| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹32.3 LAccepted-AOC NULL | L1 | Accepted-AOC lowest |
Tender Value
₹29.7 L
EMD Value
₹50,000
Closing Date
3 Oct 2024, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Executive engineer
O/oExecutive engineer, PWD Roads Division, Kannur
One Year Running Contract for various Roads under PWD Roads Section Kannur in Kannur District 16 road stretches for a length of 70.926 kms.-General Civil Work-RC
2024_PWD_690540_2
PWD/RB/TR/12413/2024_5_1_1/1
Open Tender
Civil Works - Roads
Item Rate
365 days
Kannur
Please refer Tender documents.
10 documents required · 10 mandatory
₹2,760
Yes
₹50,000
Yes
19 Nov 2024
26 Sept 2024
5 Oct 2024
26 Sept 2024
3 Oct 2024
26 Sept 2024
Amount
Appendix-A Reactive Maintenance (Initial Rectification Work)
12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
3.13.1.B:Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.<br> Ordinary soil - Mechanical Means - (Depth upto 3 m) <br>
12.8.A.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. PCC Grade M15
12.8.1.C:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications RCC Grade M20 - Using Concrete Mixer - (Without formwork)
12.8.1.C.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br> RCC Grade M20 - Using Concrete Mixer <br>
12.40:Supply, Fitting and Placing un- coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications
Appendix-B Pre-Monsoon Works
10.11:Removal of earth from the choked hill side drain and disposing it on the valley side manually
12.1.1:Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.<br> Ordinary soil - Depth upto 3 m - Manual Means
OD85639/2024-2025:Lifting and replacing of RCC slab from the drain for removing silt/muck causing choking of drain all complete; as per the directions of the engineer-in-charge.
OD85640/2024-2025:Engaging labour for cutting and removing trees/branches, clearing of earth-slips and providing temporary protection work for restoring traffic etc, on various roads as per the directions of the Engineer-in-charge. (Mate)
OD85641/2024-2025:Engaging labour for removing of trees/branches, clearing of earth-slips and providing temporary protection work for restoring traffic etc, on various roads as per the directions of the Engineer-in-charge. (Mazdoor)
OD85642/2024-2025:Engaging Hydraulic Excavator and Loader in order to remove and clear the earth-slip material due to land slippages all complete as per the directions of the engineer-in-charge. All kinds of soil
Appendix-C Proactive/Preventive Maintenance
2.3.1.A:Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness In area of light jungle - By Manual Means
10.3:Maintenance of Earth Shoulder (stripping excess soil) from the shoulder surface to achieve the approved level and compacting with plate compactor
3.11:Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.
OD85643/2024-2025:Supplying and conveying of ready mixed bituminous compound including engaging of labour and auto-pickups required in order to carry out the laying of the bituminous compound by filling potholes occurred during monsoon times or otherwise, controlling traffic etc. all complete as per the direction of the engineer-in-charge.
OD85644/2024-2025:Hiring of Inspection Vehicle; wherein charges applicable as per utilization per km run at a frequency as detailed in the guidelines of running contract along the route convenient to cover entire reach specified in the agreement and as directed by the departmental officer at site.
OD85645/2024-2025:Engaging labour as per requirement for conducting/reporting routine inspections and to take necessary instructions as applicable following the guidelines of running contract all along the route for a day of inspection covering entire reach specified in the agreement and as directed by the departmental officer at site.
OD85646/2024-2025:Providing and fixing of Non-reflective RC (Running Contract) informatory sign made of Non-reflective grade sheeting fixed over Aluminium sheeting 2 mm thick/ Aluminium composite material sheeting 4 mm thick with suitable back supporting frame of MS angle 25x25x3 and supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete min size 45 cm x 45 cm x 60 cm, 60 cm below ground level including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as per approved drawing and clause 801 including lettering symbols etc. 1200 mm x 600 mm rectangular
55.8.a:Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 36mm departmental broken stone and compacting with power roller to get a compact surface.
55.9.a:Filling up pot holes (cut and formed to regular shapes and all loose and defective materials removed) after supplying a prime coat of hot bitumen using 12mm departmental broken stone and compacting with power roller to get a compact surface.
55.2:Supplying and stacking 12mm hard blue granite broken stone in standard heaps for measurement(IRC 3.2.1.a)
55.4:Supplying and stacking 36mm size hard broken stone in standard heaps for measurement.
5.2.a:Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.
OD127048/2024-2025:Mix seal Surfacing Providing, laying and rolling of close graded premixed surfacing material of 20mm thickness composed of 11.2mm to .9mm(Type A) or 13.2mm to.9mm(Type B)aggregates using Bitumen VG-30 to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a static roller 8-10 KN and finishing to required level and grades as per Technical specification. By Manual means Type A (Bitumen VG-30) (40 mm and above)
Appendix-D Emergency Works
OD85636/2024-2025:Engaging labour for cutting and removing trees/branches, clearing of earth-slips and providing temporary protection work for restoring traffic etc, on various roads as per the directions of the Engineer-in-charge. (Mate)
OD85637/2024-2025:Engaging labour for removing of trees/branches, clearing of earth-slips and providing temporary protection work for restoring traffic etc, on various roads as per the directions of the Engineer-in-charge. (Mazdoor)
OD85638/2024-2025:Engaging Hydraulic Excavator and Loader in order to remove and clear the earth-slip material due to land slippages all complete as per the directions of the engineer-in-charge. All kinds of soil
Bidder Name
DKH CONSTRUCTIONS LLP
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1078705.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .