TENALI MUNICIPALITY
Tenali
Construction of CC road at V Furniture mall road from JK Metal store to 7-3-45 in 36th ward of tenali municipality under AP CRDA Funds
980884
17/2026-27/AP CRDA FUNDS
OPEN - NCB
Civil Engineering Works
GUNTUR, ANDHRA PRADESH
7 documents required · 5 mandatory · 2 optional
₹300
₹8,453
27 Aug 2026
27 Aug 2026
27 Aug 2026
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202 MORD / MORTH.For existing ramps
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry, including disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202 MORD / MORTH for steps
Earthwork in excavation for roads as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH(Manual Means)
Sand Filling of foundation trenches as per drawing and technical specification in Clause 305.3.9 MORD & 304 MORTH
Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixture including cost and conveyance of all materials, labour charges, machine mixing charges, curing charges etc., complete as per S.S.
Providing concrete for plain/reinforced concrete (M15) in open foundations using 20 mm nominal size Graded hard stone aggregate , mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications of MORTH(For Drain Bed)
Providing Cemenet Concrete for plain/reinforced concrete (M15) using 20 mm size Graded hard stone aggregate , mechanically mixed, placed in position and compacted by vibration including curing etc., complete as per drawings and technical specifications and as Directed by the Departmental Authroties. (Culvert wall )
VRCC M-30 Nominal mix (Cement: fineaggregate: coarse aggregate) corresponding to Table 9 of IS 456 using 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges such as machine mixing, laying concrete, curing etc., complete but excluding cost of steel and its fabrication charges for finished item of work, but excluding centering, shutteing for culvert slabs
Vibrated cement concrete M 30 grade design mix using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, ting, curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification and as directed by the Engineer-in-Charge for C.C Pavement.
Providing High Yield Strength Deformed (HYSD)/ Thermo Mechanically Treated (TMT) / Mild steel (MS) steel bars (Fe 415 grade as per IS 1786-1979) of different diameters for RCC works , including labour charges for straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks of approved materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cutting, bending, placing in position, tying etc., complete for finished item of work as per SS and as Directed by the Departmental Authroties.( APSS No.126)
Supply of 25 mm thick high performance, expansion joint filler board ( SILFLEXCAPELL HD-100 or equivalent make), placing the same 25 mm below top of pavement slab, sealing with bituminous hot sealing compund (Grade 'A' ISI)/ polysulphide at 50 m interval in CC pavement including cost and conveyace of all materials and labour charges for placing in position for expansion joints conforming to MORTH specification . -1 Rmt of joint length I) 150 mm thick sla
Supply and placing Poly Sheet (separation membrane of impermeable sheeting) 125 Micron thick under CC Pavement slab including cost of conveyance etc. complete, including over head and contractors profit etc complete
Supply of Bitumenious hot sealing compound (Grade 'A' ISI) / polysulphide and sealing the joints including cost and conveyance of all material etc., including labour charges for placing in position for contraction joints at-4.50 M interval / for expansion joints/ for longitudinal joints Os per MORTH specification No. 602
Bailing out water from the trenches with oil engine driven pump sets, including hire charges, fuel charges and wages for Driver and Helper upto 5HP capacity pumps - 1 HP/Hr.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
document.doc
TENDER_DOCUMENT • 0.34 MB
Final BOQ.xlsx
TENDER_DOCUMENT • 0.81 MB
Final NIT.xlsx
TENDER_DOCUMENT • 0.02 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .