Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹1.2 CrAccepted-AOC | ₹1.2 Cr | L-1 | Accepted-AOC Work awarded |
| 2 | L-2₹1.2 Cr+₹1.5 L (1.22%)Rejected-Finance | ₹1.2 Cr+₹1.5 L (1.22%) | L-2 | Rejected-Finance Due to higher rate |
| 3 | L-3₹1.2 Cr+₹3.0 L (2.51%)Rejected-Finance FLAT NO A 1108 TOWER P 2 ASHIYANA PALM COURT RAJNAGAR EXTENSION GHAZIABAD UP | GHAZIABAD | UTTAR PRADESH | 201001 | ₹1.2 Cr+₹3.0 L (2.51%) | L-3 | Rejected-Finance Due to higher rate |
Tender Value
Refer Docs
EMD Value
₹2.4 L
Closing Date
21 Jul 2022, 12:00 pmClosed
Superintending Engineer
Electricity Distribution Circle, Rudrapur
Increasing capacity of 33/11 KV S/s Bara from 1x8 MVA to 2x8 MVA and renovation and Reconstruction work in existing yard under Electricity Distribution Division, Sitarganj
2022_UPCL3_46494_1
EDC(USN)38/2022-23
Open Tender
Electrical Works
Item Rate
90 days
Bara, Sitarganj
Pl Refer tender Documents
3 documents required · 3 mandatory
₹11,800
SE EDC Rudrapur
₹2.4 L
21 Jul 2023
7 Jul 2022
22 Jul 2022
7 Jul 2022
21 Jul 2022
7 Jul 2022
Amount
Annexure-A (LABOUR CHARGES)
Cartage of 33/11KV 8MVA Transformer fram centeliezed store distance up to 50 km to working site including loading/unloading with help of labour, crain & Privet vechicals.
Cartage of 33/11KV Transformer Accessories fram centeliezed store distance up to 50 km to working site including loading/unloading with help of labour , crain & Privet vechicals.(Reditor , Fance & Transformer oil drum
Cartage of 11kv vcb With Accessories fram centeliezed store distance up to 25 to 50km to working site including loading/unloading with help of labour , crain & Privet vechicals.(1Nos- I/C,2Nos-O/G & 1Nos-Bus Coppouler)
Cartage of 33kv vcb,CTs & PTs With Issolator, Accesoories fram centeliezed store distance up to 50 km to working site including loading/unloading with help of labour, crain & Privet Vechicals,
Cartage of Power cable & Others small material fram centeliezed store distance up to 50 km to working site including loading/unloading with help of labour, crain & Privet Vechicals,
Cartage of MS Steel ,RS Joint,chanel ,Angle & Others small material fram centeliezed store distance up to 50 km to working site including loading/unloading with help of labour, crain & Privet Vechicals,
Cartage of SP-55 Pole & Others small material fram centeliezed store distance up to 50 km to working site including loading/unloading with help of labour, crain & Privet Vechicals,
Charges of Dismentling of old Fence & Radiator 5 MVA transformer at 33/11KV S.S Bara with help of Crain & Main Power as per direction of Engineer in charge.
Charges of Draging of 5 MVA Transformer Yard Side To Out side to yard with accessories with help of Crain & Labour as per direction of Engineer in charge.
Cartage of 33/11KV 5MVA Transformer fram 33/11KV S.S Bara To Centralized Store distance up to 50 km to working site including loading/unloading with help of lebour , crain & Privet vechicals.
Cartage of 33/11KV 5MVA Transformer accessories Fence, Rediator & Other material fram 33/11KV S.S Bara To Centralized Store distance up to 50 km to working site including loading/unloading with help of lebour , crain & Privet vechicals.
Charges of Earth Fillling with soil of out side of yard & SGR building area of out (70x40x0.600) as per direction of Engineer in charge.
Charges of Cleaning ,Drassing & leveling of Switch yard (27 x 31 x ) reduction of Exsisting Transformer plint and equipment (3x3+9)=15 sqm as per direction of Engineer in charge.
Charges of Compacting & labling of earth feeling area with JCB & Main Power (27 x 31) as per direction of Engineer in charge.
Charges of PCC work of 100MM with 25mm ,Gravel, Ciment & sands mortar 1:3:6 (27 x 31 x0.1) reduction of Trannsformer plint with equipment as per direction of Engineer in charge.
Charges of Making of rewatring arragment with slopping of Yard area with rewatering through water pump as per direction of Engineer in charge.
Charges of Excavation in Transformer Plinth in Ordinary soil (loam clay or sand) includding lift up to 1.2 Mtr.Plinth Size of 4x4x1 Mtr as per direction of Engineer in charge.
Charges of PCC work of 100MM with 25mm ,Gravel, Ciment & sands mortar 1:3:6 (4x4x0.10)mtr as per direction of Engineer in charge.
Charges of RCC work with rain force 100mm 1:2:3 Jal in transformer Plinth Top & Bottom side (4x4x0.2x2) as per direction of Engineer in charge.
Charges of Ist class Brick work in 1:4 ciment mortar with ciment,coares sand in super structore in one brick thick wall Tranformer Plinth(.450 x.4.0x 1.5x4) as per direction of Engineer in charge.
Charges of RCC work with rain force 1:2:3 Jal in transformer Plinth up to Top Size (3.0x3.0x1) as per direction of Engineer in charge.
Charges of making of MS jal with rainforce 8 mm with labour and T&P as per direction of Engineer in charge.
Charges of Plastaring of trasformer plint (4x.5)mtr x 4 as per direction of Engineer in charge.
Charges of Instalation Grouting of RS joint 150x150mm aas per direction of Engineer in charge.
Charges of Excavation in CT,PT,Isolator,VCB,LA in Ordinary soil (loam clay or sand) includding lift up to 1.2 Mtr.(.4x.4x.8x4)+(.8x.6x.8x4)+(.8x.8x1.0x2) as per direction of Engineer in charge.
Charges of PCC of 100MM along with Gravels sand & Ciment 1:4:8 L.A,CT,Iso,VCB Above (.4x4X.1X4)+ (.8x.6x.1x4)+(.8x.8x.1x2) as per direction of Engineer in charge.
Charges of C.C of structure Groutting of sam equipment of above (.4x.4x.6x4)+(.8x.6x.6x4)+(.8x.8x.9x2) as per direction of Engineer in charge.
Charges of Plastaring of top & Both Side of Plinth same as above (.4x.3x4x4+.8x.3x4x2+.8x.3x4x2) as per direction of Engineer in charge.
Charges of Excavation in power Cable trunches in Ordinary soil (loam clay or sand) includding lift up to 1.2 Mtr.Plinth Size of 1.2x1.0x53 Mtr as per direction of Engineer in charge.
Charges of PCC of 100MM along with Gravels sand & Ciment 1:4:8 of Cable Trunches ( 1.2 x 53 x.1) as per direction of Engineer in charge.
Charges of Ist class Brick work in 1:4 ciment mortar with ciment,coares sand in super structore in one brick thick wall Cable trunches (.230x1x53x2 ) as per direction of Engineer in charge.
Charges of C.C of 50mm cable trenches as top side along with gravels Ciment & Sands (.230x53x.05x2 as per direction of Engineer in charge.
Charges of Plastaring of cable trunches along with 1:3 with ciment & Sand (1.0x53x2)+(.23x53x2) as per direction of Engineer in charge.
Charges of Making & Instalation of power cable Trunch Top Cover A 50x6mm Both side lenth of 53mmtx 2nos as per direction of Engineer in charge.
Charges of Errection & Making of Power cable Trunch coverd of size -580 x.5 x600 mm and long 53 mtr includding of Cimennt sand .Gravel with rainforce ((90Pcs) as per direction of Engineer in charge.
Charges of Macking & Instalation of Control cable Trunch Top Cover A 50x6mm Both side lenth of 30 mmtx 2nos as per direction of Engineer in charge.
Charges of Excavation in Control Cable trunches in Ordinary soil (loam clay or sand) includding lift up to 1.2 Mtr.Plinth Size of .8x.6x 30 Mtr as per direction of Engineer in charge.
Charges of PCC work of 100MM along with Gravels sand & Ciment 1:4:8 of Cable Trunches ( .8 x 30 x.1) as per direction of Engineer in charge.
Charges of Ist class Brick work in 1:4 ciment mortar with ciment,coares sand in super structore in one brick thick wall Cable trunches (.230x0.5x 30x2 ) as per direction of Engineer in charge.
Charges of C.C work of 50mm cable trenches as top side along with gravels Ciment & Sands (.230x 30x.05x2) as per direction of Engineer in charge.
Charges of Plastaring of cable trunches along with 1:3 with ciment & Sand (.5x30x2)+(.23x30x2) as per direction of Engineer in charge.
Charges of Macking & Errection of Power trunch Cover Frame of ms 40x40x6 Size of 380x600mm as per direction of Engineer in charge.
Charges of Errection & Making of cable Trunch coverd of size -380 x50 x600 mm and long mtr includding of Cimennt sand .Gravel with rainforce (50Pcs) as per direction of Engineer in charge.
Charges of Spreading of 25MM Size of gravel in out door switch yard in depth 50mm (27 X 31) reduction of transformer plint with equipment (3x3+4x4+9)34 sqm as per direction of Engineer in charge.
Charges of Repairing , Plastering & Cleaning of damage Existing Control Cable Trenches at sub station area as per direction of Engineer in charge.
Charges of Repairing of Damage Existing Control Cable Trench Cover as per direction of Engineer in charge.
Charges of Making of erection of structure of isolatior ,C-100x500 &A-75x75x6, A-50x6MM as per direction of Engineer in charge.
Charges of Making of erection of structure of ,CT & LA-C-150x75,A-75x6MM as per direction of Engineer in charge.
Charges of Making of erection of structure of ,VCB as per direction of Engineer in charge.
Charges of Erection Installation of MS Earthing Rod 25 x3000 mm as per direction of Engineer in charge.
Charges of Erection Installation of G.I Earthing Electrode 50 x3000 mm with compound as per direction of Engineer in charge.
Charges of making ,Erection Cuttng , welding of earth mat size ms Strip 40x6 MM as per direction of Engineer in charge.
Charges of installation Errection of GI Earthing stripe 40x6 mm Equipment of 33KV) as per direction of Engineer in charge.
Charges of Erectioction Installation & Commissoning of of 33Kv Isolator with all accept Required accessorise allso includding power & control cable ,cutting ,drilling and welding of Earthing strip.(8 MVA Transformer) as per direction of Engineer in charge.
Charges of Errectioction Installation & Commissoning of of 33Kv CT with all accept Required accessorise allso includding power & control cable ,cutting ,drilling and welding of Earthing strip.(8 MVA Transformer) as per direction of Engineer in charge.
Charges of Erection Installation & Commissoning of of 33Kv L.A with all accept Required accessorise also includding power & control cable ,cutting ,drilling and welding of Earthing strip.(8 MVA Transformer) as per direction of Engineer in charge.
Charges of Erection Installation & Commissoning of of 33Kv Vacuum Circuit Breaker with all accept Required accessorise.along with help of crain & Main Power as per direction of Engineer in charge.
Charges of Erectioction Installation & Commissoning of of 33Kv C & R Panel with all accept Required accessorise.along with help of Main Power as per direction of Engineer in charge.
Charges of Control cable laying & termination. Laying, tracing, ferruling, lugging and termination both end of vacuum circuit breaker, 33 KV control panel, 33 KV CT terminal box, dc supply & ac supply cable size of 10cx2.5 sqmm. and 2cx1.5 mm. as per direction of Engineer in charge.
Charges of Testing of 33 KV C.T. laying, tracing, ferruling, lugging and termination both end of C.T wiring, testing and injection shoot of C.T. as per direction of Engineer in charge.
Charges of Making & Errection of 11KV VCB & C&R Panel suports of chanel 100x50mm x 10 nos as per direction of Engineer in charge.
Charges of Erectioction Installation & Commissoning of of 11Kv Vacuum Circuit Breaker with all accept Required accessorise allso includding power & control cable ,cutting ,drilling and welding of Earthing stripas per direction of Engineer in charge.
Charges of Testing of 11 KV vcb Injection shut of CT Relay Testing & setting as per load as per direction of Engineer in charge.
Charges of Errectioction Installation & Commissoning of of 33Kv Transformer with all accept Required accessorise allso includding power & control cable ,cutting ,drilling and welding of Earthing strip.(8 MVA Transformer) along with labour & Crain as per direction of Engineer in charge.
Charges of Shifting / Dragging of 8MVA T/F From out side to in side yard T/F plinth help of Crane & Labor as per direction of Engineer in charge.
Charges of Shifting & Assembling of conservator,radiator with all accessories (8 MVA)with help of crane & Labour as per direction of Engineer in charge.
Charges of Heating of oil T/F oil filling in T/F up to Conservator and with Reddiator with the centrifusing machine. 6500 Ltr as per direction of Engineer in charge.
Charges of Oil Filling of T/F 8MVA upto consarvator & Rediator with help of filling pump as per direction of Engineer in charge.
Charges of Connection of EHT/HT power cable with accessories of 8 MVA T/F as per direction of Engineer in charge.
Charges of Connection of bucoz Relay ,WTI.OTI & Preasure Releve valve alarm of 8MVA T/F as per direction of Engineer in charge.
Charges of Testing Before Charging of 8 MVA T/F Such as Insulation Rasistance.Magnetic Balance test with Low Voltage Meagnetising current & Polerity ect as per direction of Engineer in charge.
Charges of Laying & Installation of Dog Conductor (bus to Isolator,CT,VCB ,LA & Transformer (Nuw Bay) as per direction of Engineer in charge.
Charges of Laying Of Power Cable 3 X 400 Sqmm along with Digging of Cable trench Defth 750mm incl sand & protection of Top Cover half Cut of Cimented pipe.( From new VCB to O/G Pole) as per direction of Engineer in charge.
Charges of Laying Of Power Cable 3 X 400 Sqmm at on cable trunches as per direction of Engineer in charge.
Charges of Preparation of HT Cable Joint Kitts as per direction of Engineer in charge.
Charges of Replacement of WTI & OTI Temperature Meter with Sencer along with control wiring (OLD Transformer) as per direction of Engineer in charge.
Charges of Oil Filling of T/F 8MVA upto consarvator & Rediator with help of filling pump.(OLD Transformer) as per direction of Engineer in charge.
Charges of Painting of transformer of first quality of paits,cleaning of transformer thrugh Embry paper ,washing & cleaning of plint 8 MVA transformer.(OLD Transformer) as per direction of Engineer in charge.
Charges of Installation Testing Commissoing of Battery Charger as per direction of Engineer in charge.
Charges of Installation Errection & Testing of Battery Set 2V x 12Volt as per direction of Engineer in charge.
Charges of Errection Installation of Double pole with Chanel ,Inuslator ,Clamp sp-55 along with Grouting & all materal with T&P as per direction of Engineer in charge.
Charges of making of Muffing of pole sise 0.45x 0.60 redius with CC ratio1:3:6 as per direction of Engineer in charge.
Charges of Errection Installation of stay set for Double Pole along with Grauting as per direction of Engineer in charge.
Charges of Errection Instalation of Street Light rectingle Pole with Base Plate & Foundation bolts along with grevels ciment & sands size 400x400 x 750 MM as per direction of Engineer in charge.
Charges of Errection Installation of Stree Light Rectingle pole along with all accessories as per direction of Engineer in charge.
Charges of Installation & Testing of E.L.D light with all Clamps & Brackets accept as required as per direction of Engineer in charge.
Charges of Laying & Termination of lighting cable 4c x2.5sqmm also incl.digging & Back Filling of soft soil depth 300mm as per direction of Engineer in charge.
Charges of Installation Testing of Distribution Panel along with coplete fitting with cable as per direction of Engineer in charge.
Charges of installation ,Testing & Commissining of MCB spn box with MCB as per direction of Engineer in charge.
Charges of Macking & Errection & Grouting with Cement Sand & Gravels of wirmess Bracket Trisul type 400mm x 400+ 600 as per direction of Engineer in charge.
Charges of Instalation of wire mes compound wall fencing at boundry wal as per direction of Engineer in charge.
Charges of Instalation & Laying of barved strate wire (2 Run) as per direction of Engineer in charge.
Charges of Instalation of Exaust Fan in Control Room along with Wall cutting Fram Grouting with ciment & Mortar with labor & T&P as per direction of Engineer in charge.
Charges of extension of control room same as size of lxwxh (4x9.6x4) mtr along with plint beam Brick wal PCC ,,RCC Colom & Beam CC of roof as per direction of Engineer in charge.
Charges of extension of control room attached Baramada same as size of lxwxh (3.3x5.25x4) mtr along with plint beam Brick wal PCC ,,RCC Colom & Beam CC of roof as per direction of Engineer in charge.
Charges of Plastring of Extention area of control bulding attched baramada Inside /Out side 1:3:6 along with man power & T&P (4X4+9.6x 4+9.6x4x2) + (3.3x4+ 5.25x2+ 5.25x3.3+ 5.25 x.5) as per direction of Engineer in charge.
Charges of C.CMaking & Finishing of New Control Bulding Floor along with Good Quality of Floor Size of Area (4 Mtr x 9.6) +(3.3x5.25) Mtr) Ciment & Sands Provide By Contractor as per direction of Engineer in charge.
Charges of Finishing &Cleaning of New Contructed in side Bulding area with white ciment/putty of good Quality (4X9.6+4x4+5.25x4x + 4 x 9.6) TOP Receway as per direction of Engineer in charge.
Charges of Painting of Control Bulding of In side & Out side along with good quality of Paint ,Reaparing & Cleaning of control bulding & Je Room Material provide by Contractor as per direction of Engineer in charge.
Charges of Making of toiet & Both room of Near SGR Building size of (2.5x.6x3) as per direction of Engineer in charge.
Charges of Plastering of above area ( 2.0x3x4+.6x3x4 +2.5x.6) as per direction of Engineer in charge.
Charges of Fitting of Pan & Urinal system of good quality with maition & Labour as per direction of Engineer in charge.
Charges of Fiting of water line & Hume pipe with Fitting as per direction of Engineer in charge.
Charges of Flooring of Toilet & Bathroom area with good quality of Tiels (2.5x.6 x1.2) as per direction of Engineer in charge.
Charges of Painting of toilet & Bathroom area of good quality of wal putty & Paints as per direction of Engineer in charge.
Charges of Macking & Errection of pale fencing frame 3x2+1.6x2 x10 as per direction of Engineer in charge.
Charges of Replacment of old damage Pale fencing along with suports,Cutting ,welding withT&P as per direction of Engineer in charge.
Charges of Cleaning with Embry Paper of Switch yard (30 x 35 x 1.5 ) as per direction of Engineer in charge.
Charges of Painting of Yard Fensing of first quality of Green paits,cleaning of Fens suport & fens thrugh Embry paper ,washing & cleaning of Fens. Size (30+30 +35+35) Hight-1.5mtr as per direction of Engineer in charge.
Charges of Bus Bar Gantri clining of embry paper & painting of two coad Red oxide & allmunium paints as per direction of Engineer in charge.
Charges of L.A Structore clining of embry paper & painting of two coad Red oxide & allmunium paints as per direction of Engineer in charge.
Charges of Issolatore Structore clining of embry paper & painting of two coad Red oxide & allmunium paints as per direction of Engineer in charge.
Charges of C.T Structore clining of embry paper & painting of two coad Red oxide & allmunium paints as per direction of Engineer in charge.
Charges of I/C Structore clining of embry paper & painting of two coad Red oxide & allmunium paints as per direction of Engineer in charge.
Charges of Reaparing ,& Clining of damage Boundry wall at sub station area as per direction of Engineer in charge.
Charges of Plastaring of damage Boundry wall at sub station area as per direction of Engineer in charge.
Charges of Painting of Boundry wall (Inside & Out side) with Two Code of Good Quality of Paint as per side Encharge Lenth.250 mtr x hight 1,5 Mtr x2 No as per direction of Engineer in charge.
Charges of Painting of Double pole with good quality with red oxide & two code of almunium paint pole size sp-55 as per direction of Engineer in charge.
Charges if Instalation of safety material Fire exstiguser, Fire Bucket, Rubbermat Ect as per direction of Engineer in charge.
Charges of Lighting DB TP&N Double door 4 way with mcb as per direction of Engineer in charge.
Charges of Erection of Safety material Rubber mat, Fire esqugetssre & Other Fire Bucket as per direction of Engineer in charge.
Charges of Complete wiring with PVC Pipe,Band,Juction with Cu Wire New contrected VCB building area 4 x16Mtr as per direction of Engineer in charge.
Annexure-B (SUPPLY ITEMS)
Supply of PG Clamp for Panther conductor
Supply of PG Clamp for Panther to Dog conductor
Supply of Isolator connector clamps 33 KV for dog connector
Supply of CT connector clamp for 33 KV CT for panther conductor
Supply of P.T Connector
Supply of VCB Connector
Supply of MS Clamp 50x6mm
Supply of Isolator Jaw
Supply of Isolator blade
Supply of MS Flat 40x6 mm (Earth mat )
Supply of Gi Earth Electrode Mintenance Free Electrode 80mmx3000mm with chemical bag
Supply of GI Earthing strip 40x6mm
Supply of Rectangle lighting pole 6 Mter Long Botom Plate
Supply of LED Light 45W
Supply of L.T. Distribution Panel made on CRC sheet with gray coller poweder coating ,al busbar (Incommer-125A,4pole MCCB & Outgoing 63A mccb with metering & Indication
Supply of Cu armerd Control cable 10C x2.5Sqmm
Supply of Cu armerd Control cable 4C x2.5Sqmm
Supply of supply of cop flexible wire 2.5sqmm
Supply of cop flexible wire 1.5sqmm
Supply of Battery (2v x 12nos) 100 A H with all accept metarial (Exide / Amoran)
Supply of battery charger input 220v & Out put 24V havy duty coper bound Transfomer & Deemer Type auto/manual charger
Supply of winding teparature & sensor with wire wit meter good qallity
Supply of Oil teparature meter & sensor with wire good qallity
Supply of Control Cable 3C x 1.5 sqmm
Supply of PVC Pipe 25mm with Band ,T Joint & Elbo
Supply of new iron sheets of pale fencing of size 2.4mmx0.10m and of SWG 18 including nuts and bolt
Supply of Out door Juction Box with Terminal
Supply of GI Pipe dia 40mm for Lighting cable of G.L to J.Box
Supply of lighting braket made of ms Pipe
Supply of Heavy Duty Industrial type Exaust Fan 450MM Make Crompton Havels
Supply of copper flexble cable 1.5 sqmmx 3 c
Supply of MS Chakkar plate 6 mm thik
Supply of wiremess Compound Boundry wall fencing
Supply of wiremess wirebed wire for Boundry wall fencing
Supply of 3 Phase Heavy Duty of 5HP water Pump Make Kirlosker Havells)
Supply of 3 Phase Heavy Duty DOL Starter 5HP Make L&T, Simens
Supply of LEDTube Light Fitting 24W with accessories
Supply of Fire Extinguisher 4 Kg ISI Make
Supply of 11KV Rubber mat thick 3MM high Quality of Insulated ISI
Supply of Sock Treatment chart 33kv/11KV ( Hindi & English)
Supply of 33 KV Hand Gloves
Supply of First ad box including of medicine Make-Jonson
Supply of Fire Bucket 20 Ltr
Supply of MS Angle 35 x35x6mm
M/S PERFECT TECHNICAL SERVICES
M/S AGARWAL CONSTRUCTIONS
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .