| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.0 LAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | L2₹5.0 L+₹5,325 (1.07%)Admitted-Finance | L2 | Admitted-Finance | |
| 3 | L3₹5.3 L+₹26,995 (5.42%)Admitted-Finance | L3 | Admitted-Finance |
| Sl No | Description | Qty | Unit | SAROJ CONSTRUCTION L3 | PARAS ENTERPRISES L2 | SARTAJ TRADERS L1 |
|---|---|---|---|---|---|---|
| 1.00(A) Carrieage Carriage of the follwing material from Electricity store centre, Bahraich to the work site/dump site. | ||||||
| 1.01 | PCC/STP Pole (size 8.5/9/11 Mtr. Long) | 110 | Nos. | 991 ₹1,09,010 Lowest | 1,450 ₹1,59,500 | 1,050 ₹1,15,500 |
| 1.02 | AB Cable of different size | 1 | Km. | 1,375 ₹1,375 Lowest | 6,000 ₹6,000 | 1,500 ₹1,500 |
| 1.03 | ACSR conductor | 1 | Km. | 1,360 ₹1,360 Lowest | 4,500 ₹4,500 | 2,000 ₹2,000 |
| 1.04 | Other line material | 12 | Qtl. | 1,000 ₹12,000 Lowest | 2,000 ₹24,000 | 1,500 ₹18,000 |
| 2.00(B) Erection 1. Any kind of fabrication work including hole in X-arm/clamp etc. shall be done by the contractor at his own cost. 2. Fastner including suitable size of washer shall be provided and erected by the contractor at his own cost. | ||||||
| 3.00 | Erection of single PCC/ST Poles alongwith fitting of all accessories on pole. (size 8.5/9/11 Mtr. Long) | 90 | Nos. | 1,750 ₹1,57,500 Lowest | 1,750 ₹1,57,500 Lowest | 1,900 ₹1,71,000 |
| 4.00 | Erection of sectional double PCC/STP pole alongwith fitting of all accessories. (size 8.5/9/11 Mtr. Long) | 10 | Nos. | 3,700 ₹37,000 | 6,500 ₹65,000 | 3,600 ₹36,000 Lowest |
| 5.00 | Erection and Grouting of stay sets alongwith complete fittings. Cement, Sand & Brick ballast provided by the contractor at his own cost. | 20 | Nos. | 950 ₹19,000 | 750 ₹15,000 | 550 ₹11,000 Lowest |
| 6.00 | Grouting of Poles with 1:4:8 CC ratio of cement, sand & brick ballast, backfilling of pits with mud completely. All required materials provided by the contractor at his own cost. (size 8.5/9/11 Mtr. Long) | 50 | Nos. | 825 ₹41,250 | 390 ₹19,500 Lowest | 550 ₹27,500 |
Tender Value
₹5 L
EMD Value
₹5,000
Closing Date
12 Nov 2026, 2:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Superintending Engineer
33/11 KV Sub Station, Hospital Chauraha, Bahraich
Work related to the maintenance and repair of broken HT/LT power lines and poles, and other associated tasks, to ensure uninterrupted power supply in the EDSD-Ranjeetpur areas.
2026_MVVNL_1196862_2
62/EDC(B)/2026-27
Open Tender
Electrical Works
Item Rate
90 days
Bahraich
Please Refer Tender Form
2 documents required · 2 mandatory
₹1,180
Superintending Engineer, EDC
₹5,000
21 Nov 2026
4 Nov 2026
12 Nov 2026
4 Nov 2026
12 Nov 2026
4 Nov 2026
90 days
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1(A) Carrieage Carriage of the follwing material from Electricity store centre, Bahraich to the work site/dump site. | |||||
| 1.01 | PCC/STP Pole (size 8.5/9/11 Mtr. Long) | 110 | Nos. | 100 | ₹11,000 |
| 1.02 | AB Cable of different size | 1 | Km. | 10 | ₹10 |
| 1.03 | ACSR conductor | 1 | Km. | 10 | ₹10 |
| 1.04 | Other line material | 12 | Qtl. | 10 | ₹120 |
| 2(B) Erection 1. Any kind of fabrication work including hole in X-arm/clamp etc. shall be done by the contractor at his own cost. 2. Fastner including suitable size of washer shall be provided and erected by the contractor at his own cost. | |||||
| 3 | Erection of single PCC/ST Poles alongwith fitting of all accessories on pole. (size 8.5/9/11 Mtr. Long) | 90 | Nos. | 10 | ₹900 |
| 4 | Erection of sectional double PCC/STP pole alongwith fitting of all accessories. (size 8.5/9/11 Mtr. Long) | 10 | Nos. | 10 | ₹100 |
| 5 | Erection and Grouting of stay sets alongwith complete fittings. Cement, Sand & Brick ballast provided by the contractor at his own cost. | 20 | Nos. | 10 | ₹200 |
| 6 | Grouting of Poles with 1:4:8 CC ratio of cement, sand & brick ballast, backfilling of pits with mud completely. All required materials provided by the contractor at his own cost. (size 8.5/9/11 Mtr. Long) | 50 | Nos. | 10 | ₹500 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.49 MB
Re_Form62.pdf
Tender Documents • 0.59 MB
BOQ_2283891.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .