Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.9 LAccepted-AOC PATHLYAMATTATHIL HOUSE CHERAD AKATHETHARA P O PALAKKAD | PALAKKAD | PALAKKAD | KERALA | L1 | Accepted-AOC LOWEST | |
| 2 | L2₹9.3 L+₹38,666.99 (4.35%)Rejected-AOC LID AND EW KUMILY GRAMA PANCHAYAT KUMILY | PATHANAMTHITTA | KERALA | 689694 | L2 | Rejected-AOC SECOND LOWEST |
Tender Value
₹8.9 L
EMD Value
₹22,250
Closing Date
29 May 2020, 1:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Biju P Varghese
Assistant Executive Engineer, Irrigation Sub Division No II Chittur
Maintenance work
2020_Irrig_352794_2
39/ET/AEEII/CTR/2019-20
Open Tender
Civil Works - Canal
Item Rate
180 days
Peruvemba
Refer tender documents
6 documents required · 6 mandatory
₹1,870
Yes
online
₹22,250
Yes
9 Jul 2020
13 May 2020
4 Jun 2020
14 May 2020
29 May 2020
14 May 2020
14 May 2020 - 16 May 2020
60 days
Amount
Renovation of pipe culvert and renovation of canal, field channel
15.9.2 : Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
7.1.1 : Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
60.7.9 : RR with Departmental. Stone - Random rubble masonry using departmental rubble in foundation and plinth including through and bond stone and levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with Cement mortar 1:6 (1 cement : 6 coarse sand).
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.3.2 : Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
4.1.5 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
50.13.1 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
13.4.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 coarse sand)
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
4.1.3 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
60.7.4 : DR PACKING FOR APRONS - Rough stone dry packing for apron with good quality blasted rubble including packing to compactness to lines levels, cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
od68283/2019_2020/P1 : Engaging Man mazdoor for removing the sand filled bags laid temporaryduring water distribution
Sebastian
Bidder Name
NIJO P SEBASTIAN
Sebastian
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_501267.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .