Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹4.7 LAccepted-AOC | 1 | Accepted-AOC L1 | |
| 2 | Rejected-Technical | - | Rejected-Technical L2 |
| Sl No | Description | Qty | Unit | Varghese.K.T L2 | palakkalgireesh L1 |
|---|---|---|---|---|---|
| 1.00Flake Ice Installation Works | |||||
| 1.00 | OD203167/2025-2026
Dismantiling Puff insulated sandwiched panel having both side S.S sheet of thickness of 0.5 mm (SS 304) Tongue and groove panel for wall | 3.22 | sqm | 195.84 ₹630.21 | 192 ₹617.86 Lowest |
| 1.00 | 15.18
Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates,bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead. | 45 | kg | 5.97 ₹268.51 | 5.85 ₹263.25 Lowest |
| 1.00 | OD203169/2025-2026
Dismantling roofing including ridges, hips, velleys and gutters etc., and stacking the material within 50 metres lead of Aluminium Sheet | 18 | sqm | 1,739.27 ₹31,306.92 | 1,705.17 ₹30,693.06 Lowest |
| 1.00 | 15.2.2
Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) | 0.29 | cum | 1,585.52 ₹456.63 | 1,554.43 ₹447.68 Lowest |
| 1.00 | OD203174/2025-2026
Dismantling Kotta, marble work or precast concrete work manually / by mechanical means including stacking of serviceable and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge: In cement mortar | 9.45 | sqm | 1,113.74 ₹10,525.94 | 1,091.9 ₹10,319.55 Lowest |
| 1.01 | 2.1.1
Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil | 1.44 | sqm | 136.87 ₹197.1 | 134.19 ₹193.23 Lowest |
| 1.01 | 5.1.2
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) | 3.35 | cum | 10,698.55 ₹35,893.62 | 10,488.77 ₹35,189.82 Lowest |
| 1.01 | 10.2
Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | 1,049.51 | kg | 158.1 ₹1,65,927.37 | 155 ₹1,62,673.89 Lowest |
| 1.01 | 13.52.1
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.On steel work | 45.9 | sqm | 258.01 ₹11,841.58 | 252.95 ₹11,609.39 Lowest |
Tender Value
₹4.6 L
EMD Value
₹11,463
Closing Date
25 Feb 2026, 3:00 pmClosed
Managing Director, Matsyafed
Matsyafed Head Office, Kamaleswaram, Manacaud P.O, Thiruvananthapuram
PMMSY - Civil Works for Installation of Flake Ice Unit at Matsyafed CPC, Sakthikulangara Kollam
2026_MFED_833729_1
MFED/160/2024-ENGG
Open Tender
Civil Works - Buildings
Item Wise
Sakthikulangara
Please refer Tender documents.
10 documents required · 10 mandatory
₹1,015
Yes
₹11,463
Yes
1 Oct 2026
16 Feb 2026
27 Feb 2026
16 Feb 2026
25 Feb 2026
16 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Flake Ice Installation Works | |||||
| 1.001 | OD203167/2025-2026
Dismantiling Puff insulated sandwiched panel having both side S.S sheet of thickness of 0.5 mm (SS 304) Tongue and groove panel for wall | 3.22 | sqm | - | - |
| 1.002 | 15.18
Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates,bolts, nuts, cutting rivets, welding etc. including dismembering and stacking within 50 metres lead. | 45 | kg | - | - |
| 1.003 | OD203169/2025-2026
Dismantling roofing including ridges, hips, velleys and gutters etc., and stacking the material within 50 metres lead of Aluminium Sheet | 18 | sqm | - | - |
| 1.004 | 15.2.2
Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) | 0.29 | cum | - | - |
| 1.005 | OD203174/2025-2026
Dismantling Kotta, marble work or precast concrete work manually / by mechanical means including stacking of serviceable and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge: In cement mortar | 9.45 | sqm | - | - |
| 1.006 | 2.1.1
Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil | 1.44 | sqm | - | - |
| 1.007 | 5.1.2
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) | 3.36 | cum | - | - |
| 1.008 | 10.2
Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | 1,049.51 | kg | - | - |
| 1.009 | 13.52.1
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.On steel work | 45.9 | sqm | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1402261.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.11 MB
Tendernotice_2.pdf
PDF • 0.92 MB
Tendernotice_3.pdf
PDF • 0.27 MB
Tendernotice_4.pdf
PDF • 0.44 MB
Tendernotice_5.pdf
PDF • 0.19 MB
Tendernotice_6.pdf
PDF • 0.33 MB
Tendernotice_7.pdf
PDF • 0.18 MB
BOQ_1402261.xls
BOQ • 0.29 MB
corrigendum.pdf
PDF • 0.88 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .