Loading…
Loading…
Tender Value
Refer Docs
EMD Value
₹50,000
Closing Date
29 May 2023, 3:00 pmClosed
Executive Engineer
P H Division South Observatory Hills Thiruvananthapuram
AMRUT 2.0 Replacing of 80mm AC pipe line to110mm PVC pipe 6kg cm2 works at Sankar Nagar Pappanamcode Pipeline Work
2023_KWA_576515_1
TR/4390/2022_26_1_1/1
Open Tender
Civil Works - Water Works
Item Rate
180 days
P H Division South
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,760
₹50,000
Yes
2 Aug 2023
15 May 2023
31 May 2023
15 May 2023
29 May 2023
15 May 2023
Amount
Appendix A pipe laying
15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road
15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
16.83:Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge.
16.84:Laying old cement concrete interlocking paver blocks of any design/ shape laid in required line, level, curvature, colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-in-charge. (Old CC paver blocks shall be supplied by the department free of cost.)
15.24:Demolishing dry brick pitching in floors, drains etc. including stacking serviceable material and disposal of unserviceable material with in 50 metes lead:
100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil.
100.8.1:Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
100.9.9:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 110 mm nominal outside diameter pipes.
100.98.1008:Engaging Coolie.
100.98.458:Supply of CI Double Flanged Sluice Valve Conforming to IS 14846 - 2000, Sluice Valve with Cap PN 1.6, Size 100mm.
100.31.1.2:Conveying and fixing C.I. sluice valves (with cap) by providing bolts, nuts, rubber insertions etc., complete, but excluding the cost of the valve (tail pieces, if required, will be paid separately): 100mm diameter, Class I.
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
OD26420/2023-2024:Conveying and fixing 25mm/40mm air valves to be put in PVC distribution line as per the direction of the departmental officers
OD26421/2023-2024:Interconnection with newly laid line with existing line with PVC/CI/DI Tee (12.5kg/cm2) and reducer CID/CIR joints (3 Nos) suitable to the newly line including cutting the existing line without damages to the line, bailing out water, traffic controlling cleaning and grinding the edges ready for joint including all labour charges cost of materials as per the direction of departmental officers
OD28537/2023-2024:Taking connection from the existing main (single boring), including earthwork excavation supplying and fitting 25mm saddle piece 1 nos,25mm brass ferrule 1 nos, 25mm GM full way valve wheel valve 1 nos, bend 1nos, union 1nos, 32mm pvc adapter 1 nos,110x32 pvc reducer 1nos etc. and connecting the newly laid main,testing the joints etc. complete
OD28538/2023-2024:Taking connection from the existing main (double boring), including earth work excavation ,boring the main, supplying and fitting saddle piece 2 nos,25mm brass ferrule 2 nos, 25mm GM full way valve wheel valve 2 nos, bend 2nos, union 2nos, 32mm pvc adapter 2 nos,110x32 pvc reducer 2nos and connecting the newly laid main testing the joint etc. complete. Rate as per item No 100.1.1 of SH KWA approved data
Appendix B, Construction of Valve Chamber
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
Appendix C
100.98.237:Supply of PVC Pipe, 10kg/cm2, 110mm Dia.
OD26392/2023-2024:Supplying 20mm ASTM Pipe
OD10794/2023-2024: Supplying and conveyingof heavy duty CI MH cover with frame
OD10788/2023-2024:110mm/10kg PVC 90degree bend
OD10789/2023-2024:110mm/10kg PVC 45 degree bend
OD10790/2023-2024:110mm PVC 22 1/2 degree bend
OD10791/2023-2024:110mm PVC 11 1/4 degree bend
OD10792/2023-2024:110mm/10kg PVC end cap
Appendix D
100.60.1.3.2:Providing 20mm (3/4 inch) house connection with 15mm (1/2 inch) water meter from existing PVC / HDPE mains up to 110 mm dia., up to a length of 5 m using 25mm Indian Standard Class 6 uPVC pipe and uPVC / GM / Brass specials viz. brass ferrule, GM full way wheel valve, Elbow, MTA, FTA, couplers, PVC Service Saddle of suitable size etc. and connecting with the mains, testing the joints etc. complete including trenching and refilling in all kinds of soil up to a depth of 1.50m for main line tracing and trench of average cross section 0.3m x 0.75m for laying connection pipe and service pipe, fixing water meter, lighting, watching, providing caution boards, traffic control etc. complete including cost of materials, hire for tools, cost of consumables and labour charges, including the cost of tested Class B Multijet water meter with ISI mark and weather resistant PP / PE meter box of minimum size 300mm x 200mm x 150mm, but excluding charges for cutting the concrete / tarred / bituminous roads etc, and as per the direction of the departmental officers.
100.60.3.2.1:Providing additional length of house connection pipe using 25mm Indian Standard Class 6 uPVC pipe and specials and testing the joints etc., by trenching and refilling in all kinds of soil with trench of average cross section 0.3m x 0.75m for laying of connection pipe and service pipe, lighting, watching, providing caution boards, traffic control etc., including cost of materials, hire for tools, cost of consumables and labour charges etc. complete, but excluding the cost of cutting of concrete / tarred / bituminous roads etc., and as per the directions of the department officers
100.60.12.4.1:Providing 15mm PVC Tap in the water meter assembly for 20mm connection, using 25mm Indian Standard Class 6 uPVC pipes and specials including cost of materials, consumables, hire charges for tools and labour charges etc. complete and as per the direction of departmental officers.
OD10801/2023-2024:Charges for geotagging to house connections
OD10798/2023-2024:Interconnection to newly laid main from distribution main/branchlines using suitable tee, reducer, CID/CIR joints and other specials etc.
OD10807/2023-2024:Alteration of house connection/street tap connection including earthwork excavation, supplying and fitting suitable saddle piece, supplying and fitting 20 mm brass ferrule 1no,20 mm GM full way wheel valve 1no,Tap ,20mm ASTM Sch-80 pipe and other specials, other specials etc. and connecting the newly laid line, testing the joints etc. as per the direction of departmental officials.
Appendix - E Road restoration of PWD roads
3.6:Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
4.1.B.1:Construction of granular sub-base by providing graded material, spreading in uniform layers with a motor grader on a prepared surface, mixing by mix in-place method with rotavator at OMC, and compacting with a vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub-base cum drainage layer - Mix in Place Method
4.12:Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
5.1.a:Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.
5.2.a:Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.
5.3.2.a:Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with a bituminous binder (VG 30), transported to the site, laid over a previously prepared surface with paver finisher to the required grade, level, and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction For Grading II - (19 mm nominal size)
5.6.2.a:Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with a bituminous binder( NRMB) @ 5.4 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level, and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects For Grading - II (13.2 mm Nominal Size)
8.13:Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads on Bituminous Surface @ 250 gms per sqm area, the thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform, and free from streaks and holes.
8.35:Providing and fixing reflective road studs (Raised Pavement Marker) of ' category A' made out of ASA/HIPS/ABS moulded body with shanks and conforming to ASTM D 4280, strong enough to support a load of more than 13.635 T when tested in accordance with ASTM D 4280, reflective panel confirming to ASTM D 788, and reflectivity conforming to clause 804.4. including installation, drilling, fixing with adhesive etc. with 2 years warranty for the road stud as well as for in field performance as per clause 804.7.3<br> Road Markers/Road Stud with Lense Reflector :-
3.17:Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2.
Appendix - E Road restoration of LSGD roads
11.1.1.1:Excavation for Structures <br> Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. <br> I. Ordinary soil <br> (i) Upto 3 m depth
4.11.1:Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408. <br> (i) Using naturally occuring gravel
4.9:Wet Mix Macadam <br> Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. <br> By Mechanical Means with 1 km lead
5.2.1a:Tack Coat<br> Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
75.8.1:Providing Plain cement concrete for road work CC 1:2:4 (1 cement: 2 fine aggregate: 4course aggregate) laid to required slope and camber in panels (@ 3 m c/c) as requiredincluding compaction, finishing and tamping etc .complete. Max. size of courseaggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification (i) Nominal mix (1:2:4)
3.2:Preparation of Foundation for Embankment <br> Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Means <br> Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4.
ANIL R
Bidder Name
Prakash
ANIL R
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .