| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.7 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹13.3 L+₹63,940.80 (5.03%)Rejected-AOC | L2 | Rejected-AOC L2 |
Tender Value
₹12.7 L
EMD Value
₹31,772
Closing Date
15 Jun 2024, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
EXECUTIVE ENGINEER
O/o the Executive Engineer Irrigation Division Tvpm
GENERAL Upstream of KSRTC Urgent Restoration works of damaged portion of side wall at upstream of KSRTC bus stand in TVM corporation General Civil Work
2024_Irrig_674855_1
IRR/IA/TR/3613/2024_5_1_1/1
Open Tender
Civil Works - Others
Item Rate
30 days
thiruvananathapuram
Please refer Tender documents.
9 documents required · 9 mandatory
₹2,760
₹31,772
27 Jul 2024
10 Jun 2024
18 Jun 2024
10 Jun 2024
15 Jun 2024
10 Jun 2024
Amount
Reconstruction
15.9.1:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In Lime Mortar
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
60.1.1:RING BUND Type-I-Putting up ring bund as per approved shape 2.5m bottom width, 1m top width using empty gunny/polythene bags filled with earth placed in 2 rows at 0.6m apart and filled in between with puddle clay to form bund for an average height 2.00m including labour dismantling the bund after completion of the work etc. complete.
60.2.3:Bailing out water using pump above 5 HP and Up to 10 HP-Bailing out water with engine and pump set above 5HP and up to 10HP, including conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
60.7.2:DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
60.7.8:DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
7.1.1:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
60.6:PVC WEEP HOLES- Providing weep holes using 75mm dia. PVC pipes working pressure 4kg /sq.cm including cost of materials, conveyance, labour charges etc. complete.
OD4222/2024-2025:Desiltation/ Excavation by mechanical means(department/contractors own machine) over areas (exceeding 30cm in depth, 1.5m in width as well as 10sqm in plan)in or under water including getting out and disposal of removed excavated material combined with all deposited debris which comprises a mixture of organic and inorganic waste mixed with liquid mud, silt in any form without causing damages to environment or society, to government stockyard if available or otherwise on contractors own stockyard of choice including all leads and lift etc. complete as directed by departmental officers in charge.
OD4224/2024-2025: Removal of all floating organic and inorganic wastes such as cloth wastes, bottles, electronic wastes, electric wastes, wooden branches of trees, thermocols, hotel wastes, poultry waste, plastic wastes, kitchen utensils, leafs and other dumped wastes Using any type of departmental/ contractors own machinery including disposal of removed materials by the contractor at his own means without causing damage to environment and society including all leads lifts etc complete as departmental officers in charge.
OD4225/2024-2025:Engaging labour for removing wastes, clearing removed jungle and silt/clay from under side of slabs and for conveying waste from thodu to nearby road and labour for capping of unauthorized drainage lines to thodu etc
AJITH KUMAR M
Bidder Name
C SUBASH JOSE
AJITH KUMAR M
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1049519.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .