Tender Value
₹1.9 Cr
EMD Value
₹3.7 L
Closing Date
24 Aug 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
BUILDINGS
14 conditions · 2 needing a document upload
Eligibility in terms of Turnover: The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. NOTE: (i)Financial Year shall normally, be reckoned as 1st April to 31st March of the Next Year. However, for Turnover Criteria, the Financial Year as applicable to the Company/Tenderer is to be considered, if it defers from the above. (ii)Current Financial year is reckoned as the incomplete Financial year in which the date of tender submission falls. (iii)Chartered Accountant statements duly indicating yearly receipts will not be considered until and unless backed by Audited Balance Sheets, Profit & loss account statements. (iv)If the tenderer is not accompanied by the certificates(s) in support of financial eligibility as above, the tender shall be rejected. No post-tender correspondence will be entertained. (v)Attestation of documents may be self attested or attested by a Gazetted Officer.
Eligibility in terms of Experience:(a)The tenderer must have successfully completed or substantially completed any of the following during last 07(seven) years, ending last day of month previous to the one in which tender is invited: Three similar works each costing not less than the amount equal to30% of advertised value of the tender, or Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or One similar work each costing not less than the amount equal to 60% of advertised value of the tender.(b)(1) In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges -substructure, superstructure etc), tenderer must have successfully completed or substantially completed any of the following during last 07(seven)years, ending last day of month previous to the one in which tender is invited: Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender. Note for b(1): Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components. (b)(2) In such cases, what constitutes a component in a composite work shall be clearly pre- defined with estimated tender cost of it, as part of the tender documents without any ambiguity.(b)(3)To evaluate the technical eligibility of tenderer, only components of work as stipulated in tender documents for evaluation of technical eligibility, shall be considered. The scope of work covered in other remaining components shall be either executed by tenderer himself if he has work experience as mentioned in clause 7 of the Standard General Conditions of Contract or through subcontractor fulfilling the requirements as per clause 7 of the Standard GCC or jointly i.e., partly himself and remaining through subcontractor, with prior approval of Chief Engineer in writing. However, if required intender documents by way of Special Conditions, a formal agreement duly notarised, legally enforceable in the court of law, shall be executed by the main contractor with the subcontractor for the component(s) of work proposed to be executed by the subcontractor(s), and shall be submitted along with the offer for considering subletting of that scope of work towards fulfillment of technical eligibility. Such subcontractor must fulfill technical eligibility criteria as follows:The subcontractor shall have successfully completed atleast one work similar to work proposed for subcontract, costing not less than 35% value of work to be subletted, in last 5 years, ending last day of month previous to the one in which tender is invited through a works contract. Note: For subletting of work costing up to Rs 50 lakh, no previous work experience of subcontractor shall be asked for by the Railway. In case after award of contract or during execution of work it becomes necessary for contractor to change subcontractor, the same shall be done with subcontractor(s) fulfilling the requirements as per clause 7 ofthe Standard GCC with prior approval of Chief Engineer in writing.
Defination of Similar Work :- Any Civil Engineering Works (excluding Track works/Zonal works).
17 conditions · 5 needing a document upload
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Tender value is including escalation of (-)15% (Minus Fifteen percent) on CPWD DSR rates. Tenderer should note this before quoting the rates.
The original Bank Guarantee (in lieu of Bid Security) can be sent by the tenderer through a person or through Post/courier so as to reach the nominated Railway official (i,e OS/Tenders/Engg/GTL Division) on any working day before the closing date of submission of bids (i.e excluding the last date for submission of Bids). Railway will not assume any responsibility for any delays in case the BG is sent through Courier/Postal department. Any BG received by Post/Courier on or after the closing date of bid submission shall not be taken cognizance of while evaluating the tender and shall be returned back to the sender by Registered Post.
All the instructions furnished in the Technical Compliance/Commercial Compliance/Custom/ Undertakings/ General Instructions are only indicative and not exhaustive. The tenderer shall read the GCC/ Tender documents for complete details.
The tenderer shall thoroughly go through the entire tender documents and strictly adhere to the instructions and directions given therein.
SW1-Guntakal - Upgradation of infrastructure facilities for homing of Electric Locomotives of existing linking bay at Diesel Shed Guntakal.SW2-Modification to Loco body washing & cleaning plant cum Rain water leakage testing plant on initial account at Electric Loco shed, Guntakal
Engg-GTL-Coord-2136
Engg-GTL-Coord-2136
Open
Works - General
9 Months
Anantapur, Andhra Pradesh
₹0
₹3.7 L
30 Jul 2026
30 Jul 2026
10 Aug 2026
88 items across 4 schedules
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 25,86,169.25 | ||
| — | 143.32 | — | — | ||
| EARTH WORK // General // Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge. // All kinds of soil | — | — | — | 21,623.4 | |
| — | 50.00 | — | — | ||
| EARTH WORK // General // Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. | — | — | — | 8,330 | |
| — | 74.00 | — | — | ||
| EARTH WORK // General // Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. // All kinds of soil | — | — | — | 7,975.72 | |
| — | 13.85 | — | — | ||
| EARTH WORK // General // Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | — | — | — | 25,001.85 | |
| — | 273.00 | — | — | ||
| EARTH WORK // General // Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. | — | — | — | 1,62,551.02 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
GeneralInstructionstoContractor.pdf
ATTACHMENT
GenlCond-forConstofbuildingandbridges1.pdf
ATTACHMENT
specialconditions.pdf
ATTACHMENT
RevisedBrandsandmakesapprovedlist26022026.pdf List of approved brands
ATTACHMENT
DefectsliabilityClause.pdf
ATTACHMENT
JPO-172013-ST.pdf
ATTACHMENT
GTL-MasterDocument-20032026.pdf
ATTACHMENT
IRGCC-ACS-11-13032026_compressed.pdf
ATTACHMENT
RevisedBrandsandmakesapprovedlist26022026.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].