| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.3 LAccepted-AOC VILL P O DARGIA SAKRI TEHSIL DEHRA DISTT KANGRA HP | MANDI | HIMACHAL PRADESH | 175013 | L1 | Accepted-AOC Lowest 1 | |
| 2 | L3₹13.2 L+₹91,393.35 (7.44%)Rejected-Finance HIMACHAL PRADESH HP | HAMIRPUR | HIMACHAL PRADESH | 174304 | L3 | Rejected-Finance Lowest 3 | |
| 3 | L4₹13.7 L+₹1.4 L (11.6%)Rejected-Finance | L4 | Rejected-Finance Lowest 4 | |
| 4 | L5₹14.1 L+₹1.8 L (14.4%)Rejected-Finance | L5 | Rejected-Finance Lowest 5 | |
| 5 | L6₹14.8 L+₹2.5 L (20.3%)Rejected-Finance | L6 | Rejected-Finance Lowest 6 |
Tender Value
₹14.2 L
EMD Value
₹28,500
Closing Date
14 Dec 2020, 5:00 pmClosed
Executive Engineer
Executive Engineer HP PWD Division Tanda
Construction of link road to Chakban Sarotari Km 0/000 to 2/500 in Distt Kangra (HP) (SH-Construction of Edge wall at RD 0/100 to 0/200 and improvement of formation deficiency in Km 0/780 to 2/500).
2020_PWD_42547_2
PWD-Civil-9437-66
Open Tender
Civil Works - Roads
Item Rate
90 days
Tanda
Please refer Tender documents.
12 documents required · 12 mandatory
₹500
Executive Engineer HP PWD Divison Tanda
₹28,500
17 Feb 2021
3 Dec 2020
15 Dec 2020
3 Dec 2020
14 Dec 2020
3 Dec 2020
Amount
Excavation in hilly area in all heights and depths and in all kind of soil by manual/mechanical means including saturated soil comprising of ordinary soil, soft rock, hard rock, chiseling, wedging out of rock (where blasting is prohibited) and their intermediate classification of soil, setting out true to the required lines, grades, cutting and trimming of side slopes and level as shown in the drawing and as directed by engineer-in-charge at site according to the MORD technical specification clause 302, 1603.1 and 1603.2 and sorting out useful materials and stacking the same in all leads and lifts in acquired width of road and transportation of un-useful material for filling in road ways, camber, embankments for grade improvements and disposal of all surplus material to required width of the road or on approved dumping sites through all modes of transportation including head load or animal transport or mechanical means along with its leveling, fine dressing and carriage of machineries, materials, tools, equipments and safety measures and incidentals necessary to complete the work by mechanical means and labour if required. Recovery of stone to the tune of 696.23 cubic metres quantity at the rate of 300/- per cubic metre shall be effected from the contractor's running bills on pro-rata basis as per actual quantity executed. Any loss to the public, private property during the course of execution shall be the absolute responsibility of the contractor, which shall have to be compensated by him in all cases, as directed by Engineer-Incharge including carriage of material within all leads, lifts and other incidentals.
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material, including entire carriage of materials within all leads, lifts and other incidentals.
Providing and laying concrete for plain/reinforced concrete 1:3:6 (One cement: three sand: Six graded broken/crushed stone aggregate 20mm(Twenty millimeters) nominal size in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 and 1203 PCC grade M-10 (M-ten) including entire carriage of materials within all leads an d lifts and other incidentals.
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia PVC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specifications clauses 614, 709, 1204.3.7 including entire carriage of materials within all leads and lifts and other incidentals.
Backfilling behind abutment, wing wall and return wall complete as per drawings and technical specification Clause 1204.3.8, including entire carriage of materials within all leads, lifts and other incidentals.
VIJAY KUMAR
Vijay Kumar
AMIT KUMAR SHARMA
AKSHAY KAPOOR
DEEPANSHU
Kulbir Kumar
atul thakur
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .