Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
Refer Docs
Closing Date
21 Oct 2026, 3:00 pm3d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer
Executive Engineer DW and S Mech Div Gumla
Supply Installation and commissioning of 350 KVA power transformer controlled panel starter and allied accessories at Ramrekha pumping plant
2026_DWSD_119897_1
E-QUOTATION - 17/2026-27
Open Tender
Pumps/Motors
Empanelment
90 days
GUMLA
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
Exempted
14 Oct 2026
14 Oct 2026
22 Oct 2026
14 Oct 2026
21 Oct 2026
14 Oct 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 2 | Supply installation, testing & commissioning of outdoor tape 350 KVA 11/0.433 copper wound distribution transformer with offload tap changer 12.5% to 2.5% in step of 2.5% continuously rated for three phase. 50 Hz, full load and temperature rise not exceeding 45°C by thermometer in oil and 50°C by the resistance in winding after continuous run at full load rating, the transformer should have oil immersed winding having vector group of DY II. HT side connect in delta and LT side connect in star with neutral brought out connected. The transformer should have power terminal bushing arrangement on HT side & cable box in LT side with standard fitting for mounting of transformer with first filling of transformer oil including all accessories etc. Transformer shall be latest manufacturing standards as per amended IS specification and the load & NO losses shall be limited to the values given or as per IS or Norms issued by JSEB all complete with all materials. Make Kirloskar/ synergy/ Servocon. | 1 | Job | - | - |
| 3 | Electric substation- Cost of construction of DP structure for transformer, supplying and erecting steel tubular pole. Top bracket channel, back clamp. 11 KV disc insulator with hard ware, earthing set complete. MS nut and bolt, MS angle, GI wire, clamp for transformer base, top channel, D.O fuse angel, stay set complete, 11 KV lighting arrester, etc. complete as per the site requirement ans as per direction of E/I all complete. | 1 | Job | - | - |
| 4 | Cost toward supplying and fitting of 11 KV AB switch of 500A rotating type with all fitting materials. | 1 | Job | - | - |
| 5 | Cost toward supplying and fitting of 500 A copper bus bar inclosed in MS sheet cubical box | 1 | Job | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.22 MB
TC.pdf
Tender Documents • 0.24 MB
BOQ_162208.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .