| # | Company | Status |
|---|---|---|
| 1 | Accepted-Technical | Accepted-Technical The bidder is Technically Qualified |
| 2 | Accepted-Technical | Accepted-Technical The bidder is Technically Qualified |
| 3 | Not Admitted-Fee/PreQual/Technical | Not Admitted-Fee/PreQual/Technical Others-1. The bidder has not submitted the Similar work experience certificate as per NIT of one building of Sigle Storied. 2. The average annual turnover is less than the 4.03Crore. As such the bidder is Technically Disqualified. |
Tender Value
₹5.0 Cr
EMD Value
₹10.1 L
Closing Date
20 Jul 2026, 3:00 pmClosed
Executive Engineer (Civil)
Executive Engineer (Civil) Construction and Maintenance Division IIT Hyderabad Kandi Sangareddy-502284
Construction of Directors Residence cum Integrated Office Ancillary Buildings including Boundary wall at IIT Hyderabad Kandi Sangareddy
2026_IITH_915617_1
IITH/CMD/CIV/NIT/2026-27/14
Open Tender
Civil Works - Buildings
EPC Contract
300 days
Construction and Maintenance Division IITHyderabad
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹10.1 L
Conference Hall, CMD, IIT Hyderabad
27 Jul 2026
2 Jul 2026
21 Jul 2026
2 Jul 2026
20 Jul 2026
3 Jul 2026
3 Jul 2026 - 9 Jul 2026
9 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Construction of Director's Residence cum Integrated Office including servant quarter framed structurer with finishing’s
(Payement percentage breakup at Annexure A) | 1 | Lumpsum | - | - |
| 2 | All internal water supply, sanitary & rain water pipe lines and sanitary fixtures and fittings, etc. complete as per the directions of EIC.
(Payement percentage breakup at Annexure B) | 1 | Lumpsum | - | - |
| 3 | External Development Works
(Payement percentage breakup at Annexure C) | 1 | Lumpsum | - | - |
| 4 | Landscaping & Horticulture Works
(Payement percentage breakup at Annexure D) | 1 | Lumpsum | - | - |
| 5 | Payment percentage breakup for Internal Electrical wiring and internal electrification installations, UPS System, Illuminated Signage's, street lighting, compound and Foot Path Lighting, etc.
(Payement percentage breakup at Annexure E) | 1 | Lumpsum | - | - |
| 6 | Payment percentage breakup for External Service Connection from MV Panels at AC Plant-5 and DG Set with AMF Panel and Earthing System
(Payement percentage breakup at Annexure F) | 1 | Lumpsum | - | - |
| 7 | Payment percentage breakup for Supply, Installation, Testing and Commissioning of VRF Based AC System
(Payement percentage breakup at Annexure G) | 1 | Lumpsum | - | - |
| 8 | Payment percentage breakup for Supply, Installation, Testing & Commissioning of Lifts with complete Earthing System
(Payement percentage breakup at Annexure H) | 1 | Lumpsum | - | - |
| 9 | Payment percentage breakup for Automatic Fire Alarm System, Fire Extinguishers
(Payement percentage breakup at Annexure I) | 1 | Lumpsum | - | - |
| 10 | Payment percentage breakup for LAN, Networking system
(Payement percentage breakup at Annexure J) | 1 | Lumpsum | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 26.95 MB
Tendernotice_2.pdf
PDF • 6.16 MB
Tendernotice_3.pdf
PDF • 25.37 MB
Tendernotice_4.pdf
PDF • 15.21 MB
Tendernotice_5.pdf
PDF • 7.43 MB
Tendernotice_6.pdf
PDF • 20.76 MB
Tendernotice_7.pdf
PDF • 10.28 MB
BOQ_962227.xls
BOQ • 0.34 MB
DrawingsforNIT14final.pdf
PDF • 38.08 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .