| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.9 CrAccepted-AOC | ₹7.9 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹9.6 Cr+₹1.7 Cr (22.1%)Rejected-Finance | ₹9.6 Cr+₹1.7 Cr (22.1%) | L2 | Rejected-Finance L2 |
Tender Value
₹7.9 Cr
EMD Value
₹15.8 L
Closing Date
1 Feb 2023, 5:00 pmClosed
Superintending Engineer
Office of the Superintending Engineer, Construction Circle, Uttarakhand PeyJal Nigam, Almora.
Civil Work-water works, Electrical and mechanical works
2023_MDPEY_54072_1
87/NIVIDA QUOTATION/1, DATE 16/01/2023
Open Tender
Civil Works - Water Works
Item Rate
365 days
Block-Syalde in District-Almora.
Please Refer to Tender Documents
3 documents required · 3 mandatory
₹5,900
EE, Construction Division, UKPJN, Bhikiyasain.
₹15.8 L
Construction Circle, UKPJN, Almora.
18 Aug 2023
18 Jan 2023
3 Feb 2023
18 Jan 2023
1 Feb 2023
20 Jan 2023
20 Jan 2023
Amount
Providing of all materials, carting from site store to site of work , lowering into trenches with true to alignmen, laying of APL-5L, Jointing by electric welding process with proper grade of electrodes suitable for jointing of water supply lines ( Ador, L&T or equivalent electrodes) by cutting of pipes and making required bends by welding, completion of work with testing of pipe line etc complete.
From Infiltration Well-1 to MPS API pipe 125 mm Dia 4.0 MM Thickness
From Infiltration Well-1 to MPS API pipe 125 mm Dia 4.8 MM Thickness
From IPS to Top CWR API pipe 100mm Dia 4.4mm Thickness
Survey, design (The contractor has to survey the site, take levels with total station, measure the length of pipe with metalic tape on prescribed alignment and submit the design of Supply Main for checking the dia of pipe before ordering for supply of pipe. On completion of this work, the laid length of pipe will be deemed eligible for supply. The respective amount for quantity of surplus supply of pipes (which remained unlaid or unutilized) will be deducted from final bill and surplus quantity of pipes will be the property of contractor),, Supply main/Distribution ,carting to site of work, laying to true alignment & jointing of GI (Medium) Screwed pipes conforming to latest BIS code (including supply of all jointing materials like specials, white lead, hemp and oil etc.) in trenches with its cutting, threading and testing of pipe line etc. complete for the following dia:
Excavation of earth for Pipe Line trenches of Clear Water Rising/ Feeder / Supply Main/ Distribution system in following strata requiring the use of special T&P such as Pick Axes, Sabbals etc. or by blasting or by crow bars with a lift up to 1.5 m and lead upto 30 m including refilling, watering and ramming of excavated earth into the trenches and removal and disposal of surplus earth upto a distance of 60 m from the trenches including supply of all materials, labour, T&P etc. complete assuming that 90% Pipeline is laid in trenches & also it is estimated that 75% trenches will be in soil mixed with shingle, bazri, boulder and rest of 25% will be in medium rock.
Soil mixed with boulder and bajri
Same as above but in medium rock by chiseling.
Design, testing bearing capacity of soil (For CWR more than 25 KL capacity only) and construction of M 30 grade R.C.C. semi-sunk circular Service Reservoir of following capacity and other appurtenant works including supply of necessary scaffolding, shuttering and other accessories along with construction of valve chambers, fixing of inlet and outlet pipes, making bye pass arrangement & fixing of lightening conductor & M.S. Manhole Cover, supply and fixing of M.S. Steel Ladder outside and inside the tank and fixing of railing around top dome as per approved design of R.C.C. tank in latest IS codes including painting with delux multi surface paint and also connection with the exsiting network alongwith carting of all materials including supply & fixing of Bucket Type Chlorinator 25 L capacity on top of service reservoirs including supply of all materials, labour, T&P etc. complete and constructing chlorinator over CWR capacity 50 KL or more
Painting of API/ MS ERW Pipes with 2 coats of approved quality. (Anti-Corrosive) epoxy paint over one coat of Primer
Provision of Barbed Wire Fencing through angle iron posts of size 50x50x6mm and height of post 1.8m weight of wire not less than 9.38 kg per 100m and spacing of row 20 cm c/c barbed wire shall be cross diagonaly of post around the water works site, on the top of Boundary Wall as per specifications including all materials, labour etc. complete.
Provide all materials, labour, T & P for Construction of 3.60 m wide MS Iron Gate (Not less than 100 Kg.) with two nos. 2- brick thick brick masonry Pillars 2.00 m high and 30 cm below ground level in 2 and half brick masonry over 10 cm thick PCC 1:4:8 ( 1 cement, 4 sand and 8 stone aggregate). Pillars to plastered all over in 1:4 Cement and Sand mortar , complete with two or more coats of synthetic enamelled paint over a coat of steel primer on steel work and acrylic smooth exterior paint for pillars.
Supply and fixing of following size of heavy duty Cast Steel Sluice / Scour / Gate Valve confirming to API 600 for Clear Water Rising Main including cartage of materials (Kirloskar, Jayant, Butterfly or Oswal make)
100mm dia WP 30 kg/sqcm
125mm dia WP 50 kg/sqcm
Supply and fixing of following size of heavy duty Cast Steel Reflux Valve (Swing Check Type) conforming to IS code for Clear Water Rising Main including cartage of materials (Kirloskar, Jayant, Butterfly or Oswal make).
100mm dia WP 30 kg/sqcm
125mm dia WP 30 kg/sqcm
Supply and fixing of following size of Air Valve confirming to API Standard including cartage of materials.For Clear Water Rising Main
80 mm dia. heavy duty Cast Steel Double Orifice type WP 30 kg/sqcm
Supply and fixing of following size of wheel/ Gate Valve as per IS:778 :1997 & IS 14846:2000 for feeder Main /Supply main /distribution including cartage of materials.
20 mm dia (PN 1.0 / 1.6)
25 mm dia (PN 1.0 / 1.6)
32 mm dia (PN 1.0 / 1.6)
40 mm dia (PN 1.0 / 1.6)
50 mm dia (PN 1.0 / 1.6)
65 mm dia (PN 1.0 / 1.6)
Construction of following Valve chamber in R.C.C. 1:1.5:3 with necessary reinforcement along with fixing of manhole cover on top for Feeder / Supply Main/ Distribution System including supply of all materials, labour, T&P etc. complete required for proper completion of work.
Sluice/ Reflux/ Scour/ Air Valve Chamber 1.2m x1.2m x 1.2m
Wheel Valve/Gate Valve/Water meter/ Air Valve Chamber 0.6m x 0.6m x 0.6m
Supply of all materials, labour, T & P etc and construction of RCC 1:1.5:3 Break Pressure Tank (1 m x1 m x1 m )as per departmental type design .
Construction of Anchor Block in R.C.C. 1:1.5:3 size 1m x 1m x 1m with necessary reinforcement along the alignment of Clear Water Rising Main including supply of all materials, labour, T&P etc. complete as per type design as per direction of engineer incharge including cartage of materials. size of thrust block at spacing of 100 m each from pump to half length of top CWR.
Supply ,carting,fixing of Clamp (5mm thick MS Flat) for verious size of pipes with nut,bolts,anchors and grouting materials Etc. All complete.
Up to 20 mm to 40mm dia
Up to 50 mm to 80mm dia
Construction of protection works for Site Development, source work, Rising Main, Supply Main, CWRs, Distribution system and Buildings etc. as per site conditions wherever necessary as follows :-
Excavation in following strata for foundation requiring the use of special T&P such as Pick Axes, Sabbals etc. or by blasting or by crow bars with a lift up to 1.5 m and lead upto 30 m including refilling, watering and ramming of excavated earth into the trenches and removal and disposal of surplus earth upto a distance of 60 m including supply of all materials, labour, T&P etc. complete including cartage of materials in soil mixed with shingle, bazri, boulder
Cement concrete 1:4:8 including supply of all materials, labour, T&P etc. complete.
Random Rubble Stone Masonry in 1:6 cement and sand mortar including supply of all materials, labour, T&P etc. complete.
Random Rubble Stone Masonry laid dry including supply of all materials, labour, T&P etc. complete.
Cement concrete 1:2:4 including supply of all materials, labour, T&P etc. complete.
Water meters conforming to IS 779-1994 Class A (Multi Jet water meter) of following sizes
25 mm diameter
Repairing work of existing structures as per directed by engineer in charge in all respects.
Repairing of Infiltration well including supply of all materials, labour, T&P etc. required for proper completion work.
Supply of all materials, labour and T&P etc. and repairing of Pump House as per type design and drawing.
Supply of all materials, labour and T&P etc. and repairing of Staff Quarter for Chaukidar as per type design and drawing.
Provision of 1.5m high boundary wall in brick masonary with cement sand mortar (1:6) including supply of all materials, labours T&P etc complete.
Making ferrule connection in the existing main of G.I,A.c,PVC or any type of pressure mains with saddle piece, service connections fittings and fixing of G.M ferrule including tapping the main, including all materials, ferrule, clamp etc. and bib cock.
PART-B (ELECTRICAL AND MECHANICAL WORKS) Pumping Plant for for Stage -I (Existing Infiltration Well Submersible clear water Pump (700 LPM, 35 M Head)
Starter
main switch 100Amps
Control Panel
Power Wiring & Earthing Material
Main Piping & Valves
Gauges
Chain Pulley Block (1.5 Tonne capacity)
Stage-II: (IPS-1 to IPS-2): Centrifugal Pump (700 LPM, 320 M Head)
Electric Motor
Main switch 400Amps
Base Plate
Fully Auotomatic Auto Transformer Starter
Control Panel
Power Wiring & Earthing Material
Main Piping & Valves
Gauges
H.O.T crane 3Tonne Capacity
Stage-III: (IPS-2 to CWR) Centrifugal Pump (450LPM, 365 M Head)
Electric Motor
315 Amp main switch
Base Plate
Fully Auotomatic Auto Transformer Starter
Control Panel
Power Wiring & Earthing Material
Main Piping & Valves
Gauges
Chain Pulley Block (3 Tonne capacity)
Tools for all stages
150mm dia Bulk Head Water Meter
Rubber Resistance Sheet (1×2×0.025 M)
Transformer oil (1 Drum=209 Ltrs)
Installation & commissioning of Pumping Plants & related acceessories for all stages.
Testing (all stages) : (i) At Works
(ii) At Site
Painting (all stages)
Carting for all stages
Maintenance (one year) (all stages)
S.I.T.C. of Transformer
(i) Stage-II) (250 KVA)- 2 Nos.
(iii) Stage-III) (160 KVA)- 2 Nos.
S.I.T.C. of H.T. Panel
(i) Stage-I (MPS) - 1No.
(ii) Stage-II (IPS) - 1No.
SHIVRAJ BANAULA
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .