Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹3.9 L
EMD Value
₹3,944
Closing Date
15 Oct 2026, 12:00 pm3d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Municipal Engineer
OFFICE OF THE MUNICIPAL COUNCIL Yellareddy
Providing Repairs of Existing 60KL OHSR Including staircase ,Painting of OHSR, and Construction of Cattle Pond and Providing of Pumping Main Pipe for Water supply in ward no.06 of Yellareddy Municipality under 15th Finance Commission Grants
740316
E1/YLRD/83/2026-27
OPEN
Civil Works
KAMAREDDY, TELANGANA
3 documents required · 3 mandatory
₹140
₹3,944
7 Oct 2026
7 Oct 2026
7 Oct 2026
Providing DOUBLE SCAFFOLD using Cashewrina balli props and bracings supporting wooden brackets, wooden stage scaffold boards including hire charges for cashewrina ballies, wooden baords, scaffolds etc., and cost and conveyance of all other consumable accessories, taxes etc complete for finished item of work for ELEVATION AREA Upto Top Slab Quantity
Dismantling of existing Top slab (Not in good codition) structure comprising cement concrete, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202 MORD / MORTH Top slab 60 Kl
dismanteling of RCC railing top slab railing
Chipping and removal of Plastering and loose materials for all the steel exposed surfaces of the OHSR done with CM(1:3), 20mm thick including conveyance charges for disposal of debris from the site and including all labour charges. etc..Complete
Premeasurement of steel for top slab bottom layer and radial bars including Cost of steel and its fabrication charges, bending, cost of binding wire etc., complete as per standard specification
VRCC(1:1.5:3)) using 20 mm HBG metal including cost,conveyance and labour etc.. Complete for Tank top slab/Landing Flat at 12-15m height top slab
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 1000, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications in sections 1500, 1600, 1700 & 2703 MORTH. top slab
Repair of steel railing to bring it to the original shape. It is assumed that the damage to the steel railing is to the extent of 10 %. Stair case
Impervous coat with Plastering in CM(1:3) prop 12/20 mm thick including cost&coveyance of all materials lalbour charges, seign. charges etc. complete for wearing coat.
Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel reinforcement complete as per Technical Specification 2804 MORTH. in side Side wall and bottom slab Inner face of Side Wall
Top surface of Bottom slab
Bottom surface of Top Slab
Painting to new walls with 2 coats of plastic emulsion paint of approved brand and shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges, overhead charges & Contractors profit etc., complete but excluding VAT and seigorage charges for finished item of work as per APSS No.911 for external walls side to brass
Manhole TBSP-B.11-13
Central Phenial
Mesh to Central Phenial
Pumping main Construction of Pipeline for water supply with HDPE pipes as per IS : 4984/1995, with amendments and recisions thereon including supply of pipes, trench excavation for pipelines in ordinary gravelly soils except hard rock requiring blasting, lowering, laying and jointing of pipelines true to alingment and gradient, and refilling trenches with excavated earth (other than rocky soils and bounlders) and removing surplus earth from work site and testing pipeline with water to its required pressure etc., complete. The rates are inclusive of cost, conveyance of all materials and labour carges needed for finished pipeline work and excluding cost of valves and valve chambers. 75mm dia 6kg/cm2 PE-100 Gr
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
06 2026 83.xls
TENDER_DOCUMENT • 0.56 MB
06 2026 83.doc
TENDER_DOCUMENT • 0.06 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .