Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹68.2 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹71.0 L+₹2.8 L (4.15%)Rejected-Finance | L2 | Rejected-Finance L2 |
Tender Value
₹71.6 L
EMD Value
₹50,000
Closing Date
12 Feb 2024, 2:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Assistant Executiuve Engineer
LID and EW Sub Division Pattanakkad
Annual Plan-Pro no-121/24-PATTANAKKAD BLOCK PANCHAYATH SECOND FLOOR CONSTRUCTION
2024_LSGD_654564_1
2/AEE/LIDEW/2024
Open Tender
Civil Works - Buildings
Item Rate
240 days
Pattanakkad
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
₹50,000
2 Mar 2024
5 Feb 2024
13 Feb 2024
5 Feb 2024
12 Feb 2024
5 Feb 2024
Amount
Construction of building
15.3:Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
15.7.4:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar
5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.9.7:Centering and shuttering including strutting, etc. and removal of form for:Stairs, (excluding landings ) except spiral - staircases)
5.9.16.1:Centering and shuttering including strutting, etc. and removal of form for: Edges of slabs and breaks in floors and wallsUnder 20 cm wide
5.9.19:Centering and shuttering including strutting, etc. and removal of form for:Weather shade, Chajjas, corbels etc., including edges
5.22A.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
50.6.1.6:Solid block masonry using pre cast solid blocks (Factory made) of size 30x20x20cm or nearest available size confirming to IS 2185 part I of 1979 for super structure above floor two level upto floor five level thickness 20cm and above in : CM 1:6 ( 1 cement : 6 coarse sand sand) etc complete
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.16.1:6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
13.7.1:12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
OD356216/2023-2024:od127687/2019_2020 :Providing and laying in position machine batched and machine mixed design mix M-30 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. Note:- Cement content considered in this item is @ 340 kg/ cum. Excess or less cement used as per design mix is payable or recoverable separately.
GITHIN M G
Bidder Name
P N Gopalakrishnan
GITHIN M G
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .