| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 LAccepted-Finance HIMACHAL PRADESH HP | ₹1.9 L | L1 | Accepted-Finance QUOTED RATES AT LOWER SIDES. |
| 2 | L2₹2.0 L+₹11,340 (6.05%)Rejected-Finance HIMACHAL PRADESH HP | ₹2.0 L+₹11,340 (6.05%) | L2 | Rejected-Finance QUOTED RATES AT HIGHER SIDES. |
| 3 | L2₹2.0 L+₹11,340 (6.05%)Rejected-Finance VILLAGE BADHAL JEORI TEHSIL RAMPUR DISTT SHIMLA H P | ₹2.0 L+₹11,340 (6.05%) | L2 | Rejected-Finance QUOTED RATES AT HIGHER SIDES. |
Tender Value
₹1.9 L
EMD Value
₹4,650
Closing Date
12 Aug 2026, 3:30 pmClosed
ADDL. SE
ED, KAZA
Tender for Restoration of existing 22kV HT line at Various Location between Lidang to Kaza due to heavy Rainfall/landslide/shooting stone w.e.f. 21/07/2026 to 23/07/2026 in Electrical Section Kaza, under Electrical Sub- Division, HPSEBL, Kaza.
2026_HPSEB_140578_1
Kaza/ED/DB-Tender/2026-27/2
Open Tender
Supply and Erection
Percentage
7 days
kaza
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
₹4,650
18 Aug 2026
5 Aug 2026
13 Aug 2026
5 Aug 2026
12 Aug 2026
5 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismentalement Charges of 22kV HT line. | - | - | - | - |
| 2 | Dismentalement charges of ST poles D/Pole Str. (with complete accessories.) | - | Each | 1,652 | - |
| 3 | Dismentalement charges of ST poles S/Pole Str. (with complete accessories.) | - | Each | 826 | - |
| 4 | De-sagging of ACSR conductor 6/1/3.35mm. (Removal of conductor & De stringing only) | - | P/Km | 5,310 | - |
| 5 | Erection of 22kV H.T Line | - | - | - | - |
| 6 | Erection of pole.Digging of pit, (ii) Laying of RCC muff (iv) Erection of pole (v) fixing of insulator,X-arm, X-bracing set, (vi) fixing of Barbed wire, Danger plate (vii) filling of pit & Ramming D/Pole str. (Complete in all respect). | - | Each | 12,628.36 | - |
| 7 | Erection of pole.Digging of pit, (ii) Laying of RCC muff (iii) Drilling of holes in X-bracing set, X-arms (iv) Erection of pole (v) fixing of insulator,X-arm, Knee bracing set, Top Clamp (vi) fixing of Barbed wire, Danger plate (vii) filling of pit & Ramming i/c painting of pole S/Pole str. (Complete in all respect). | - | Each | 6,033.34 | - |
| 8 | Re erection/erection of stay set (HT). | - | - | - | - |
| 9 | Digging of pit, fixing of stay rod, filling of pit, Nozzeling & Tighting.) Complete in all respect. | - | P/set | 2,338.76 | - |
| 10 | SAGGING OF ACSR CONDUCTOR 6/1/3.35mm (Single wire). | - | - | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.50 MB
BOQ_208539.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .