Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.1 CrAdmitted-Finance | -14.57% | ₹1.1 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.2 CrAdmitted-Finance | -9.30% | ₹1.2 Cr | L2 | Admitted-Finance |
| 3 | L3₹1.2 CrAdmitted-Finance | -4.10% | ₹1.2 Cr | L3 | Admitted-Finance |
Tender Value
₹1.3 Cr
EMD Value
₹2.6 L
Closing Date
11 Aug 2026, 6:00 pmClosed
Secretary KDA Kota
KDA KOTA
RENOVATION WORK IN MAHARAJA SURAJ MAL SAMUDAYAK BHAWAN SECTOR 4 MAHAVEER NAGAR THIRED AT WARD 70
2026_UITKo_581103_1
16/2026-27 (53)
Open Tender
Civil Works
Percentage
120 days
Kota
Please refer Tender documents.
2 documents required · 2 mandatory
₹3,500
OnlineSSO Portal
₹2.6 L
Yes
17 Aug 2026
5 Aug 2026
12 Aug 2026
5 Aug 2026
11 Aug 2026
5 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge: In cement mortar. | 72 | Cum | 641 | ₹46,152 |
| 2 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils | 250.13 | Cum | 178 | ₹44,522.78 |
| 3 | Random Rubble stone masonry for with hard stone in foundation and plinth in Cement Sand mortar above 30 CM thick wall in:Cement Mortar 1:6 ( 1-Cement : 6-Sand). | 238.28 | Cum | 2,838 | ₹6,76,224.45 |
| 4 | Random Rubble stone masonry with hard stone in superstructure above plinth level and upto five level above 30cm. thick walls in : Cement Mortar 1:6 ( 1-Cement : 6-Sand). | 70.88 | Cum | 3,479 | ₹2,46,574.13 |
| 5 | Providing and laying in position specified grade of cement concrete for all RCC structural elements upto plinth level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers( if required) excluding the cost of centering, shuttering and reinforcement. 20 grade Nominal Mix / Design Mix | 71.07 | Cum | 4,934 | ₹3,50,644.58 |
| 6 | Providing and laying in position specified grade of cement concrete for RCC structural elements upto floor five level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers (if required ) excluding the cost of centering, shuttering and reinforcement for Walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc.
M20 grade Nominal Mix / Design Mix | 28.8 | Cum | 5,609 | ₹1,61,539.2 |
| 7 | Providing and laying in position specified grade of cement concrete for RCC structural elements upto floor five level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers( if required) excluding the cost of centering, shuttering and reinforcement for Beams, suspended floors, roofs, griders having slopes up to 15º, landings, balconies, shelves, chajjas, lintels, bands, plain windows sills, staircases and spiral staircases etc.
M20 grade Nominal Mix / Design Mix | 92.7 | Cum | 5,185 | ₹4,80,649.5 |
| 8 | Centering and Shuttering with plywood or steel plate including strutting, propping bracing both ways and removal of formwork for foundation , footings, strap beam, raft , bases of columns etc. | 883.26 | Sqm | 157 | ₹1,38,671.82 |
| 9 | Centering & shuttering with plywood or steel sheets including strutting, propping bracing both ways with steel props and removal of formwork for upto floor five level for : Columns, pillars, posts and struts etc. | 222 | Sqm | 375 | ₹83,250 |
| 10 | Centering & shuttering with plywood or steel sheets including strutting, propping bracing both ways with steel props and removal of formwork for upto floor five level for : Columns, pillars, posts and struts etc. Suspended floors, roofs, landings, staircases, balconies, girders, cantilevers, bands, coping bed plates, anchor blocks, sills, chhajjas, lintel, beam, plinth beam etc. | 438 | Sqm | 340 | ₹1,48,920 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.88 MB
BOQ_1032632.xls
BOQ • 0.49 MB
Condition_53.pdf
Tender Documents • 0.43 MB
Corrigendum_16_Date.pdf
PDF • 0.15 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].