Loading…
Loading…
Tender Value
Refer Docs
EMD Value
₹50,000
Closing Date
8 Jun 2026, 3:00 pm3d left
Executive Engineer
head works Division,Aruvikkara
State PlanState Plan20232Source Improvement and Water Conservation Raising the road towards Podiakkala in connection with raising the Water Level of Peppara DamPart II Construction of Approach Road General Civil Work RT1
2026_KWA_852553_2
03/2026
Open Tender
Civil Works - Others
WORKS
Please refer Tender documents.
3 documents required · 3 mandatory
₹3,257
₹50,000
1 Jun 2026
1 Jun 2026
9 Jun 2026
1 Jun 2026
8 Jun 2026
1 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1Construction of Retaining Walls | ||||||
| 1.001 | 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | - | sqm | - | - | BI01010001010000000000000515BI0100001114 |
| 1.002 | 100.7.5:Bailing out water with engine and pump set above 30HP up to 40HP including conveyance to the site, erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc., complete. | - | Kwh | - | - | BI01010001010000000000000515BI0100001115 |
| 1.003 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 1 | cum | - | - | BI01010001010000000000000515BI0100001116 |
| 1.004 | 2.9.1:Excavation work by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m.Ordinary rock | 1 | cum | - | - | BI01010001010000000000000515BI0100001117 |
| 1.005 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete | 1 | sqm | - | - | BI01010001010000000000000515BI0100001118 |
| 1.006 | 5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. | - | sqm | - | - | BI01010001010000000000000515BI0100001119 |
| 1.007 | 4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) | 1 | cum | - | - | BI01010001010000000000000515BI0100001120 |
| 1.008 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 0.6 | kilogram | - | - | BI01010001010000000000000515BI0100001121 |
| 1.009 | 50.2.26.1:Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge. | - | cum | - | - | BI01010001010000000000000515BI0100001122 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
KWAGeneralConditionsforeTenderingV5.pdf
PDF • 0.69 MB
Tendernotice_1.pdf
PDF • 0.79 MB
Tendernotice_2.pdf
PDF • 0.79 MB
Tendernotice_3.pdf
PDF • 0.05 MB
BOQ_1442783.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid