate of Size 45 x 45 x 1.8 cms including engraving The letters as per 1350.00 One Thousand Three No.
drawing/ directed etc. complete. Hundred Fifty Rupees
1000.00 Jungle Clearance of specified category and bushes for canal/dam work as directed with depositing materials etc
10 four rupee and ten paisa
completing. (Excluding tree of girth above 0.5 mtr) sq.m
11 1.00 Care & diversion of river/creek incl. required dewatering during construction of earthen dam, C.O.T. and allied works as 1% One Percent Per Job Job.
prescribed and directed etc. complete.
In Words Rs. ( forty seven lakh ninety nine Thousand eight hundred ten and ninety Paisa Only)
I/We am/are willing to carry out the work at % above/ below present (should be written in figures and words)
of the estimated rates mentioned above. An amount of my/our tender works out as under:
* Estimated Amount * Estimated Amount
Put to tender Rs_____________________________ Put to tender Rs_________________
In Words (Rs. ) In Words Rs.( )
(Pease strike out whichever is not applicable)
Note-1: The Contractor shall exhibit a board with brief details of work as directed by the Engineer-In-Charge for which no extra payment shall bemade.
Note-2: Thel abour cess will be deducted as per prevailing rules i.e. 1% of the work done.
Note-3: GST and Incometax TDS will be deducted at a source while making payments of bills
Note-4: In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R. NO.: MIS102010/17/K1 Dated:30/07/2018 as stated in S.O.R. therefore in R.C.C. items where there is a change as per actual
mix design the cost of difference of cement consumption have been deducted from the rate of original item at the rate of input rate mentioned in all the tender.
Executive Engineer
Signature of Contractor. Surendranagar Irrigation Division
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr.)
SURENDRANAGAR IRRIGATION DIVISION - SURENDRANAGAR
Name of Work : construction of vavdi checkdam across falku river near village vavdi, taluka: dhrangadhra, dist:surendranagar
Memorandum showing Items of Woks to be carried out
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
estimated but In Figures In words according to
may be more estimated quantities
1 7087.00 Excavation in all sort of strata and formations incl. depositing the unusefull excavated stuffas and where directed incl 79.00 Seventy Nine Rupees Cum.
sorting and stacking useful materials as directed up to 200 m. lead and all lifts etc. complete incl. dewatering. (a) In
Overburden incl. HM
2 2941.15 Prov. & Laying in position cement concrete using cement , sand and crushed metal coarse aggregate by mass and 3423.00 Three Thousand Four Cum.
machine mix for PCC/RCC including necessary formworks compaction by vibrator,curing as directed with all lead & lift Hundred and twenty
etc complete. (Excluding cost of steel ) FOR .BODY WALL, APRON, TRAINING WALL, SIDE WALL, SPLAY WALL, KEY Three Rupees only
WALL, CUT OF WALL ETC.
4/C) Controlled Concrete grade M-15 and MSA-40mm
3 32.48 Providing,cutting,bending,binding and fixing in position as per drawing .TMT BAR , reinforcement for R.C.C. works and 76574.00 Seventy Six Thousand M.T.
anchor bars incl cost of black annealed 16 to 18 BWG M.S.. Wire etc.complete with all lead and lift. (b) FE 500 Five Hundred Seventy
Four Rupees Only
4 303.00 Backfilling with appropriate excavated material behind structure or refilling the trench with excavated useful material 84.00 Eighty Four Rupees Only Cum.
etc. complete all lead and all lift
5 1594.60 Providing and laying STONE LOANCHING APRON by using 50% stone which having weighing not less than 40 Kg or as 765.00 seven hundred sixty five Cum.
specified incl hand packing and filling the interstices by spouls etc complete with all lead and lift. only
6 713.60 Providing and laying dry rubble pitching with 20 cms gravel/metal and 20 cms sand layers as base of inverted graded 723.00 seven hundred twenty Sqmt.
filter and without header stone but incl.hand packing trimming & dressing of slopes etc complete. three only
B) 45 cms thick stone pitching
7 350.30 Providing and laying graded filters of sand,gravel/metal and over size metal ( 100 to 150 mm) behind the retaining wall 530.00 Five Hundred And Thirty Cum.
& wing walls as directed as per approved drawing with all lead and lifts etc complete. Rupees Only
8 71.00 Providing and fixing in position 100/110 mm dia PVC Pipe weep holes in the retaining walls/sidewall/abt etc 358.00 Three Hundred and fifty Rmt.
Eight Rupees only
9 1.00 Providing and fixing in position White marble plate of Size 45 x 45 x 1.8 cms including engraving The letters as per 1350.00 One Thousand Three No.
drawing/ directed etc. complete. Hundred Fifty Rupees
5695.00 Jungle Clearance of specified category and bushes for canal/dam work as directed with depositing materials etc
10 four rupee and ten paisa
completing. (Excluding tree of girth above 0.5 mtr) sq.m
11 1.00 Care & diversion of river/creek incl. required dewatering during construction of earthen dam, C.O.T. and allied works as 1% One Percent Per Job Job.
prescribed and directed etc. complete.
In Words Rs. ( one carore fifty two lakh sixty two Thousand six hundred ninety nine and ten Paisa Only)
I/We am/are willing to carry out the work at % above/ below present (should be written in figures and words)
of the estimated rates mentioned above. An amount of my/our tender works out as under:
* Estimated Amount * Estimated Amount
Put to tender Rs_____________________________ Put to tender Rs_________________
In Words (Rs. ) In Words Rs.( )
(Pease strike out whichever is not applicable)
Note-1: The Contractor shall exhibit a board with brief details of work as directed by the Engineer-In-Charge for which no extra payment shall bemade.
Note-2: Thel abour cess will be deducted as per prevailing rules i.e. 1% of the work done.
Note-3: GST and Incometax TDS will be deducted at a source while making payments of bills
Note-4: In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R. NO.: MIS102010/17/K1 Dated:30/07/2018 as stated in S.O.R. therefore in R.C.C. items where there is a change as per actual
mix design the cost of difference of cement consumption have been deducted from the rate of original item at the rate of input rate mentioned in all the tender.
Executive Engineer
Signature of Contractor. Surendranagar Irrigation Division
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr.)
SURENDRANAGAR IRRIGATION DIVISION - SURENDRANAGAR
Name of Work : construction of dhrangadhra (jasapar) checkdam across tributary of falku river near village dhrangadhra (jasapar) and construction of vavdi checkdam across
falku river near village vavdi, taluka: dhrangadhra, dist:surendranagar
Memorandum showing Items of Woks to be carried out
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
estimated but In Figures In words according to
may be more estimated
or less quantities
1 9206.00 Excavation in all sort of strata and formations incl. depositing the unusefull excavated stuffas and where directed incl 79.00 Seventy Nine Rupees Cum.
sorting and stacking useful materials as directed up to 200 m. lead and all lifts etc. complete incl. dewatering. (a) In
Overburden incl. HM
2 3743.15 Prov. & Laying in position cement concrete using cement , sand and crushed metal coarse aggregate by mass and 3423.00 Three Thousand Four Cum.
machine mix for PCC/RCC including necessary formworks compaction by vibrator,curing as directed with all lead & lift Hundred and twenty
etc complete. (Excluding cost of steel ) FOR .BODY WALL, APRON, TRAINING WALL, SIDE WALL, SPLAY WALL, KEY Three Rupees only
WALL, CUT OF WALL ETC.
4/C) Controlled Concrete grade M-15 and MSA-40mm
3 43.21 Providing,cutting,bending,binding and fixing in position as per drawing .TMT BAR , reinforcement for R.C.C. works and 76574.00 Seventy Six Thousand M.T.
anchor bars incl cost of black annealed 16 to 18 BWG M.S.. Wire etc.complete with all lead and lift. (b) FE 500 Five Hundred Seventy
Four Rupees Only
4 354.00 Backfilling with appropriate excavated material behind structure or refilling the trench with excavated useful material 84.00 Eighty Four Rupees Only Cum.
etc. complete all lead and all lift
5 2378.60 Providing and laying STONE LOANCHING APRON by using 50% stone which having weighing not less than 40 Kg or as 765.00 seven hundred sixty five Cum.
specified incl hand packing and filling the interstices by spouls etc complete with all lead and lift. only
6 1217.60 Providing and laying dry rubble pitching with 20 cms gravel/metal and 20 cms sand layers as base of inverted graded 723.00 seven hundred twenty Sqmt.
filter and without header stone but incl.hand packing trimming & dressing of slopes etc complete. three only
B) 45 cms thick stone pitching
7 415.30 Providing and laying graded filters of sand,gravel/metal and over size metal ( 100 to 150 mm) behind the retaining 530.00 Five Hundred And Thirty Cum.
wall & wing walls as directed as per approved drawing with all lead and lifts etc complete. Rupees Only
8 98.00 Providing and fixing in position 100/110 mm dia PVC Pipe weep holes in the retaining walls/sidewall/abt etc 358.00 Three Hundred and fifty Rmt.
Eight Rupees only
9 2.00 Providing and fixing in position White marble plate of Size 45 x 45 x 1.8 cms including engraving The letters as per 1350.00 One Thousand Three No.
drawing/ directed etc. complete. Hundred Fifty Rupees
6695.00 Jungle Clearance of specified category and bushes for canal/dam work as directed with depositing materials etc
10 four rupee and ten paisa
completing. (Excluding tree of girth above 0.5 mtr) sq.m
11 1.00 Care & diversion of river/creek incl. required dewatering during construction of earthen dam, C.O.T. and allied works 1% One Percent Per Job Job.
as prescribed and directed etc. complete.
In Words Rs. ( two carore sixty two Thousand five hundred ten Only)
I/We am/are willing to carry out the work at % above/ below present (should be written in figures and words)
of the estimated rates mentioned above. An amount of my/our tender works out as under:
* Estimated Amount * Estimated Amount
Put to tender Rs_____________________________ Put to tender Rs_________________
In Words (Rs. ) In Words Rs.( )
(Pease strike out whichever is not applicable)
Note-1: The Contractor shall exhibit a board with brief details of work as directed by the Engineer-In-Charge for which no extra payment shall bemade.
Note-2: Thel abour cess will be deducted as per prevailing rules i.e. 1% of the work done.
Note-3: GST and Incometax TDS will be deducted at a source while making payments of bills
Note-4: In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R. NO.: MIS102010/17/K1 Dated:30/07/2018 as stated in S.O.R. therefore in R.C.C. items where there is a change as per actual
mix design the cost of difference of cement consumption have been deducted from the rate of original item at the rate of input rate mentioned in all the tender.
Executive Engineer
Signature of Contractor. Surendranagar Irrigation Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
01- TITLE PAGE.pdf
02- E-Tender Notice.pdf
03- Invitation For Bid.pdf
04- SECTION-1 Instruction to Bidders.pdf
05- SECTION-2 Qualification Information.pdf
06- SECTION-3 Conditions of Contract.pdf
07- SECTION-4 Contract Data.pdf
08- SECTION-5 TO 10 Annexere.pdf
09- Annexure-1 Section-5 Tech Spec.pdf
10- BOQ.pdf
jasapar.pdf
vavdi.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].