Tender Value
₹96.3 Cr
EMD Value
₹12 L
Closing Date
23 Apr 2026, 4:00 pmClosed
Additional Chief Engineer(Procurement & Contracts)
Supply, Laying, Erection, Testing and Commissioning of 66kV,1CX630 sqmm XLPE Cable with Poly.Al. / Aluminum construction on EPC basis Various lines under Jambuva Circle.
293021
ACE(P&C)/Contracts/SS/E-446/66kV/UG/S&L,E
Open
Electrical
Turn-key
Vadodara
27 documents required · 20 mandatory · 7 optional
₹11,800
Gujarat Energy Transmission Corporation Limited
₹12 L
1 Apr 2026
1 Apr 2026
1 Apr 2026
23 Apr 2026
1 Apr 2026
the date of bid opening of opening of Technical Bid.
Technical Bid. c) Payment of Earnest Money
Deposit (EMD) will be accepted
by RTGS/NEFT/Online or
Demand Draft or Banker’s
Cheque or Pay Order or Bank
12.2 The bid security is required to 12.2 The bid security is required to
protect the owner against the risk of protect the owner against the risk of
Bidder’s conduct, which would Bidder’s conduct, which would warrant
warrant the guarantee forfeiture, the guarantee forfeiture, pursuant to
pursuant to relevant paras elsewhere relevant paras elsewhere
The bid guarantee shall be made The bid guarantee shall be made
payable to the Owner without any payable to the Owner without any
condition whatsoever. condition whatsoever.
12.3 Any bid not secured in 12.3 Any bid not secured in accordance
accordance with Para 23.1 above will with Para 23.1 above will be rejected by
be rejected by the Owner as non- the Owner as non-responsive. No
responsive. No exemptions are made exemptions are made in the furnishing
in the furnishing of the security. of the security.
Seal & Signature of Bidder
12.4 Unsuccessful Bidder’s bid 12.4 Unsuccessful Bidder’s bid
security/EMD will be security/EMD will be returned/refunded
returned/refunded on finalization of
forthwith on finalization of tender i.e.,
tender or three months-from the date
of submission of tender whichever is once the award of contract, after
later. opening of price bids. However, the Bid
Security/ EMD of the bidder ranked next
(L2) to the bidder determined as the
successful bidder (L1) shall be retained
by GETCO, along with the Bid Security/
EMD of the successful bidder. Bid
Security/ EMD of L2 bidder shall be
returned immediately after the Letter of
Acceptance/ Award (LOA) is issued by
GETCO to the successful bidder and
acknowledged/ accepted by the
successful bidder or the Contract is
signed with the successful bidder,
whichever event occurs earlier.
However, if there is a delay of 21 days
or more in aforesaid events reckoned
from the date of approval of award of
contract by the competent authority, as
aforesaid, the Bid Security/ EMD of the
L2 bidder shall be released immediately
after the said period of 21 days.
If the validity of the bid expires and any
bidder chooses not to extend the bid
validity, the Bid Security/ EMD of such
bidder shall be returned forthwith.
12.5 The successful bidders, Bid 12.5 The successful bidders, Bid
Security will be discharged upon, Security will be discharged upon,
furnishing the contract performance furnishing the contract security deposit /
guarantee. performance guarantee.
12.6 The bid guarantee may be 12.6 The bid guarantee may be forfeited.
a) If a Bidder withdraws its bid
a) If a Bidder withdraws its bid during the period of bid validity
during the period of bid specified by the bidder on the bid
validity specified by the bidder Form:
on the bid Form. b) If a bidder refuses to accept the
b) If a bidder refuses to accept contract or fails to commence the
the contract or fails to works (including supplies within
commence the works thirty days of letter of award of
(including supplies within contract)
thirty days of letter of award of
2. Part –I 47.0 Terms of Payment 47.0 Terms of Payment
General The payment for materials to be The payment for materials to be
Conditions of supplied and erected shall be made supplied and erected shall be made as
Contract/ as under only after execution of the under only after execution of the
Seal & Signature of Bidder
Clause 47.0 contract documents/furnishing of contract documents/furnishing of
and its sub- Security Deposit and on execution of Security Deposit and on execution of
clauses substation work. substation work.
47.1 For supply 47.1 For Supply
47.1.1 Interest Bearing Advance
(i) Interest Bearing Advance
(Optional*): Ten percent (10%) of the
total Ex-works price component of
Substation materials shall be paid as
an interest bearing initial advance, at the
rate of interest as per (ii) below, after
signing the Contract Agreement and on
submission of the following:
(a) Proforma invoice(s),
(b) Advance Bank Guarantee for [{110%
(one hundred ten percent) of the amount
of Advance}], from a Public Sector
Indian bank/Scheduled, Commercial
Bank in the form attached herewith as
Annexure-I (The guarantee shall be
initially valid up to 90 days after the Time
of Completion and shall be reduced at
the end of every Quarter prorata to the
advance adjusted),
(c) Performance Securities in line with
GCC Clause 36.0 including its sub-
Provided further that the Proforma
Invoice(s) for advance payment along
with all supporting documents is
submitted by the Contractor to the
Employer within 3 months from the date
of Letter/ Notification of Award. In case
the Contractor does not submit the
requisite documents including applicable
Bank Guarantee(s) /Security(ies) within
the aforesaid period, the advance shall
not be payable. The Contractor shall,
within 7 days from the date of receipt of
Advance, furnish an Advance Receipt
Voucher to the Employer, as prescribed
under the GST Law.
Note: * This payment is an optional
payment. The Contractor has the option
of taking the interest bearing initial
advance or otherwise. The option for
advance payment is to be indicated by
the bidder in its bid as per the format
attached herewith as Annexure–III and
shall be deemed to be part of the
bidding scheduled referred as
Seal & Signature of Bidder
SCHEDULED-21 to be submitted by the
bidder with Technical bid.
(ii) Interest rate applicable on advance
payment to the Contractor shall be at the
rate equal to one-year MCLR rate [One-
year Tenor rate p.a.] published by State
Bank of India prevailing as on the date
of drawl of advance. The said interest
rate shall remain fixed and shall be
applicable till the advance amount is
fully repaid. The interest will be charged
considering proportionate adjustment of
advance against progressive payment
as per 47.1.2 below. The interest shall
be calculated on the daily progressive
balances outstanding as on the date of
recovery/adjustment. It is the Employer’s
understanding that as per extant
provisions, GST is not payable on
interest paid on the amount of Advance.
The Contractor is, however, advised to
check the position from their own
sources. If payable even at later stage,
the same shall be to the Contractor’s
account and Employer shall not
reimburse any GST on this account.
Recovery of this advance shall be
adjusted in such a way that that all the
sums of advance with interest thereon
shall be fully recovered 3 months prior to
the scheduled Time of Completion,
failing which the whole amount of
advance along with interest thereon
shall be recovered immediately from the
payments due to the Contractor.
The contractor may however, return /
pay to GETCO the unadjusted advance
amount at any stage during the
execution of the work along with the
accrued interest thereon till the time of
return / payment. Alternatively, the
contractor may also request GETCO for
early adjustment of the advance along
with accrued interest.
Further, the Contractor shall submit the
certificate of Tax Deduction at Source
(TDS) on interest within 3 months from
the end of the quarter in which
adjustment of advance has been made
Seal & Signature of Bidder
for claiming refund from Employer. No
claim for refund will be entertained after
end of the aforesaid period of 3 months.
Further, while submitting the TDS
Certificate the details of Contract No,
Project, Region, Quarter etc to which the
TDS certificate pertains, shall also be
submitted tallying the amount with the
TDS Certificate.
In case, the Contractor opts not to take
interest bearing advance as above, it
would be mandatory for him to submit
the documents listed at Sl. No. (i) (c)
above within twenty-eight (28) days of
issuance of Letter/ Notification of Award.
47.1.2 Progressive Payments
(i) 80% of supply value for each
consignment of Sub-Station material (i) (a) 70% of supply value if contractor
including accessories on submission opts to take interest bearing initial
of invoice along with 100% GST, advance or
duties, F & I shall be paid from (b) 80% instead of 70% of supply value if
corporate office within 30 days from contractor opts not to take interest
actual material receipt date bearing initial advance or has opted to
mentioned in SR Note after verifying take interest bearing initial advance but
the following documents. the advance payment has become
A. Tax invoice. each consignment of Sub-Station
B. Delivery challan. material including accessories on
C. Endorsed RR / LR copy. submission of invoice along with 100%
D. Dispatch clearance certificate / GST, duties, F & I shall be paid from
letter wherever applicable. corporate office within 30 days from
E. E Way Bill, if applicable actual material receipt date mentioned in
SR Note after verifying the following
A. Tax invoice.
B. Delivery challan.
C. Endorsed RR / LR copy.
D. Dispatch clearance certificate / letter
wherever applicable.
E. E Way Bill, if applicable
(ii) 10% payment out of balance 20% (ii) 10% of the of supply value shall be
shall be released from corporate paid pro-rata on completion of erection/
office on completion of sub-station installation of substation equipment,
work, handing over and preliminary hardware, structures etc and furnishing
acceptance certificate issued by the of completion certificate from Engineer-
site engineers in charge after in-charge and Chief Engineer (Projects),
rectification work if any and pro-rata on monthly basis.
settlement of material account
according to actual quantity utilized
for completion of S/S. Supply to be
made as per approved drawing/
Seal & Signature of Bidder
(iii) Balance10% of supply value shall
be paid from corporate office on (iii) Balance 10% of supply value shall
successful commissioning of Sub- be paid on completion of on quarterly
Station against completion certificate basis on completion of erection/
and only after settlement of material installation of completed bay(s) in all
account statement of items supplied, respects and liquidation of
used, erected and successful defects/deficiencies of corresponding
commissioning is settled for complete bay on prorata basis and on completion
job and will be released only after certificate from Engineer-in-charge and
passing of final bill. Chief Engineer (Projects) and
submission of an unconditional &
irrevocable Bank Guarantee for amount
paid so that Bank Guarantee available
with the GETCO is of cumulative value
of amount paid on this account, initially
valid till 3 months beyond the scheduled
date of completion of testing &
commissioning of the substation and its
taking over by the GETCO and shall be
extended from time to time till the actual
date of successful completion of testing
& commissioning of substation complete
in all respects and its taking over by the
GETCO, including issuance of
preliminary acceptance certificate issued
by the site engineers in charge after
rectification work if any and settlement of
material account according to actual
quantity utilized for completion of S/S.
Supply to be made as per approved
(iv) Welfare Cess
(iv) Welfare Cess
The modality of payment/
reimbursement of welfare cess will The modality of payment/
be as under. reimbursement of welfare cess will be
On receipt of A/T, the contractor /
bidder will get them registered On receipt of A/T, the contractor /
under Welfare Cess Act and submit bidder will get them registered under
the documentary evidence to the Welfare Cess Act and submit the
concern office. documentary evidence to the concern
Before release of payment of first office.
R.A.Bill, the contractor has to Before release of payment of first
submit the documentary evidence R.A.Bill, the contractor has to submit
of registration. Only thereafter, the the documentary evidence of
bill will be processed for payment. registration. Only thereafter, the bill
Before release of payment of will be processed for payment.
subsequent R.A.Bills, the contractor Before release of payment of
has to submit the documentary subsequent R.A.Bills, the contractor
evidence of payment of welfare has to submit the documentary
cess of previous R.A.Bill. evidence of payment of welfare cess
Before release of payment of Final of previous R.A.Bill.
Bill, the contractor has to submit the Before release of payment of Final
documentary evidence of payment Bill, the contractor has to submit the
of welfare cess of previous R.A.Bill documentary evidence of payment of
as well as the final bill. welfare cess of previous R.A.Bill as
If the R.A.Bill happens to be first well as the final bill.
If the R.A.Bill happens to be first and
Seal & Signature of Bidder
and final bill, then before release of final bill, then before release of
payment, contractor has to submit payment, contractor has to submit
documentary evidence of documentary evidence of registration
registration under Welfare Cess Act under Welfare Cess Act and evidence
and evidence of payment of welfare of payment of welfare cess.
cess. The welfare cess shall be
The welfare cess shall be reimbursed to the contractor on
reimbursed to the contractor on submission of copy of documentary
submission of copy of evidence of payment by observing
documentary evidence of due formalities.
payment by observing due
47.2 For Erection works. 47.2 For Erection works.
Supply of Services Portion.
47.2.1 A. Interest Bearing Initial
Advance (Optional ^^) Ten percent
(10%) at the rate of interest as per
47.2.1 A.1 1st Installment of 05%
(Five) of the total Installation price
component shall be paid on
Establishment of Contractor’s site offices
for preparatory to mobilization for
Installation establishment and on
submission of the following:
(a) Proforma invoice,
(b) Advance Bank Guarantee for [{110%
(one hundred ten percent) of the amount
of Advance} Plus {amount of GST
reimbursable on Advance as per the
Proforma invoice}] from a Public Sector
Indian bank/Scheduled, Commercial
Bank in the form attached herewith as
Annexure-I (The guarantee shall be
initially valid up to 90 days after the Time
of Completion and shall be reduced at
the end of every Quarter prorata to the
advance adjusted),
(c) Performance Securities in line with
GCC Clause 36.0 including its sub-
47.2.1. A.2 2nd Installment of 05%
(Five)^^ of the total Installation price
component shall be paid on start of
equipment erection & certification of the
same by Project Manager and on
submission of the following:
Seal & Signature of Bidder
(a) Proforma invoice(s),
(b) Advance Bank Guarantee for [{110%
(one hundred ten percent) of the amount
of Advance} Plus {amount of GST
reimbursable on Advance as per the
Proforma invoice}] from a Public Sector
Indian bank/Scheduled, Commercial
Bank in the form attached herewith as
Annexure-I (The guarantee shall be
initially valid up to 90 days after the Time
of Completion and shall be reduced at
the end of every Quarter prorata to the
advance adjusted),
(c) Performance Securities in line with
GCC Clause 40.0 including its sub-
(d) A declaration by the Contractor
stating that 1st Installation (5%) of
advance has been utilized against the
mobilization works for the subject
Recovery of this advance shall be
adjusted in such a way that that all the
sums of advance with interest thereon
shall be fully recovered 3 months prior to
the scheduled Time of Completion,
failing which the whole amount of
advance along with interest thereon
shall be recovered immediately from the
payments due to the Contractor.
The contractor may however, return /
pay to GETCO the unadjusted advance
amount at any stage during the
execution of the work along with the
accrued interest thereon till the time of
return / payment. Alternatively, the
contractor may also request GETCO for
early adjustment of the advance along
with accrued interest.
Note: ^^ This payment is an optional
payment. The Contractor has the option
of taking the interest bearing advance or
otherwise. The option for advance
payment is to be indicated by the bidder
in its bid as per the format attached
herewith as Annexure–III and shall be
deemed to be part of the bidding
scheduled referred as SCHEDULE-21 to
be submitted by the bidder with
Seal & Signature of Bidder
Note: After release of various advances,
the rate of recovery of the advance shall
be re-adjusted.
Provided further that the Proforma
Invoice(s) for advance payment along
with all supporting documents as per
para A.1 and A.2 above is submitted by
the Contractor to the Employer within
months from the date of fulfillment of the
requisite activities. In case the
Contractor does not submit the requisite
documents including applicable Bank
Guarantee(s)/ Security(ies) within the
aforesaid period, the advance at A.1 &
A.2 above shall not be payable.
The Contractor, shall, within 7 days from
the date of receipt of Advance, furnish
an Advance Receipt Voucher to the
Employer, as prescribed under the GST
47.2.1 A.3. Interest rate applicable on
advance payment to the Contractor shall
be at the rate equal to one year MCLR
rate [One-year Tenor rate p.a.]
published by State Bank of India
prevailing as on the date of drawl of
advance. The said interest rate shall
remain fixed and shall be applicable till
the advance amount is fully repaid. The
interest will be charged considering
proportionate adjustment of advance
against progressive payment for the
work done as per 47.2.2 below. The
interest shall be calculated on the daily
progressive balances outstanding as on
the date of recovery/adjustment. It is the
Employer’s understanding that as per
extant provisions, GST is not payable on
Interest paid on the amount of Advance.
The Contractor may, however, advised
to check the position from their own
sources. If payable, the same shall be to
the Contractor’s account and Employer
shall not reimburse any GST on this
Further, the Contractor shall submit the
Seal & Signature of Bidder
certificate of Tax Deduction at Source
(TDS) on interest within 3 months from
the end of the quarter in which
adjustment of advance has been made
for claiming refund from Employer. No
claim for refund will be entertained after
end of the aforesaid period of 3 months.
Further, while submitting the TDS
Certificate the details of Contract No,
Project, etc to which the TDS certificate
pertains, shall also be submitted tallying
the amount with the TDS Certificate.
In case, the Contractor opts not to take
interest bearing advance as above, it
would be mandatory for him to submit
the document listed at Sl. No. A1 (c)
and, A2(c) above within twenty-eight
(28) days of issuance of Letter /
Notification of Award.
47.2.2 (i) (a) 80% payment if contractor
opts to take interest bearing initial
(b) 90% payment instead of 80%
payment if contractor opts not to take
(i) 90% payment of amount claimed interest bearing initial advance or has
covering various activities such as opted to take interest bearing initial
excavation, foundation, erection, advance but the advance payment has
earthing, stringing of bus bar and
earthwire including insulator become inadmissible,
hoisting works against R.A. bills of amount claimed covering various
duly certified by EIC within 30 days activities such as excavation,
from the date of R.A. bill. foundation, erection, earthing, stringing
of bus bar and earthwire including
insulator hoisting works against R.A.
bills duly certified by EIC within 30 days
from the date of R.A. bill.
47.2.2 (ii) Balance 10% of erection value
shall be paid against commissioning of
Sub-Station only after settlement of
material account statement of items
supplied, used, erected and successful
(ii) Balance 10% of erection value
shall be paid against commissioning commissioning of Sub-Station line the
of Sub-Station only after settlement same amount will be release in final bill
of material account statement of only and payment will be made only
items supplied, used, erected and after passing of final bill.
successful commissioning of Sub-
Station line the same amount will be
release in final bill only and payment
will be made only after passing of
final bill. (iii) If net payable amount is more than
Rs 5.0 Lacs, payment will be released
Seal & Signature of Bidder
from circle office/corporate office.
(iii) If net payable amount is more
(iv) Welfare Cess
than Rs 5.0 Lacs, payment will be
released from circle office/corporate The modality of payment/
office. reimbursement of welfare cess will be
(iv) Welfare Cess
On receipt of A/T, the contractor /
The modality of payment/ bidder will get them registered under
reimbursement of welfare cess will Welfare Cess Act and submit the
be as under. documentary evidence to the concern
On receipt of A/T, the contractor / Before release of payment of first
bidder will get them registered R.A.Bill, the contractor has to submit
under Welfare Cess Act and submit the documentary evidence of
the documentary evidence to the registration. Only thereafter, the bill
concern office. will be processed for payment.
Before release of payment of first Before release of payment of
R.A.Bill, the contractor has to subsequent R.A.Bills, the contractor
submit the documentary evidence has to submit the documentary
of registration. Only thereafter, the evidence of payment of welfare cess
bill will be processed for payment. of previous R.A.Bill.
Before release of payment of Before release of payment of Final
subsequent R.A.Bills, the contractor Bill, the contractor has to submit the
has to submit the documentary documentary evidence of payment of
evidence of payment of welfare welfare cess of previous R.A.Bill as
cess of previous R.A.Bill. well as the final bill.
Before release of payment of Final If the R.A.Bill happens to be first and
Bill, the contractor has to submit the final bill, then before release of
documentary evidence of payment payment, contractor has to submit
of welfare cess of previous R.A.Bill documentary evidence of registration
as well as the final bill. under Welfare Cess Act and evidence
If the R.A.Bill happens to be first of payment of welfare cess.
and final bill, then before release of The welfare cess shall be reimbursed
payment, contractor has to submit to the contractor on submission of
documentary evidence of copy of documentary evidence of
registration under Welfare Cess Act payment by observing due formalities.
and evidence of payment of welfare
The welfare cess shall be
reimbursed to the contractor on
submission of copy of documentary
evidence of payment by observing
due formalities.
3. Part –I 2.0 Tender Fee 2.0 Tender Fee
(SCC)/ The tender fee plus GST as The tender fee plus GST as
Special applicable specified in notice applicable specified in notice
Conditions of inviting tender is payable by inviting tender is payable by
Contract/ Demand Draft (DD) at Demand Draft (DD) at Vadodara
Clause 2.0 Vadodara drawn on any drawn on any Scheduled Bank in
Scheduled Bank in favour of favour of Gujarat Energy
Gujarat Energy Transmission Transmission Corporation Ltd.
Corporation Ltd. The same The same will be furnished in
will be furnished in Cover-1 of Cover with EMD (Bid Security).
Bid along with EMD (Bid
Security). Payment of Tender Fees will
be accepted by RTGS /
NEFT/Online only.
Seal & Signature of Bidder
4. Part –I 5.0 QUALIFYING REQUIREMENT 5. QUALIFYING REQUIREMENT
Special FINANCIAL CRITERIA: FINANCIAL CRITERIA:
Contract/ 2.1 MAAT (Minimum Average
Clause 5.0 Annual Turnover)
and its sub- Route -1 & Route -2 :- Bidder’s
clauses Minimum Average Annual Turnover
(MAAT) for best three years out of last
five financial years shall not be less
than the 50% of estimated amount of
Route -3 :- Minimum Average Annual
Turnover (MAAT) of the consortium/
Joint Venture (JV) company added
together for best three years out of last
five financial years shall not be less
than the 50% of the estimated cost.
However Minimum Average Annual
Turnover (MAAT) for best three years
out of last five financial years of the
lead partner shall be at least 25% of
the estimated cost & for each other
partners shall be at least 17% of the
Note:- For the purpose of arriving at
MAAT, Turnover shall be taken as
revenue from operation (excluding
GST) as stated in Financial statement
of the bidder, but excluding other
2.2 Liquid Assets
Route -1 & Route -2 :- Last Financial
Year Liquid Assets should not be less
than 20% of estimated cost of tender.
Route -3 :- Last Financial year liquid
asset of the consortium/ Joint Venture
(JV) company added together should
not be less than 20% of estimated cost
of tender. However Last Financial Year
Liquid assets of the lead partner shall
Details as per qualifying requirement to be at least 10% of estimated Cost of
be submitted along-with offer, in a tender and for each other partners shall
separate cover. be at least 7% of estimated cost of
CA certificate to be attached for MAT.
Note: For the purpose of arriving at
Supply/Order executed details for
Liquid Assets Current Assets Less
offered items with name of purchaser, Inventories shall be considered.
date and location to be mentioned.
Performance certificate for satisfactory 2.3 Net-Worth
operation/working for period as per Bidder’s Networth for last Financial Year
qualifying requirement attached with should be positive including all JV
specification. (This is must for getting Partners
the offer qualified) Note: Net Worth means Paid-up Share
Capital, Share Application Money
Seal & Signature of Bidder
pending allotment and Reserves &
Surplus less Accumulated Losses and
Deferred revenue expenditure/
Miscellaneous Expenses to the extent
not Written Off.
Reserves and Surplus to be
considered for the purpose of net
worth shall be all reserves created
out of the profits and securities
premium account but shall not
include reserves created out of
revaluation of assets, write back of
depreciation and amalgamation.
Share Application Money pending
allotment will be considered only if it
is in respect of shares to be allotted.
Bidder to submit the following
documents in support of meeting
financial qualifying criteria:
1. CA Certificate with valid UDIN
Number failing which certificate shall
not be considered for the purpose of
evaluation and Audited Balance
Sheet and Profit & Loss account
along with the schedules referred
therein and the Auditor’s Report for
the preceding five financial years, in
line with one of the following
2. In case last financial year’s closing
date was within 6 months prior to bid
due date and audited Balance Sheet
and Profit & Loss account of last
financial year are not available,
bidder has the option to submit the
financial details of five previous years
immediately prior to the last financial
year. For example, in case bid due
date is up to 30th September and
financial details of immediate
preceding financial years (year
ending 31st March of same year) are
not available, the financial details of
the five previous years immediately
prior to the last financial year may be
3. Otherwise it is compulsory to submit
the financial details of immediate
preceding five financial years.
4. In case bidder is a holding company,
the Financial Position criteria referred
to in Financial Qualification criteria
shall be that of holding company only
(i.e. excluding its subsidiary / group
companies). In case bidder is a
Seal & Signature of Bidder
subsidiary of a holding company, the
Financial Position criteria referred
to above shall be that of subsidiary
company only (i.e. excluding its
holding company).
5. In case the date of constitution /
incorporation of bidder is less than
five years old the MAAT in respect of
the completed financial year after the
date of constitution shall be taken
into account. Provided further that
the date of constitution /
incorporation of the bidder shall not
be less than one year old and
audited financial statements of at
least one completed financial year is
Details as per qualifying requirement to be
uploaded online,
CA certificate to be attached for MAAT,
LA and Net-worth. (This is must)
Supply/Order executed details for offered
items with name of purchaser, date and
location to be mentioned.
Performance certificate for satisfactory
operation/working for period as per
qualifying requirement attached with
specification. (This is must for getting the
offer qualified).
Under taking in respect of reference to
NCLT under Insolvency & Bankruptcy
Code. The undertaking is to be furnish by
the bidder in its bid as per the format
attached herewith as Annexure–IV and
shall be deemed to be part of the bidding
scheduled referred as Annexure–4 to be
submitted by the bidder with QR bid.
5. Part –I 6.0 Additional Documents: 6.0 Additional Documents:
Special Apart from various documents to be Apart from various documents to be
Conditions of furnished along with the Bid as furnished along with the Bid as required
Contract/ required in the GCC and ECC, the in the GCC and ECC, the following
Clause 6.0 following documents/details are to be documents/details are to be furnished by
and its sub- furnished by the Bidder: the Bidder:
clauses 1. GST Registration No. date/ 1. GST Registration No. date/
issuing authority. issuing authority.
2. Regn. No. under Shops & Estt. 2. Regn. No. under Shops & Estt.
Act/ issuing authority Act/ issuing authority
3. Details of Partners/Directors of 3. Details of Partners/Directors of
the Firm/Company. the Firm/Company.
4. Experience Record and details 4. Experience Record and details
of orders pending / executed for of orders pending / executed for
various utilities various utilities
5. Last five years Audited 5. Last five years Audited
Accounts Accounts
6. Detail of Manufacturing 6. Detail of Manufacturing
Seal & Signature of Bidder
/Fabrication facilities if /Fabrication facilities if
applicable applicable
7. Factory Registration/license 7. Factory Registration/license
details if applicable details if applicable
8. Solvency certificate from
Bank (up to 20 % of Bid value)
6. Part –I 41.0 PENALTY FOR DELAY: 41.0 LIQUIDATED DAMAGES (LD)
(SCC)/ FOR DELAY:
Conditions of 41.1 The tenderer should note that 41.1 The tenderer should note that the
Contract/ the completion time allowed for completion time allowed for carrying out
Clause 41.0 carrying out the work should be the work should be strictly observed.
and its sub- strictly observed. Any delay that may
Any delay that may take place in
clauses take place in supply, erection and
civil beyond Contractual period achieving Completion of the works
stated shall be subject to the penalty beyond Contractual Time of Completion
at the rate of ½ % per week or part in the Contract shall be subject to
there of plus GST as applicable on Liquidated Damages (LD), and not by
delayed portion, with a ceiling of 10 way of penalty, at the rate of ½ % of the
% of the total contract value plus Contract Price plus GST as applicable,
GST as applicable. For calculating
per week or part thereof of the delay
the delayed portion date of actual
receipt of material at store shall be subject to a ceiling of 10% (ten percent)
considered. of the Contract Price plus GST as
41.2 The penalty plus GST as 41.2 The penalty plus GST as applicable
applicable will be deducted from bills will be deducted from bills payable
payable either against this contract either against this contract or from any
or from any Bank Guarantee or any Bank Guarantee or any other amount
other amount payable under any payable under any other contract with
other contract with the GETCO. the GETCO.
41.3 In event of failure of the 41.3 In cases where the Completion of
Contractor to pay the amount of
Penalty as demanded, the Owner the works/ along with supplies extend
shall be entitled to deduct the beyond the contractual completion
amount of Penalty for delay from period, without prejudice to any other
the amounts payable to the right that it may have under the Contract
Contractors under any bills raised or in law, the Owner shall be entitled to
under this contract or any other deduct the amount of LD from the
amount payable under any other amounts payable to the Contractors
contract with the GUVNL and its under any bills raised under this Contract
Subsidiary companies i.e. GETCO, or any other amount payable under any
GUVNL, GSECL, MGVCL, DGVCL, other contract with the GUVNL and its
PGVCL, UGCVL. It is permissible for
Subsidiary companies i.e. GETCO,
the Owner to adjust the amount of
GUVNL, GSECL, MGVCL, DGVCL,
Penalty of delay against any Bank
Guarantee furnished by the PGVCL, UGCVL. It is permissible for the
Contractor under this contract or any Owner to adjust the amount of LD
other contract with GUVNL and/or its against any Bank Guarantee furnished
subsidiary companies. by the Contractor under this contract or
any other contract with GUVNL and/or
its subsidiary companies.
41.3 Notwithstanding the provision of
Seal & Signature of Bidder
Clause 10.2, if so requested by the
Contractor, amount from the RA bills,
pending settlement of Liquidated
Damages (LD), shall not be withheld/
retained by the Owner, if adequate
retention payment [over and above
security deposit/ Contract Performance
Guarantee (CPG)] remains to be
released as per Contract. In case, it is
not so, it shall be examined by the
Owner whether BGs/other securities
(excluding CPG/Security Deposit)
furnished by the Contractor are available
with GETCO, which have partly or fully
served their purpose, and can therefore
be utilized by GETCO to recover LD, if
finally levied. If available, it will be further
checked whether the contractor is willing
to furnish a suitable undertaking
authorizing GETCO to retain those
BGs/security (for such value which along
with retention payments remaining with
GETCO is considered to be sufficient to
take care of maximum leviable LD) to be
kept valid till 6 months beyond the
anticipated completion of the works/ supplies
under the Contract. If the Contractor
requests and gives the undertaking as
above and validity of BG is suitably
extended wherever required, amount from
RA bills, pending settlement of LD, shall not
be withheld/ retained on account of LD.
Seal & Signature of Bidder
BANK GUARANTEE FORM FOR ADVANCE PAYMENT
(For the purpose of verification/confirmation of this Bank Guarantee by the GETCO, the Bank
shall indicate 2 official email ids of the authorized signatories from Issuing Branch and also of
the designated higher office (Corporate Office, Zonal Office etc) in the covering letter of the
Bank forwarding the Bank Guarantee.)
Bank Guarantee No. …………………… Date...................
…………..[Name of Contract]…………………….
To: [Name and address of the Employer/ Owner]
Dear Ladies and/or Gentlemen,
We refer to the Contract ("the Contract") vide Letter of Award issued on ............ (insert date of the
letter of award)….by you (the Employer/ Owner) to M/s ................. (Name of Contractor) ..................,
signed on ..............(insert date of the Contract)…..... between you and M/s ................. (Name of
Contractor) ..................,
having its Principal place of business at ………....(Address of Contractor) ............................... and
Registered Office at ………....(Registered address of Contractor)
…….................….. (Indicate brief scope of work) ............................... for the complete execution of the
…… (insert name of Package along with name of the Project)……..
Whereas, in accordance with the terms of the said Contract, the Employer has agreed to pay or cause
to be paid to the Contractor an interest bearing Advance Payment against furnishing of an irrevocable
bank guarantee for an amount of ………………………..(Amount in figures and words) ……………which
is equal to [{110% (one hundred ten percent) of the amount of Advance} Plus {amount of GST
reimbursable on Advance as per the Proforma invoice, if applicable}].
By this letter we, the undersigned, ………(insert name & address of the issuing bank) ………, a Bank
(which expression shall include its successors, administrators, executors and assigns) organized
under the laws of .................................... and having its Registered/Head Office at …..…….(insert
address of registered office of the bank)……..... do hereby irrevocably guarantee repayment of
………….(Amount of the bank guarantee in figures and words)…………… upon the first demand of the
Employer without cavil or argument in the event that the Contractor fails to commence or fulfill its
obligations under the terms of the said Contract for reasons whatsoever.
Provided always that the Bank's obligation shall be limited to the amount of this Bank guarantee or an
amount equal to the outstanding balance of the Advance Payment and the accrued interest on the
Advance Payment, taking into account such amounts, which have been repaid by the Contractor from
time to time in accordance with the terms of payment of the said Contract, as certified by you.
This Guarantee shall remain in full force from the date upon which the said Advance Payment is
received by the Contractor up to ninety (90) days beyond the date on which the entire Advance
Payment along with the accrued interest if any due thereon has been fully adjusted in terms of the
Contract i.e., up to ninety (90) days beyond the date of Completion of the Facilities under the Contract.
This Guarantee may be extended from time to time, as may be desired by M/s. ………………………..
on whose behalf this Guarantee has been issued.
Seal & Signature of Bidder
Any claims to be made under this Guarantee must be received by the Bank during its period of validity,
i.e. upto ninety (90) days beyond the date of Completion of the Facilities by the Employer i.e. upto and
inclusive of ……………. (dd/mm/yy).
Notwithstanding anything contained herein:
1. Our liability under this Bank Guarantee shall not exceed _________ (value in
2. This Bank Guarantee shall be valid upto ________(validity date)__________.
3. We are liable to pay the guaranteed amount or any part thereof under this Bank Guarantee
only & only if we receive a written claim or demand on or before ________ (validity date)
For and on behalf of the Bank
[Signature of the authorised signatory(ies)]
Designation_______________________
Contact Number(s): Tel.______________Mobile______________
Common Seal of the Bank______________________
Contact Number(s): Tel.______________Mobile______________
1. For the purpose of executing the Bank Guarantee, the non-judicial stamp papers of appropriate
value shall be purchased in the name of Bank who issues the ‘Bank Guarantee’.
2. The Bank Guarantee shall be signed on all the pages by the Bank Authorities indicating their
POA nos. and should invariably be witnessed.
3. The Bank Guarantee should be in accordance with the proforma as provided. However, in
case the issuing bank insists for additional paragraph regarding applicability of ICC
publication No: 758, the following may be added at the end of the proforma of the Bank
Guarantee [i.e., end paragraph of the Bank Guarantee preceding the signature(s) of the
issuing authority(ies) of the Bank Guarantee]:
“This Guarantee is subject to Uniform Rules for Demand Guarantee, ICC publication No.
758 except that article 15(a) is hereby excluded.”
Seal & Signature of Bidder
Specification No: ACE(P&C)/Contracts/SS/E-421/66kV/UG/S&L,E
Sub: Supply, Laying, Erection, Testing and Commissioning of 66kV 1CX630 sqmm XLPE Cable with
Poly AL-Poly / Aluminum Corrugated construction on EPC basis for various lines in Anjar circle in
Option for Initial Advance (either Interest Bearing Initial Advance of No Initial Advance or No Initial
Additional Chief Engineer (Procurement & Contracts)
Gujarat Energy Transmission Co. Ltd.,
Corporate office,
I. We have read the provision in the Bidding Documents regarding furnishing the option for
advance payment. Accordingly, as per clause GCC 47.1.1 (For Supply) and GCC 47.2.1 (b)
(For Erection) provided in Amendment-I of the Bidding Documents, we hereby confirm to opt
Interest Bearing Initial Advance:
Supply Portion: (Ref GCC 47.1.1) *
Erection Portion: (Ref GCC 47.2.1 (b)) *
* ‘Yes’ or ‘No’ to be filled up by the Bidder. ‘Yes” shall mean that Bidder has opted for the
Interest Bearing Advance and ‘No’ shall mean that Bidder has not opted for the Interest Bearing
Advance. If nothing is mentioned, it shall mean that Bidder has not opted for the Interest
Bearing Advance.
(Name of Authorized Signatory of Bidder)
Seal & Signature of Bidder
Specification No ACE(P&C)/Contracts/SS/E-421/66kV/UG/S&L,E
Sub: Supply, Laying, Erection, Testing and Commissioning of 66kV 1CX630 sqmm XLPE
Cable with Poly AL-Poly / Aluminum Corrugated construction on EPC basis for various
lines in Anjar circle in Rajkot Zone
In connection with above subject, I / we confirm that our firm is not declared in NCLT
under Insolvency & Bankruptcy Code. Further, I / we also agree that, if any found NCLT
under Insolvency & Bankruptcy Code, the offer shall be out rightly rejected without
assigning any reason thereof.
Signature of Authorized
Representative of Company/Agency
Name of bidder Company
Seal & Signature of Bidder
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
4. EMD BG Format.pdf
02TOWER MATERIAL66KV LINEPANTHER.pdf
66 KV LA R6 June 22.pdf
66KV CABLE TRENCH APPROVED DRAWING 100419.pdf
66KV630SQ MM 1C POLY AL POLYR4.pdf
66KV630SQ MMALUMINUM CORRUGATED 012021.pdf
166kvMOC 29102025 R4.pdf
266KVMOC61 DT291025R3.pdf
366KVMOC DT291025 R2.pdf
466KV MOC DT291025 R2.pdf
GIEARTHING STRIPS.PDF
MOC66kVcable 130122 CE(Project) letter.pdf
Notes for FOAC laying.pdf
Standard MQP GI Tower material for issuence.PDF
TSLAYINGCABLE66KV R2.pdf
48F FODP Ref Drg1.pdf
48F FODP Ref Drg2pdf.pdf
End to End Test Final.pdf
Joint Box FOAC OPGW Ref Drg2.pdf
Joint Box FOACFOAC Ref Drg.pdf
Joint Box FOACOPGW Ref Drg1.PDF
OFC Underground cable Manhole Chamber.pdf
1. Form of LD undertaking 1A.pdf
2. Form of LD undertaking 1B.pdf
4. EMD BG Format.pdf
5. SD cum PBG Format.pdf
Public Procurement Circular of GOI.pdf
Amendment -I Part-I Tender Specifications E-421.pdf
Tender Notice-E421 66KV Cable EPC Anjar.pdf
Tender Specification Part-I E-421 66KV Cable EPC Anjar.pdf
Amendment -I Part-I Tender Specifications E-446.pdf
Tender Notice-E446 66KV Cable EPC Jambuva.pdf
Tender Specification Part-I E-446 66KV Cable EPC Jambuva.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .