| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹61.8 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹63.8 L+₹2.0 L (3.29%)Rejected-AOC | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | ANISH C P L1 | JITHIN RADHAKRISHNAN L2 |
|---|---|---|---|---|---|
| 1.00Construction of class rooms above existing building, GLPS Panayikulam | |||||
| 1.00 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | 3.12 | cum | 2,110.9 ₹6,586.01 Lowest | 2,209.57 ₹6,893.86 |
| 1.00 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 2.88 | cum | 301.6 ₹868.61 Lowest | 315.8 ₹909.5 |
| 1.00 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete | 5.28 | sqm | 323.8 ₹1,709.66 Lowest | 338.19 ₹1,785.64 |
| 1.00 | 5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers | 219.54 | sqm | 639.8 ₹1,40,461.69 Lowest | 648.44 ₹1,42,358.52 |
| 1.00 | 5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts | 153.15 | sqm | 845.8 ₹1,29,534.27 | 818.03 ₹1,25,281.29 Lowest |
| 1.01 | 5.9.7:Centering and shuttering including strutting, etc. and removal of form for:Stairs, (excluding landings ) except spiral - staircases) | 25.36 | sqm | 691.7 ₹17,542.9 | 678.37 ₹17,204.82 Lowest |
| 1.01 | 5.9.19:Centering and shuttering including strutting, etc. and removal of form for:Weather shade, Chajjas, corbels etc., including edges | 42.6 | sqm | 857.1 ₹36,512.46 | 847.96 ₹36,123.1 Lowest |
| 1.01 | 5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform | 204.09 | sqm | 806.1 ₹1,64,516.95 Lowest | 818.03 ₹1,66,951.74 |
| 1.01 | 5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for:
Edges of slabs and breaks in floors and wallsUnder 20 cm wide | 80.2 | metre | 191.3 ₹15,342.26 Lowest | 197.52 ₹15,841.1 |
Tender Value
₹73.7 L
EMD Value
₹50,000
Closing Date
9 Feb 2026, 2:00 pmClosed
The Executive Engineer
O/o the Executive Engineer PWD,Buildings Division Ernakulam
construction of the First Floor and Truss work roofing in existing building
2026_PWD_832543_1
PWD/BLDG/TR/11786/2024_5_1_1/1
Open Tender
Civil Works - Buildings
Item Rate
365 days
PANAYIKUALM
Please refer Tender documents.
11 documents required · 11 mandatory
₹2,760
Yes
₹50,000
Yes
10 Mar 2026
31 Jan 2026
11 Feb 2026
31 Jan 2026
9 Feb 2026
31 Jan 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of class rooms above existing building, GLPS Panayikulam | |||||
| 1.001 | 15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | 3.12 | cum | - | - |
| 1.002 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 2.88 | cum | - | - |
| 1.003 | 5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete | 5.28 | sqm | - | - |
| 1.004 | 5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers | 219.54 | sqm | - | - |
| 1.005 | 5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts | 153.15 | sqm | - | - |
| 1.006 | 5.9.7:Centering and shuttering including strutting, etc. and removal of form for:Stairs, (excluding landings ) except spiral - staircases) | 25.36 | sqm | - | - |
| 1.007 | 5.9.19:Centering and shuttering including strutting, etc. and removal of form for:Weather shade, Chajjas, corbels etc., including edges | 42.6 | sqm | - | - |
| 1.008 | 5.9.3:Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform | 204.09 | sqm | - | - |
| 1.009 | 5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for:
Edges of slabs and breaks in floors and wallsUnder 20 cm wide | 80.2 | metre | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.05 MB
viewsbd.pdf
Tender Documents • 1.64 MB
BOQ_1399486.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .