| Sl No | Description | Qty | Unit | RAJU KC L1 | Subin M P L2 |
|---|---|---|---|---|---|
| 1.00RETARRING | |||||
| 1.00 | 2.14.2.A:Dismantling of Flexible Pavements Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking serviceable and unserviceable materials separately as per Technical Specification Clause 202 (II) By Mechanical Means (A) Bituminous Courses | 34.4 | cum | 424.2 ₹14,594.18 Lowest | 500 ₹17,202 |
| 1.00 | 3.5.3:Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 | 33 | cum | 51.02 ₹1,683.66 Lowest | 100 ₹3,300 |
| 1.00 | 4.1.A.2:Granular Sub-base with Well Graded Material (Table 400.1)(A) By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. (ii) For Grading II Material | 10.32 | cum | 3,170.13 ₹32,715.74 Lowest | 3,500 ₹36,120 |
| 1.00 | 4.9:Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. By Mechanical Means with 1 km lead | 155.03 | cum | 3,504.6 ₹5,43,300.62 Lowest | 3,800 ₹5,89,095 |
| 1.00 | 75.5.1.1pb:Prime Coat - Low porosity - With Packed Bitumen Rates Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 | 1,823.4 | sqm | 80.21 ₹1,46,254.91 Lowest | 100 ₹1,82,340 |
| 1.01 | 75.5.2.3pb:Tack Coat - With Packed Bitumen Rates Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503. | 1,823.4 | sqm | 18.75 ₹34,188.75 Lowest | 20 ₹36,468 |
| 1.01 | 75.5.5.B.2pb:Modified Penetration Macadam 75 mm thick using Bitumen S-65 - Packed Bitumen Rates Construction of penetration macadam over prepared base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a three wheel 80-100 kN static roller to achieve the desired degree of compaction as per Technical Specification Clause 506. | 106.14 | sqm | 387.05 ₹41,081.49 Lowest | 400 ₹42,456 |
| 1.01 | 75.5.2.1pb:Tack Coat - With Packed Bitumen Rates Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503. | 678.6 | sqm | 15.65 ₹10,620.09 Lowest | 20 ₹13,572 |
| 1.01 | OD406782/2025-2026:Mixseal surfacing manual means type A Bitumen s 65 using shredded plastic
prividung laying and rolling of closegraded premix surfyfacing materialof 20mm
thickness composed of 1.2 mm to 0.90mm (type A )or 13.2mm to 0.9 mm
(typeb)aggregate coated with shredded plastic (3%by weight of bitumen)as per
standard procedure using penetration grade bitumen to required line grade and level to
serve as wearing course on a previously prepared base ,including mixing in a suitable
plant , laying abd rolling with a three wheel 8-10kn static roller and finishing to
required level and grade as per tecnical specification clase 509by mann=ual means
typeA (ll)bitumen (S-65) | 2,502 | sqm | 273.58 ₹6,84,497.16 Lowest | 290 ₹7,25,580 |
Tender Value
₹16.1 L
EMD Value
₹40,188
Closing Date
3 Feb 2026, 2:00 pmClosed
Assistant engineer LID and EW section Pattiam
o/o Assistant Engineer LID and EW section Pattiam
PATTIAM GP CANAL PANCHAYATH ATHIR AARAM MILE ROAD IMPROVEMENTS
2026_LSGD_830891_3
AE/LSGD PATTIAM/25-26/9
Open Tender
Civil Works - Roads
Item Rate
120 days
Pattiam
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
₹40,188
20 Feb 2026
27 Jan 2026
4 Feb 2026
27 Jan 2026
3 Feb 2026
27 Jan 2026
RETARRING
2.14.2.A:Dismantling of Flexible Pavements Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking serviceable and unserviceable materials separately as per Technical Specification Clause 202 (II) By Mechanical Means (A) Bituminous Courses
3.5.3:Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3
4.1.A.2:Granular Sub-base with Well Graded Material (Table 400.1)(A) By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. (ii) For Grading II Material
4.9:Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. By Mechanical Means with 1 km lead
75.5.1.1pb:Prime Coat - Low porosity - With Packed Bitumen Rates Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
75.5.2.3pb:Tack Coat - With Packed Bitumen Rates Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause 503.
75.5.5.B.2pb:Modified Penetration Macadam 75 mm thick using Bitumen S-65 - Packed Bitumen Rates Construction of penetration macadam over prepared base by providing a layer of compacted crushed coarse aggregate using chips spreader with alternate applications of bituminous binder and key aggregates and rolling with a three wheel 80-100 kN static roller to achieve the desired degree of compaction as per Technical Specification Clause 506.
75.5.2.1pb:Tack Coat - With Packed Bitumen Rates Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
OD406782/2025-2026:Mixseal surfacing manual means type A Bitumen s 65 using shredded plastic prividung laying and rolling of closegraded premix surfyfacing materialof 20mm thickness composed of 1.2 mm to 0.90mm (type A )or 13.2mm to 0.9 mm (typeb)aggregate coated with shredded plastic (3%by weight of bitumen)as per standard procedure using penetration grade bitumen to required line grade and level to serve as wearing course on a previously prepared base ,including mixing in a suitable plant , laying abd rolling with a three wheel 8-10kn static roller and finishing to required level and grade as per tecnical specification clase 509by mann=ual means typeA (ll)bitumen (S-65)
75.8.1.1:Providing plain/reinforced concrete(1 cement:2 fine aggregate: 4 course aggregate) forsubstructure as per drawings and technical specifications Clause 802, 803, 1202 & 1203as required including compaction, finishing and tamping etc .complete. Max. size ofcourse aggregate not exceeding 25mm , mixed in concrete mixer etc complete as perspecification (i) Nominal mix (1:2:4)
10.14:Tubular Steel Railing on Medium Weight Steel Channel (ISMC series) 100 mm x 50 mm Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 m high above ground, 2 m centre-to-centre, complete as per approved drawings Clause 1706
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.16 MB
BOQ_1396115.xls
BOQ • 0.31 MB
NIT.pdf
Tender Documents • 0.02 MB
PRELIMINARY.pdf
Tender Documents • 0.14 MB
BIDdoc.pdf
Tender Documents • 1.69 MB
AFFIDAVIT.pdf
Tender Documents • 0.11 MB
FORMOFTENDER.pdf
Tender Documents • 0.13 MB
INTEGRITY.pdf
Tender Documents • 0.10 MB
EPAYMENT.pdf
Tender Documents • 0.11 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .