Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹88.6 LAccepted-AOC | ₹88.6 L | L1 | Accepted-AOC AOC |
| 2 | Rejected-Technical | - | - | Rejected-Technical Second Lowest |
| Sl No | Description | Qty | Unit | PRAHALAD SINGH RAWAT L2 | ANUP PRAKASH CHAUHAN L1 |
|---|---|---|---|---|---|
| 1.00Supply, Carting, laying, jointing, fixing, testing & commissioning of following sizes of G.I. pipe as per latest IS : 1239 codes specification (Class medium) with specials & fittings in trenches underground including cutting, threading etc. complete in all respect or as per direction of Engineer in charge. | |||||
| 1.10 | 20mm | 9,025 | Rm | 259.22 ₹23,39,460.5 | 259 ₹23,37,475 Lowest |
| 1.20 | 25mm | 1,768 | Rm | 366.65 ₹6,48,237.2 | 366 ₹6,47,088 Lowest |
| 1.30 | 50mm | 2,268 | Rm | 683.92 ₹15,51,130.56 | 683 ₹15,49,044 Lowest |
| 2.00Excavation of earth for Pipe Line trenches of Supply Main in following strata requiring the use of special T&P such as Pick Axes, Sabbals etc. or by blasting or by crow bars with a lift up to 1.5 m and lead up to 30 m including refilling, watering and ramming of excavated earth into the trenches and removal and disposal of surplus earth up to a distance of 60 m from the trenches including supply of all materials, labour, T&P etc. complete. Assuming that 90% Pipeline is laid in trenches & also it is estimated that 75% trenches will be in soil mixed with shingle, bazri, boulder and rest of 25% will be in medium rock. | |||||
| 2.10 | Soil mixed with single boulder with bazri | 3,173.82 | Cum | 418 ₹13,26,656.76 Lowest | 418 ₹13,26,656.76 Lowest |
| 2.20 | Medium Rock | 1,057.94 | Cum | 676 ₹7,15,167.44 | 674 ₹7,13,051.56 Lowest |
| 3.00Supply, cartage & fixing of Air Valve(IS 778 class-I) of following dia. including supply of all necessary T&P like flanges, nut bolts, rubber gaskets, etc. complete as per latest IS speciation or as per satisfaction & approval of Engineer in Charge. | |||||
| 3.10 | 25mm | 3 | Each | 2,329 ₹6,987 Lowest | 2,329 ₹6,987 Lowest |
| 3.20 | 32mm | 1 | Each | 3,840 ₹3,840 Lowest | 3,840 ₹3,840 Lowest |
Tender Value
₹82 L
EMD Value
₹1.6 L
Closing Date
12 Jun 2023, 9:00 amClosed
Superintending Engineer
Superintending Engineer Construction Circle Uttarakhand Peyjal Nigam Gopeshwar
Salna water supply scheme in block Pokhari Distt Chamoli
2023_MDPEY_57367_3
742/Lekha 05/282 Dated 12.04.2023
Open Tender
Civil Works
Item Rate
270 days
block Pokhari Distt Chamoli
Please refer Tender documents.
3 documents required · 3 mandatory
₹3,540
Executive Engineer Construction Division UKPJN
₹1.6 L
30 Sept 2025
2 Jun 2023
13 Jun 2023
2 Jun 2023
12 Jun 2023
2 Jun 2023
Amount
Supply, Carting, laying, jointing, fixing, testing & commissioning of following sizes of G.I. pipe as per latest IS : 1239 codes specification (Class medium) with specials & fittings in trenches underground including cutting, threading etc. complete in all respect or as per direction of Engineer in charge.
Excavation of earth for Pipe Line trenches of Supply Main in following strata requiring the use of special T&P such as Pick Axes, Sabbals etc. or by blasting or by crow bars with a lift up to 1.5 m and lead up to 30 m including refilling, watering and ramming of excavated earth into the trenches and removal and disposal of surplus earth up to a distance of 60 m from the trenches including supply of all materials, labour, T&P etc. complete. Assuming that 90% Pipeline is laid in trenches & also it is estimated that 75% trenches will be in soil mixed with shingle, bazri, boulder and rest of 25% will be in medium rock.
Soil mixed with single boulder with bazri
Medium Rock
Supply, cartage & fixing of Air Valve(IS 778 class-I) of following dia. including supply of all necessary T&P like flanges, nut bolts, rubber gaskets, etc. complete as per latest IS speciation or as per satisfaction & approval of Engineer in Charge.
Design, drawing & construction of Air Valve chamber, complete in all respects, as per directions of Engineer in charge including supply of material, labour, T&P and fixing of required size M.H. Cover required for proper completion of work.(Size-0.60x0.60x0.75 M)
Supply and fixing of the following fittings including cartage of materials, labours, T&P etc complete Gate valves (Class-I) as per I S 778/1997
20mm dia
25mm dia
Design, drawing & construction of Gate valve chamber, complete in all respects, as per directions of Engineer in charge including supply of material, labour, T&P and fixing of required size M.H. Cover required for proper completion of work.(Size-0.60x0.60 M)
RCC CWR:-Design, testing bearing capacity of soil and construction of R.C.C. semi sunk Clear Water Reservoir of following capacities in K.L. including supply of necessary scaffolding, shuttering and other accessories along with supply and fixing of inlet and outlet pipes of size equal to sizes of inlet and outlet pipe line, making bye pass arrangement, fixing of overflow pipe in outlet pipe/distribution system, fixing of lightening conductor & M.S. Manhole of size as per norms, supply and fixing of M.S. Steel Ladder outside and inside the tank, and colour washing of approved class snowcem and along with carting of all materials including supply of all materials, labour, T&P etc. complete as per latest IS specification or as per satisfaction & approval of Engineer in Charge.
PROTECTION WORK:-Construction of protection works including necessary Earth Work for Site Development, Service Reservoir etc. as per site conditions wherever necessary as follows :-
Random Rubble stone masonry in 1:6 cement and course sand mortar including supply of all materials, labour, T&P etc. complete.
Random Rubble stone masonry laid dry including supply of all materials, labour, T&P etc. complete.
Supply,cartage of all labour,material & T&P and construction/Fixing of Chlorinator of FRP coated Bucket type of 25 liter capacity over CWR.
Construction of 4.00m wide RCC. B.F.G at Gadhera including construction of intake chamber and supply of all materials,labour, T&P etc. complete.
Construction of R.C.C. Cross wall Gadhera tapping arrangement per running meter length excess over 4 meter gadhera including supply of all materials,labour, T&P etc.
Construction of R.C.C. roughening filter cum screening chamber Including supply of all material labour, T&P as per type design etc complete
Supply of all materials, labours,T&P etc and construction of Break pressure tank.
PRAHALAD SINGH RAWAT
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_72123.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .