| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.9 LAccepted-AOC | L1 | Accepted-AOC Lowest bidder | |
| 2 | L2₹4.9 L+₹4,841.17 (0.99%)Rejected-AOC | L2 | Rejected-AOC second lowest bidder | |
| 3 | L3₹5.3 L+₹38,949.85 (7.97%)Rejected-AOC | L3 | Rejected-AOC third lowest bidder |
Tender Value
₹6.5 L
EMD Value
₹16,188
Closing Date
19 Aug 2024, 5:00 pmClosed
Assistant Executive Engineer
O/o Assistant Executive Engineer Irrigation Sub Division NO.I Chittur , Pin-678104
CADA Rectification work
2024_Irrig_684895_1
IRR/PI/TR/4209/2022_5_8_7/1
Open Tender
Civil Works - Canal
Item Rate
270 days
Chittur
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,605
Yes
₹16,188
Yes
19 Oct 2024
9 Aug 2024
23 Aug 2024
9 Aug 2024
19 Aug 2024
9 Aug 2024
9 Aug 2024 - 12 Aug 2024
Amount
RECTIFICATION OF CADA FIEDLD CHANNEL
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for: Edges of slabs and breaks in floors and wallsUnder 20 cm wide
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
2.25:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
TARIKH ANVAR E
SIVADAS C
Bidder Name
SIVADAS C
TARIKH ANVAR E
SURESH M
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1065794.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .