| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.5 LAccepted-AOC BIJAHARPUR | WEST BENGAL | ₹11.5 L | L1 | Accepted-AOC STANDS 1ST LOWEST AND ACCEPTED. |
| 2 | L2₹13.6 LRejected-Finance NAWABPUR RAJARHAT KOLKATA 700135 | KOLKATA | 24 PARAGANAS NORTH | WEST BENGAL | 700135 | ₹13.6 L | L2 | Rejected-Finance STANDS 2ND LOWEST AND REJECTED |
| 3 | L3₹13.7 LRejected-Finance 140 1 110 N S C BOSE ROAD REGENT PARK KOLKATA WEST BENGAL 700040 | KOLKATA | KOLKATA | WEST BENGAL | 700040 | ₹13.7 L | L3 | Rejected-Finance STANDS 3RD LOWEST AND REJECTED |
| 4 | L4₹13.8 LRejected-Finance GURERAIT RAJARHAT KOLKATA 700 135 | KOLKATA | 24 PARAGANAS NORTH | WEST BENGAL | 700135 | ₹13.8 L | L4 | Rejected-Finance STANDS 4TH LOWEST AND REJECTED |
Tender Value
₹13.7 L
EMD Value
₹27,322
Closing Date
17 Feb 2026, 2:00 pmClosed
GENERAL MANAGER (ENGG.)-I, WBHIDCO LTD.
HIDCO BHABAN, 2nd Call, Premises No. 35-1111, Biswa Bangla Sarani, 3rd Rotary, New Town, Kolkata-700156
Supply, Fitting and Fixing of IRC Fabric Mesh Fencing along the boundary of Plot No. - 1242, Mouza-Chakpachuria, AA-II(CBD), New Town, Kolkata.
2026_HIDCO_998458_1
HIDCO/GM(E)-I/NIT-43/2025-26
Open Tender
CIVIL WORKS
Percentage
30 days
NEW TOWN, KOLKATA
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹27,322
6 Aug 2026
3 Feb 2026
19 Feb 2026
3 Feb 2026
17 Feb 2026
7 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.
(a) Depth of excavation not exceeding 1,500 mm. | 14.85 | Cum | 119.27 | ₹1,771.16 |
| 2 | Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches. | 49.5 | Sqm | 24 | ₹1,188 |
| 3 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. | 14.85 | Cum | 6,136.04 | ₹91,120.19 |
| 4 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor).
(f) 25 mm to 30 mm shuttering without staging in foundation | 198 | Sqm | 209 | ₹41,382 |
| 5 | Supplying fitting and fixing I.R.C. fabric mesh with covering battens including cost of screws etc complete (excluding the cost of battens).In ground floor. (b) 75mm x 25mm x 2.7mm x 2.7mm. | 780 | Sqm | 231 | ₹1,80,180 |
| 6 | M.S. structural works with hollow sections (square or rectangular shape) conforming to IS: 806-1968 & IS:1161-1998) connected to one another with bracket, gusset, cleat as per design, drawing & direction of Engineer-in-Charge complete including cutting to requisite shape & size, fabrication including metal arc welding conforming to IS: 816-1969 & IS: 9595 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and
erection all complete.
The rate includes the cost of all M.S. Hollow section, all consumables such as electrodes, gas and hire charges of all tools and plants and labour reqired for execution and all incidental chages (such as electricity, labour insurance) etc. complete.
Payment to be made on the basis of calculated weight of structural
memebrs of MS Holow Section as specified in relevent IS code in
finished work. Payment for gusset, bracket, cleat may be made by
adding the actual weight of such items with weight of finished
structural members. The rates are considered for a hight of erection
8 m. / 2nd floor level from the ground. Add 1.5 % extra over the rate
for each additional floor or 4m. beyond the initial 8 m. or part
thereof.
ii) For other Structural works like galleries etc. | 9.4 | MT | 74,900 | ₹7,04,209.8 |
| 7 | Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc. | 780 | Sqm | 29 | ₹22,620 |
| 8 | Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface b ysand paperin etc. including using of approved putty etc. on the surface, if necessary : Two coats (with any shade except white) | 780 | Sqm | 79 | ₹61,620 |
| 9 | Clearing compound premises of shurbs, plants, jungles etc. by cutting and removing as directed (Specific permission of Engineer-in-Charge prior to execution will be necessary). (Payment to be made on area cleared) | 2,600 | Sqm | 11 | ₹28,600 |
| 10 | Labour charge for cleaning the garbage around boundary wall (Un-Skilled Labour) | 35 | Each | 437 | ₹15,295 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.39 MB
2911.pdf
Additional Documents • 0.09 MB
BOQ_2444956.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].