Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹5.7 Cr
EMD Value
₹11.4 L
Closing Date
8 Dec 2026, 3:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
SUPERINTENDING ENGINEER
AGRA CIRCLE, U.P. AVAS EVAM VIKAS PARISHAD, OFFICE COMPLEX, SECTOR-13, SIKANDRA YOJNA, AGRA
Construction work related to establishment of Center of Excellence in Government Polytechnic, Tundla, Firozabad in collaboration with Tata Technology Limited (TTL)
2026_UPHDB_1208389_1
S.No.-1/NIT-No-3278/UPHDB DATED 05/11/2026
Open Tender
Civil Works
Percentage
365 days
TUNDLA FIROZABAD
Please refer Tender documents.
3 documents required · 3 mandatory
₹8,850
EXECUTIVE ENGINEER, C.D.AGRA-01, U.P.A.V.P., AGRA
₹11.4 L
14 Nov 2026
14 Nov 2026
9 Dec 2026
14 Nov 2026
8 Dec 2026
14 Nov 2026
90 days
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-incharge. All kinds of soil | 678.86 | cum | 132.9 | ₹90,220.49 |
| 2 | Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. Excavation work by mechanical means /manual means beyond 1.5 m (extra cost). | 68.53 | cum | 94.94 | ₹6,506.24 |
| 3 | Providing and injecting chemical emulsion for preconstructional antitermite treatment and creating a chemical barrier under and around the column pits wall trenches basement excavation top surface if plinth filling junction of wall and floor, along the the external perimeter of binding expansion joints, surrounding of pipes and conduits etc, complete (plinth area of the building at ground Floor)
Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor:
With Chlorpyriphos/Lindane E.C. 20% with 1%
concentration | 659.94 | sqm | 232.15 | ₹1,53,205.07 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 117.49 | cum | 5,100.41 | ₹5,99,247.17 |
| 5 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 15 in .foundation and plinth in :Cement mortar 1:6 (1 cement : 6 coarse sand) | 47.52 | cum | 6,169.48 | ₹2,93,173.69 |
| 6 | Providing and laying in position ready mixed or sitebatched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana /Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge, for the following grades of concrete.: Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement..All works upto plinth level Concrete of M25 grade with minimum cement content of 330 kg /cum R.C.C. work in Plinth Beam | 264.85 | cum | 7,116.57 | ₹18,84,823.56 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for :Foundations, footings, bases of columns, etc. for mass concrete | 433.74 | sqm | 293.62 | ₹1,27,354.74 |
| 8 | Steel reinforcement for R.C.C. work ready to use “cut and bend” rebars of approved make from factory/workshop to construction site including placing in position and binding all complete. Steel reinforcement for R.C.C. work including straightening, cutting, bending (TMT bar). Fe 500-D OR more | 38,212.49 | kg | 74.61 | ₹28,51,033.88 |
| 9 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 452.57 | cum | 146.75 | ₹66,414.65 |
| 10 | Providing and laying LDPE Sheet Under Concreta including supply of all material ,labour and t&p etc.required for completion of work. | 911.97 | sqm | 162 | ₹1,47,739.14 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.15 MB
DRAWING_TTL_TUNDLA_FZD_1.pdf
Additional Documents • 2.14 MB
BOQ_2292886.xls
BOQ • 4.76 MB
TECHNICALBID_TTL_Tundla_FZD_1.pdf
Tender Documents • 17.01 MB
Corrigendum3354.pdf
PDF • 0.63 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .