| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 CrAccepted-AOC | ₹1.6 Cr | L1 | Accepted-AOC Agreement Executed and work awarded |
| 2 | L2₹1.9 Cr+₹32.2 L (20.2%)Rejected-AOC | ₹1.9 Cr+₹32.2 L (20.2%) | L2 | Rejected-AOC Agreement Executed and work awarded |
| 3 | L3₹2.0 Cr+₹36.6 L (23.0%)Rejected-Finance | ₹2.0 Cr+₹36.6 L (23.0%) | L3 | Rejected-Finance Lowest bid accepted |
| 4 | L4₹2.0 Cr+₹39.9 L (25.1%)Rejected-Finance | ₹2.0 Cr+₹39.9 L (25.1%) | L4 | Rejected-Finance Lowest bid accepted |
Tender Value
₹2.1 Cr
EMD Value
₹1 L
Closing Date
9 Apr 2025, 3:00 pmClosed
Superintending Engineer
Buildings North Circle Kozhikode PWD Complex Mananchira Kozhikode
Construction of compound wall balance work
2025_PWD_756192_1
PWD/BLDG/15308/2024-2025
Open Tender
Civil Works - Buildings
Item Rate
360 days
medical college kozhikode
Please refer Tender documents.
10 documents required · 10 mandatory
₹8,270
Yes
₹1 L
Yes
27 May 2025
28 Mar 2025
11 Apr 2025
28 Mar 2025
9 Apr 2025
28 Mar 2025
Amount
Detailed Estimate
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
OD268184/2024-2025:Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.9.2:Centering and shuttering including strutting, etc. and removal of form for:Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.6.7.2:Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc.
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
4.3.3:Centering and shuttering including strutting, propping etc. and removal of form work for:Columns, piers, abutments, pillars, posts and struts
16.18.1:Fencing with angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 metres (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for serarately) :- Payment to be made per metre cost of total length of barbed wire used.With G.I. barbed wire
16.19:Supplying at site Angle iron post & strut of required size including bottom to be split and bent at right angle in opposite direction for 10 cm length and drilling holes upto 10 mm dia. etc. complete.
13.46.1:Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm)
OD212657/2024-2025:PVC WEEP HOLES- Providing weep holes using 110 mm pipe . PVC pipes working pressure 6 kg /sq.cm including cost of materials, conveyance, labour charges etc. complete. ( Similar to DSR 60.6)
OD268307/2024-2025:Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. All work up to plinth level Note: Excess or less cement used as per mix design is not payable or recoverable separately
OD268308/2024-2025:Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is not payable or recoverable separately. All work above plinth level upto floor V level
5.22A.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
AK.DINESHAN (BID ID -2192028)
ASHRAF PT (BID ID -2192235)
PURAYIL GROUP CONSTRUCTION (BID ID -2192729)
Bidder Name
AK.DINESHAN
Santhosh Kumar K.V.
PURAYIL GROUP CONSTRUCTION
ASHRAF PT
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1228145.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .